Great Western Electrification Progress

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Railperf

Established Member
Joined
30 Oct 2017
Messages
2,942
Am I right in thinking that it is unlikely the 387's would be authorised to run through Steventon until a fully electrified solution were found because they do not have diesel mode to fall back on? It is conceivable they could be allowed to coast through that section but wouldn't that require some kind of special working arrangements to ensure that they have a clear run through this effectively long neutral section?
 

Sean Emmett

Member
Joined
9 Mar 2015
Messages
498
Am I right in thinking that it is unlikely the 387's would be authorised to run through Steventon until a fully electrified solution were found because they do not have diesel mode to fall back on? It is conceivable they could be allowed to coast through that section but wouldn't that require some kind of special working arrangements to ensure that they have a clear run through this effectively long neutral section?
Or the mooted 60 mph PSR for all electric traction?

Any news re when electric working eastbound from Swindon will recommence? At Temple Meads at mo hoping to experience the sparks effect!
 

JN114

Established Member
Joined
28 Jun 2005
Messages
3,354
Am I right in thinking that it is unlikely the 387's would be authorised to run through Steventon until a fully electrified solution were found because they do not have diesel mode to fall back on? It is conceivable they could be allowed to coast through that section but wouldn't that require some kind of special working arrangements to ensure that they have a clear run through this effectively long neutral section?

It includes 2 level crossings so it’s unlikely coasting will be allowed due to the likelihood a train may have to be stopped in the dead section.
 

Phil G

Member
Joined
16 Oct 2017
Messages
178
Well after a weeks holiday I checked my train times today to find the 8:17 from Chippenham to Temple Meads has moved to 08:22 but still 07:00 from Paddington - My first reaction was that now the power is on to Swindon that's a bit of a shame to lose 5 mins! However when I looked at RTT i realise it must be temporary due to the Filton bank blockade as a diverted XC service actually passes at 8:17! Unfortunate coincidence with the turning on of AC!
 

3973EXL

Established Member
Joined
2 Feb 2017
Messages
2,446
Catch-up on a few bits and pieces around Reading West.

Droppers have now been adjusted.
DSC01570.JPG

No further work on the platform extension or Tilehurst Rd parapets.
DSC01569.JPG DSC01572.JPG DSC01568.JPG

New camera of some sort on the up platform.
DSC01571.JPG
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,493
Location
Between Peterborough & Bedlington
GWML Electrification: State of Play, as of 5/11/18.
All mileages given from Paddington, except where noted.
Paddington to Wootton Bassett Jct - LIVE
  • All main line tracks wired as far as Wootton Bassett Jct, and are to be considered "live" as such. The envelope of "live" wires continues along the South Wales Main Line to Filton Jct (inc. Bristol Parkway), and to the Limits of Wiring on the Berks & Hants line and Reading-Basingstoke Line; details are given below.
  • TTCs have replaced/been replacing headspans at various locations within London - locations include Westway (beneath the A40), Acton Main Line, Ealing Broadway, and between Southall & H&H. These are part of the works for the Elizabeth Line.
  • Everything wired at Reading (bar P4-6 which were never in the plan). Includes the TCD & the curves, down to Reading West (see B&H section).
  • West of Didcot Parkway, all lines are wired & live heading towards Swindon.
  • Everything wired at Swindon (bar the goods lines north of P1, where provision is provided).

