Hi
Can anyone give an update to any news of progress on the electrification of the Wales and West country line?

Thanks
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

PhilipW

Member
Joined
6 Feb 2008
Messages
756
Location
Fareham, Hants
No further news really to that already announced.

Electrification to Newbury, Didcot and Oxford is due for completion by 2016 and that to Bristol and Cardiff approx 2 years later. Don't expect to see much visible indication such as masts being erected for some time yet. The most visible evidence will be in the rebuilding of bridges to allow OHLE underneath.

In Wales the wires are still planned to stop at Cardiff. I personally think that there will be a change of mind and electrification will be extended to Swansea (but who knows).

If you area asking about further electricifaction to the West of England, that's something for way into the future. Ask again in 10 years time. Network Rail have their hands fuil at the moment with the current plans and the probable Valley Lines electrification around 2018-20.
 
Last edited:
Joined
12 Jan 2011
Messages
17
Location
London SE23
This may have been covered on another thread, but if electrifications of the Hants & Berks will not extend further west than Newbury what will happen to the current semi-fasts to Bedwyn?
 

anthony263

Established Member
Joined
19 Aug 2008
Messages
6,531
Location
South Wales
This may have been covered on another thread, but if electrifications of the Hants & Berks will not extend further west than Newbury what will happen to the current semi-fasts to Bedwyn?

That is something I have been thinking about it would be better if the wires were extended beyond Newbury to say Westbury to cover the semi fast Bedwyn - London services which could be extended to/from Westbury if possible and stock is avilable.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,382
Bedwyn will potentially be served by an additional semifast IEP service each hour that goes as far as Westbury or Taunton.

It is all described in the GWML RUS, and a few previous threads in RailUK...
 

Zoe

Established Member
Joined
22 Aug 2008
Messages
5,905
Bedwyn will potentially be served by an additional semifast IEP service each hour that goes as far as Westbury or Taunton.
The franchise consultation says hourly to Westbury with some extensions to Exeter and one train per day to Paignton.
 