Small Points
  • ATF wires in operation from Maidenhead to Wootton Bassett; Kensal Green to Maidenhead currently only using return conductors but will be AT-ready in the near future. Some AT wires up along this stretch now; whether they are live remains to be seen.
    • In preparation for the Elizabeth Line running to Maidenhead, Hayes & Harlington to Maidenhead was closed off over the Early May Bank Holiday (5/5 to 7/5); this included renewals of S&C at West Drayton & Slough West Jct, alongside HOPS work at Langley. Paddington to H&H was also closed on May 6th, and encompassed final OLE works for Crossrail, alongside (presumably) ATF installation, finishing of Platform Extensions, lift shaft installation, passenger footbridge installation, and ticket hall foundation installation.
  • At Ealing Broadway, the staircase to P2/3 is being demolished and replaced with a new structure as part of the Crossrail works. Access is via the footbridge at the London end from P4 - work started on 1/10 and should continue until late December.
  • Parapet Work ongoing at Southbury Lane Bridge, Ruscombe; the top of the parapets & the wing walls remain unfinished.
  • Parapet Work has yet to commence on Butts Hill Rd Bridge, Woodley; restrictions were due to be lifted by Hallowe'en.
  • Few masts and cantilevers now up on the Didcot Avoiding Line, which finish at Appleford; Appleford LC being the limit of wires for the time being.
  • Oxford Lines west of Didcot Pkwy wired as far as the loco fuelling sdg; Down Oxford as far as 53m 31ch, Up Oxford as far as 53m 42ch. Didcot avoiding lines have sprouted masts (4 portals, 2 TTCs), with a wire pair over the Down Didcot Avoider.
  • A note on Steventon: Wires up under the High St Bridge (aka the "Brunel Bridge"); however, the bridge may well be demolished in CP6. "Temporary" parapet work to protect passers-by from stray currents now complete. Wires west of Causeway Crossing are only authorised for passenger service on Down trains; the discussion continues.
  • Overruns through Swindon Jct (77m 36ch) onto the Golden Valley Line have also been wired.
  • Another note on the OLE beyond Didcot: the wires west of Causeway Crossing were authorised for passenger service (as of Sunday 28th October) as far as Swindon for Down (westbound) trains ONLY, with the Up line due to follow on the 4th of November - this has been suspended UFN. (Down trains are continuing to run on AC, however). Trains may run on AC under test conditions (as ECS) beyond to Wootton Bassett & Bristol Parkway, but entry of IETs in AC passenger service beyond Swindon is unlikely before December.

The "Main Line"; Wootton Bassett Jct - Chippenham (Cocklebury Lane Bridge)
Until further notice, the 25kV transmission wires will run in a trough from Cocklebury Lane Bridge (just east of Chippenham) to Thingley Jct. Large steelwork is expected to remain in situ until wiring is authorised west of Thingley, but some specific items may be poached if required elsewhere (and duplicates aren't stored at RAF Wroughton). Details given in the "Postponements" section.
  • All masts and earth wires are now up between Wootton Bassett Jct & Cocklebury Lane Overbridge.
  • The Up Line is wired throughout from Cocklebury Lane to Wootton Bassett.
  • The Down Line is fully wired apart for a half-mile gap in both catenary & contact wires from Dauntsey to Christian Malford.

Chippenham (Cocklebury Lane Bridge) - Thingley Jct
  • No piles in Chippenham station, nor any masts affixed to the viaduct.
  • All piles in and majority of masts (and cantilevers) up from the western end of the viaduct to Thingley Junction (where the feeder station will be). Most TTCs have booms from beyond the viaduct to Thingley East Junction. About 14 masts are up in the vicinity of Thingley Feeder Stn, 2 of which have TTC booms affixed. Another has an STC boom.
  • Piles continue westwards to the next bridge.

Thingley Jct - Keynsham
  • No wiring for the foreseeable future, but overbridges between Thingley Jct & Box Tunnel have all been rebuilt. Corsham Main Road Bridge needs its parapets raising. New aqueduct & footbridge at Corsham complete.
  • Both Box & Middle Hill Tunnels have had track lowered.
  • A new footbridge has been built at Ashley Box.
  • Piles also in (and have been for over a year) at Ashley (beyond Box Tunnel) - these might well be trial piles.
  • Bathampton Jct to beyond Sydney Gardens has had track lowered. A new signal gantry at Bathampton Jct was installed over Xmas 2017 but is not yet in use.
  • Bath Spa platforms realigned & raised, with track also slewed.
  • Track through Oldfield Park & Keynsham now lowered.
  • A lot of piles are in along the embankment around Saltford and Keynsham in readiness for future wiring.

South Wales Main Line (Wootton Bassett Jct-Bristol Parkway-Severn Tunnel-Newport-Cardiff)

Wootton Bassett Jct to Filton Jct (inc. Bristol Parkway) - LIVE
  • All catenary & contact wires up from Wootton Bassett Jct, past Westerleigh Jct (107m 14ch) through Bristol Parkway and thence to Filton Jct & Stoke Gifford IEP Depot; Chipping Sodbury Goods Loop and the Cheltenham Curve overrun (as far as the limit of wiring) are also fully wired and live.
  • BPW Platforms now fully wired; includes the Down Goods Loop & Up Passenger Loop.
    • A number of masts & booms (now all wired up) are up on the line towards Filton Abbey Wood, between Stoke Gifford Jct No.1 (111m 79ch) and Filton Jct No.1 (113m 01ch); these end just short of Filton Jct 1 and will presumably act as an overrun until electrification continues into Temple Meads.
    • Section Isolator Masts now installed immediately before Stoke Gifford Jct No. 1, for the proposed neutral section just west of Bristol Parkway; these now have their feeder wires.
  • Filton Bank bridge works (mileages all from Temple Meads):
    • Easton Rd Overbridge (1m 18ch) completely rebuilt.
    • Narroways Footbridge (2m 12ch) replaced.
    • Ashley Hill Footbridge (3m 11ch) replaced.
    • Bonnington Walk Overbridge (3m 62ch) - parapets raised.
    • Footbridge south of Filton Abbey Wood (4m 18ch) will need work if wiring is to occur.
Filton Jct - Severn Tunnel
  • The Patchway/Severn Tunnel Blockade is now complete.
  • The 3-week Bristol Parkway Blockade and subsequent weekend blockade are also now complete.
  • Stoke Gifford IEP Depot all wired.
  • Patchway Tunnels conductor rail installed.
  • Masts, booms and SPS up through Patchway. No wires yet.
    • Cattybrook Brickworks Bridge closed as of 18/3/18.
  • At Pilning, during the Summer Tunnels blockade, all portals and masts have now been erected, and wires have gone up.

Severn Tunnel - Newport
Due to have IETs in AC service by 2020!
  • Severn Tunnel Conductor rail in place. A number of masts on both sides of the line are now up at Caldicot, just before the Western tunnel mouth; these now extend westwards towards the eastern end of the platforms at STJ.
  • Part of the central island platform at Severn Tunnel Junction has been fenced off - a possible mast location?
  • All bridge rebuilding complete from Severn Tunnel Jct (149m 14ch) to Bishton Flyover (152m 30ch).
  • Masts beginning to go up between Severn Tunnel Jct & Bishton Flyover, as of 3/4/18. These include:
    • At least 11 between Undy (Church Rd Bridge) and the M4 viaduct over the mains; one just east of the "white house" has a TTC boom. It can be assumed that its 8 comrades will be similarly adorned. Another mast over the Reliefs west of the "white house" has now gained a TTC boom with 1 SPS assembly; it has a twin over the Mains.
    • Two opposing pairs of TTC masts have gone up between Church Rd Bridge & the Playing Fields Footbridge.
    • Two large uprights have gone up between Undy Playing Fields footbridge & "the ramp" bridge at Magor on opposite sides of the line; these may well take a portal boom.
    • Another 3 masts (two for a portal boom, one a TTC with boom up) have appeared east of "the ramp" bridge at Magor; these join the sole TTC on the Up side by the bridge.
    • The 3 TTCs west of "the ramp" bridge (2 on the Down, 1 on the Up) have gained SPS.
    • The signal gantry at Magor (west of the West End Footbridge) has been replaced by 4 signals on posts; this should mean its removal prior to electrification is imminent. A TTC with SPS is up over the Mains there too.
    • 1 mast is up to the west of Redwick Rd Bridge (by the Down Relief), and a mast due to bear a portal is up to the east of Whitewall Footbridge (by the Up Main). OTP is in place for a piling/masting operation by Redwick Rd compound.
    • Masts (with SPS fitted) up between Bishton Flyover (including over it) and Llanwern West Jct (156m 20ch). 5 masts are currently up on the curve down from the flyover at its eastern end.
    • Plenty single masts (with SPS fitted & folded) up along the Mains between the Flyover and Bishton LC. A run of Earth wire is now up on the Up side at Bishton.
  • West of Bishton LC (153m 01ch), masts are around 90-95% up (all bar a few have booms and SPS), with the main gap at Llanwern Works East Connection (153m 05ch). This continues west towards Llanwern Works West Connection/Llanwern West Junction (156m 03ch to 156m 20ch). 4 masts (3 over the Mains, 1 over the Reliefs) also have booms & SPS immediately west of the LC.
  • Some masts have sprouted near Lliswerry pond.
  • 6-track portals, probably TGBUs (aka Thumpin' Great Big-Uns) going up aroung East Usk Yard (approx. MP157 1/2).
  • Between the Maindee Jcts (157m 74ch to 158m 16ch), a cluster of piles is in beside the Down Relief; these are complemented by masted piles on the Main side (adjacent to the Up Main).
  • Caerleon Rd Overbridge to be refurbished in 2 phases - 20/7 to 30/11, and then January ‘19 to March ‘19. Not sure what impact on wiring this will have.
  • Some SPS has now gone up between Maindee West & Maindee East; between Maindee West Maindee North Jct (41m 03ch from the former Rotherwas Jct, just south of Hereford; the ELR for the southern part of the Marches Line), masts with TTCs on are also going up (as overruns) over the Marches Line; the termination mast & associated TTC are just north of signal "NT 1559".
  • Fixings for masts have now been installed on the Usk Bridge.

Newport
  • All canopies now cut back.
  • Masts and portals now appearing at the western end of the station, some with SPS attached. More started to appear in mid-April; additionally, two at the Cardiff end & two through the P1 canopy on the weekend of April 28th/29th.
  • 4-track portal now up over the southern 4 tracks, just east of the new station footbridge.
  • Two six-track portals have now gone up over the western throat of the station, just short of a 4-track portal (uprights of) & a TTC (with SPS) adjacent to Clytha Park Rd.
  • Old stn footbridge now removed; 4-track portal of the "TGBU" (Thumpin' Great Big 'Un) variety has been installed in its place.
  • A new portal has gone up at the east end of Newport, with all the fixings for switchgear affixed at the top. Droptubes for registration arms are also on.

Newport - Cardiff
  • Plenty masts up around Gaer Jct (159m 32ch) north of Cardiff Rd Bridge (the B4237):
    • one by the Down Relief;
    • two by the Up Main (one of which is a boomed TTC with SPS);
    • three by the Gaer Jct - Park Jct Chord.
  • Around 6 piles are in adjacent to the Up Main between Gaer Jct and Ebbw Jct (160m 07ch); these will probably take masts for portal booms. One such boom appears to have gone in! Currently unknown if Alexandra Dock Jct Yard will be electrified.
  • Lots of steelwork up immediately behind the signal gantry adjacent to the Up Main at Ebbw Jct; this includes a full portal boom and a TTC acting as an overrun mast on the Ebbw Vale branch.
  • Over 100 masts from Ebbw Jct to Marshfield (163m 60ch). Booms & SPS starting to appear in the area too.
  • Green Lane Bridge, nr Marshfield (164m 57ch) reopened to traffic after reconstruction. Masts (with SPS) up around here too.
  • Lots of masts (with booms, SPS & ATF brackets) now up near Mardy Rd Bridge, Rumney.
  • Two TTCs, one on each side of the tracks, have been erected by the bridge at Rhymney River Bridge Jct (167m 61ch).
  • About 4 or 5 portals have been erected just west of Pengam Jct (168m 40ch); 5 masts are up on the Up side east of Rover Lane bridge, complemented by 2 on the Down side. Some of the portals now have booms, and bear SPS; one of these has all its registration arms up.
  • First Welsh Wire Run: 1 run of C&C has gone up between Moorland Road Jct (168m 65ch) and Long Dyke Jct (169m 35ch) over the Reliefs on the 15-16th September 2018; this is assumed to be a crossover as it crosses from one Relief line to the other.
  • A handful of masts are also up around Long Dyke Jct; some have now gained TTC booms and SPS as well.
  • Substantial mast foundations have appeared at each corner of the bridge over St. Mary's Street in Cardiff, along with work behind the nearby OU building. Masts may be imminent.
  • Splott Rd Bridge upgrade work now complete.
Cardiff Central - Platforms 0-4 to be wired
  • Re-signalling completed. Platform 0 now open. 3 masts now up over P0/1 with TTC booms.
  • Piling underway at the extreme ends of P1/2 & P3/4 for future masts. One can assume portals will bridge the gap between P2 & P3, over the Through lines.
  • Canopy cut-back work now underway on P2.
  • Brackets appear to be in place on the coping stones on the Taff Viaduct (at the western end of the station).
  • Plenty piles up adjacent to Cardiff Canton.
  • Brickwork Sidings to be increased in length (and electrified) to accommodate GWR Class 387s.
  • Proposed Limit of Wiring: Leckwith Loop North Jct (171m 55ch) at a guess.
Swansea IEP Depot
  • New IEP Depot at Maliphant Sidings, Swansea now complete; all steelwork up but no wires.

GWML/SWML Blockades:
  • 6/7 to 3/12: Reduced capacity between Newport & Cardiff Central while electrification progresses; assume only 1 pair of lines open at a time.
  • 15/9 to 6/10, and 13/10 to 14/10: Bristol Parkway blockaded to allow OLE to be installed within the station; done.
  • 27/10 to 18/11: Filton Bank blockaded for 4-tracking; worth posting on here as *some* OLE works might occur - not that I know for certain.
  • 11/11: Bristol TM to Bath Spa blockaded until 13:00 while the resignalling work is completed on this stretch.
  • 25/12/18 to 1/1/19: Bristol Parkway - Newport will be blockaded again, due to electrification work at Severn Tunnel Junction.
  • More Blockades will follow; details as they become available.

Berks & Hants Line (Reading-Newbury) - LIVE
Electric trains are set to be in squadron service from January 2019 - ORR sign-off due around Christmas.
  • Wires from Oxford Rd Jct are now LIVE to the limits of electrification (53m 42ch on the Newbury Lines, 38m 07ch on the Basingstoke Lines) as of 0650 on 21/10/18.
  • EMUs to Newbury on test SOON - IETs likely to be first (as they're already route-cleared), with 387s and 319s to follow. Platforms will need to be gauged.
  • Within Reading West, piles for the new footbridge (under Murphy's remit) are in, but have been "decapitated" (i.e. shortened) and capped until a new footbridge solution is found.
  • Extension to Reading West Up platform nearly complete. A new camera of sorts has appeared, but no further visible work on the platform extension has taken place since the 29th of October.
  • Parapet work now complete on the A4 (Bath Rd) overbridge. Similar works for Tilehurst Rd overbridge are now underway; the bridge has now been reduced to single-lane working for road traffic.
  • Platform extension works complete (and now opened) at Theale, Aldermaston and Thatcham.
  • Newbury's new footbridge is now open (not the lifts yet).

Limit of Wiring: 53m 42ch.
  • Gives Ample room to reverse a 12-car 387 formation.
  • Immunised signalling continues to about MP55 1/2. Bedwyn Turnback Siding now extended to accommodate 5-car IETs.

Project Postponements
  • Thames Valley Branches: Windsor & Henley deferred to CP6. Marlow removed from scope of current programme. The first few yards of each branch (bar the Henley Branch) have been wired as an overrun.
  • Southcote Jct to Basingstoke has also been deferred to CP6.
  • Appleford LC to Oxford paused; if CP6 accounts allow for wiring to be extended to Oxford, it would be very likely to happen now that Oxford has been remodelled.
  • Catenary & Contact wires between Chippenham (Cocklebury Lane Overbridge) & Thingley Jct have been deferred until (presumably) CP6; presumably this will wait until Bath-Bristol resignalling is complete. All Large steelwork to remain, unless required elsewhere.
  • Bristol Temple Meads to Bath & Bristol Parkway paused, dependent on Bristol resignalling (Taunton-Parkway over Easter 2018; Temple Meads to Bath in November 2018), track remodelling and Filton Bank 4-tracking (underway - to be completed by December 2018).
  • Bristol Temple Meads' "Midland Shed" to be reopened in CP6, after Bristol resignalling is complete and the PSB is demolished.
As always, do let me know if I've missed anything!
(apologies to anyone who saw it in a state of source code chaos too).
 

dougofakkad

Member
Joined
11 Oct 2017
Messages
10
Hello all,

I saw another blockade listed for Theale - Bedwyn at Reading station yesterday for 19-22 Nov. Is this a new addition? I'm fairly sure I remember hearing the Oct one was supposed to be the last.
 

oglord

Member
Joined
13 Oct 2010
Messages
331
Location
Newport, Monmouthshire
A run of earth and ATF wires has appeared on the down relief side between Llanwern West and East junctions. This is followed by a run of catenary wire with droppers on the down main towards Bishton.
 

3973EXL

Established Member
Joined
2 Feb 2017
Messages
2,446
Hello all,

I saw another blockade listed for Theale - Bedwyn at Reading station yesterday for 19-22 Nov. Is this a new addition? I'm fairly sure I remember hearing the Oct one was supposed to be the last.

There was originally but is not required now.
Removed from the GWR website but there are still some old posters up at Reading.
 

oglord

Member
Joined
13 Oct 2010
Messages
331
Location
Newport, Monmouthshire
A run of earth and ATF wires has appeared on the down relief side between Llanwern West and East junctions. This is followed by a run of catenary wire with droppers on the down main towards Bishton.
Quoting myself, I can now add (having travelled in the opposite direction) that there is a complete run of C&C on the up main in the same location, ending just before the Bishton crossing.
 

hugogreatwest

New Member
Joined
9 Nov 2018
Messages
1
Can I ask about reading Newbury when is this section going to get used as it’s now energised and when do we get electrics was told by network rail that it will be done the same time as Swindon goes live but not the case ???
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,493
Location
Between Peterborough & Bedlington
Can I ask about reading Newbury when is this section going to get used as it’s now energised and when do we get electrics was told by network rail that it will be done the same time as Swindon goes live but not the case ???
Test runs with units need to occur; AIUI no units have yet run down from Reading on AC power.
800s/802s are likely to be the first units to test the wires as they're already route-cleared; the 387s and 319s (to be 769s) will follow afterwards.
 

deltic08

On Moderation
Joined
26 Aug 2013
Messages
2,718
Location
North
Can I ask about reading Newbury when is this section going to get used as it’s now energised and when do we get electrics was told by network rail that it will be done the same time as Swindon goes live but not the case ???
Punctuation will make more sense of this.
 

FGW_DID

Established Member
Joined
23 Jun 2011
Messages
2,728
Location
81E
There is still work to be done regardless of the section being energised, there are another 4 weekends of planned work with Blocks to Electric Traction in and around the Reading area.
 

HowardGWR

Established Member
Joined
30 Jan 2013
Messages
4,983
Can I ask about reading Newbury when is this section going to get used as it’s now energised and when do we get electrics was told by network rail that it will be done the same time as Swindon goes live but not the case ???
Welcome to the forum. Could you please write with punctuation?
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,493
Location
Between Peterborough & Bedlington
GWML Electrification: State of Play, as of 12/11/18.
All mileages given from Paddington, except where noted.
Paddington to Wootton Bassett Jct - LIVE
  • All main line tracks wired as far as Wootton Bassett Jct, and are to be considered "live" as such. The envelope of "live" wires continues along the South Wales Main Line to Filton Jct (inc. Bristol Parkway), and to the Limits of Wiring on the Berks & Hants line and Reading-Basingstoke Line; details are given below.
  • TTCs have replaced/been replacing headspans at various locations within London - locations include Westway (beneath the A40), Acton Main Line, Ealing Broadway, and between Southall & H&H. These are part of the works for the Elizabeth Line.
  • Everything wired at Reading (bar P4-6 which were never in the plan). Includes the TCD & the curves, down to Reading West (see B&H section).
  • West of Didcot Parkway, all lines are wired & live heading towards Swindon.
  • Everything wired at Swindon (bar the goods lines north of P1, where provision is provided).

Small Points
  • ATF wires in operation from Maidenhead to Wootton Bassett; Kensal Green to Maidenhead currently only using return conductors but will be AT-ready in the near future. Some AT wires up along this stretch now; whether they are live remains to be seen.
    • In preparation for the Elizabeth Line running to Maidenhead, Hayes & Harlington to Maidenhead was closed off over the Early May Bank Holiday (5/5 to 7/5); this included renewals of S&C at West Drayton & Slough West Jct, alongside HOPS work at Langley. Paddington to H&H was also closed on May 6th, and encompassed final OLE works for Crossrail, alongside (presumably) ATF installation, finishing of Platform Extensions, lift shaft installation, passenger footbridge installation, and ticket hall foundation installation.
  • At Ealing Broadway, the staircase to P2/3 is being demolished and replaced with a new structure as part of the Crossrail works. Access is via the footbridge at the London end from P4 - work started on 1/10 and should continue until late December.
  • Parapet Work ongoing at Southbury Lane Bridge, Ruscombe; the top of the parapets & the wing walls remain unfinished.
  • Parapet Work has yet to commence on Butts Hill Rd Bridge, Woodley; restrictions were due to be lifted by Hallowe'en.
  • Few masts and cantilevers now up on the Didcot Avoiding Line, which finish at Appleford; Appleford LC being the limit of wires for the time being.
  • Oxford Lines west of Didcot Pkwy wired as far as the loco fuelling sdg; Down Oxford as far as 53m 31ch, Up Oxford as far as 53m 42ch. Didcot avoiding lines have sprouted masts (4 portals, 2 TTCs), with a wire pair over the Down Didcot Avoider.
  • A note on Steventon: Wires up under the High St Bridge (aka the "Brunel Bridge"); however, the bridge may well be demolished in CP6. "Temporary" parapet work to protect passers-by from stray currents now complete. Wires west of Causeway Crossing are now authorised for passenger service both directions (with 80x units only); the discussion continues.
  • Overruns through Swindon Jct (77m 36ch) onto the Golden Valley Line have also been wired.
  • Another note on the OLE beyond Didcot: the wires west of Causeway Crossing were authorised for passenger service (as of Sunday 28th October) as far as Swindon for Down (westbound) trains ONLY, with the Up line following on Sunday 11th November. Trains may run on AC under test conditions (as ECS) beyond to Wootton Bassett & Bristol Parkway, but entry of IETs in AC passenger service beyond Swindon is unlikely before December.

The "Main Line"; Wootton Bassett Jct - Chippenham (Cocklebury Lane Bridge)
Until further notice, the 25kV transmission wires will run in a trough from Cocklebury Lane Bridge (just east of Chippenham) to Thingley Jct. Large steelwork is expected to remain in situ until wiring is authorised west of Thingley, but some specific items may be poached if required elsewhere (and duplicates aren't stored at RAF Wroughton). Details given in the "Postponements" section.
  • All masts and earth wires are now up between Wootton Bassett Jct & Cocklebury Lane Overbridge.
  • The Up Line is wired throughout from Cocklebury Lane to Wootton Bassett.
  • The Down Line is fully wired apart for a half-mile gap in both catenary & contact wires from Dauntsey to Christian Malford.

Chippenham (Cocklebury Lane Bridge) - Thingley Jct
  • No piles in Chippenham station, nor any masts affixed to the viaduct.
  • All piles in and majority of masts (and cantilevers) up from the western end of the viaduct to Thingley Junction (where the feeder station will be). Most TTCs have booms from beyond the viaduct to Thingley East Junction. About 14 masts are up in the vicinity of Thingley Feeder Stn, 2 of which have TTC booms affixed. Another has an STC boom.
  • Piles continue westwards to the next bridge.

Thingley Jct - Keynsham
  • No wiring for the foreseeable future, but overbridges between Thingley Jct & Box Tunnel have all been rebuilt. Corsham Main Road Bridge needs its parapets raising. New aqueduct & footbridge at Corsham complete.
  • Both Box & Middle Hill Tunnels have had track lowered.
  • A new footbridge has been built at Ashley Box.
  • Piles also in (and have been for over a year) at Ashley (beyond Box Tunnel) - these might well be trial piles.
  • Bathampton Jct to beyond Sydney Gardens has had track lowered. A new signal gantry at Bathampton Jct was installed over Xmas 2017 but is not yet in use.
  • Bath Spa platforms realigned & raised, with track also slewed.
  • Track through Oldfield Park & Keynsham now lowered.
  • A lot of piles are in along the embankment around Saltford and Keynsham in readiness for future wiring.

South Wales Main Line (Wootton Bassett Jct-Bristol Parkway-Severn Tunnel-Newport-Cardiff)

Wootton Bassett Jct to Filton Jct (inc. Bristol Parkway) - LIVE
  • All catenary & contact wires up from Wootton Bassett Jct, past Westerleigh Jct (107m 14ch) through Bristol Parkway and thence to Filton Jct & Stoke Gifford IEP Depot; Chipping Sodbury Goods Loop and the Cheltenham Curve overrun (as far as the limit of wiring) are also fully wired and live.
  • BPW Platforms now fully wired; includes the Down Goods Loop & Up Passenger Loop.
    • A number of masts & booms (now all wired up) are up on the line towards Filton Abbey Wood, between Stoke Gifford Jct No.1 (111m 79ch) and Filton Jct No.1 (113m 01ch); these end just short of Filton Jct 1 and will presumably act as an overrun until electrification continues into Temple Meads.
    • Section Isolator Masts now installed immediately before Stoke Gifford Jct No. 1, for the proposed neutral section just west of Bristol Parkway; these now have their feeder wires.
  • Filton Bank bridge works (mileages all from Temple Meads):
    • Easton Rd Overbridge (1m 18ch) completely rebuilt.
    • Narroways Footbridge (2m 12ch) replaced.
    • Ashley Hill Footbridge (3m 11ch) replaced.
    • Bonnington Walk Overbridge (3m 62ch) - parapets raised.
    • Footbridge south of Filton Abbey Wood (4m 18ch) will need work if wiring is to occur.
Filton Jct - Severn Tunnel
  • The Patchway/Severn Tunnel Blockade is now complete.
  • The 3-week Bristol Parkway Blockade and subsequent weekend blockade are also now complete.
  • Stoke Gifford IEP Depot all wired.
  • Patchway Tunnels conductor rail installed.
  • Masts, booms and SPS up through Patchway. No wires yet.
    • Cattybrook Brickworks Bridge closed as of 18/3/18.
  • At Pilning, during the Summer Tunnels blockade, all portals and masts have now been erected, and wires have gone up.

Severn Tunnel - Newport
Due to have IETs in AC service by 2020!
  • Severn Tunnel Conductor rail in place. A number of masts on both sides of the line are now up at Caldicot, just before the Western tunnel mouth; these now extend westwards towards the eastern end of the platforms at STJ.
  • Part of the central island platform at Severn Tunnel Junction has been fenced off - a possible mast location?
  • All bridge rebuilding complete from Severn Tunnel Jct (149m 14ch) to Bishton Flyover (152m 30ch).
  • Masts beginning to go up between Severn Tunnel Jct & Bishton Flyover, as of 3/4/18. These include:
    • At least 11 between Undy (Church Rd Bridge) and the M4 viaduct over the mains; one just east of the "white house" has a TTC boom. It can be assumed that its 8 comrades will be similarly adorned. Another mast over the Reliefs west of the "white house" has now gained a TTC boom with 1 SPS assembly; it has a twin over the Mains.
    • Two opposing pairs of TTC masts have gone up between Church Rd Bridge & the Playing Fields Footbridge.
    • Two large uprights have gone up between Undy Playing Fields footbridge & "the ramp" bridge at Magor on opposite sides of the line; these may well take a portal boom.
    • Another 3 masts (two for a portal boom, one a TTC with boom up) have appeared east of "the ramp" bridge at Magor; these join the sole TTC on the Up side by the bridge.
    • 3 of the 4 TTCs west of "the ramp" bridge (2 on the Down side, 1 on the Up side) bear SPS; a 4th TTC has been boomed on the up, opposite the more western boom on the Down side.
    • The signal gantry at Magor (west of the West End Footbridge) has been replaced by 4 signals on posts; this should mean its removal prior to electrification is imminent. A TTC with SPS is up over the Mains there too.
    • 1 mast is up to the west of Redwick Rd Bridge (by the Down Relief), and a mast due to bear a portal is up to the east of Whitewall Footbridge (by the Up Main). OTP is in place for a piling/masting operation by Redwick Rd compound.
    • Masts (with SPS fitted) up between Bishton Flyover (including over it) and Llanwern West Jct (156m 20ch). 5 masts are currently up on the curve down from the flyover at its eastern end.
    • Plenty single masts (with SPS fitted & folded) up along the Mains between the Flyover and Bishton LC. A run of Earth wire is now up on the Up side at Bishton.
  • West of Bishton LC (153m 01ch), masts are around 90-95% up (all bar a few have booms and SPS), with the main gap at Llanwern Works East Connection (153m 05ch). This continues west towards Llanwern Works West Connection/Llanwern West Junction (156m 03ch to 156m 20ch). 4 masts (3 over the Mains, 1 over the Reliefs) also have booms & SPS immediately west of the LC.
  • A run of Earth Wires & ATF wires have been strung up on the Relief side (adjacent to the DR) between Llanwern Works East Connection & Llanwern West Jct.
  • In this stretch also, wires are now up on the Mains:
    • Catenary wire & droppers only on the Down Main;
    • Catenary & contact wires on the Up Main.
  • Some masts have sprouted near Lliswerry pond.
  • 6-track portals, probably TGBUs (aka Thumpin' Great Big-Uns) going up aroung East Usk Yard (approx. MP157 1/2).
  • Between the Maindee Jcts (157m 74ch to 158m 16ch), a cluster of piles is in beside the Down Relief; these are complemented by masted piles on the Main side (adjacent to the Up Main).
  • Caerleon Rd Overbridge to be refurbished in 2 phases - 20/7 to 30/11, and then January ‘19 to March ‘19. Not sure what impact on wiring this will have.
  • Some SPS has now gone up between Maindee West & Maindee East; between Maindee West Maindee North Jct (41m 03ch from the former Rotherwas Jct, just south of Hereford; the ELR for the southern part of the Marches Line), masts with TTCs on are also going up (as overruns) over the Marches Line; the termination mast & associated TTC are just north of signal "NT 1559".
  • Fixings for masts have now been installed on the Usk Bridge.

Newport
  • All canopies now cut back.
  • Masts and portals now appearing at the western end of the station, some with SPS attached. More started to appear in mid-April; additionally, two at the Cardiff end & two through the P1 canopy on the weekend of April 28th/29th.
  • 4-track portal now up over the southern 4 tracks, just east of the new station footbridge.
  • Two six-track portals have now gone up over the western throat of the station, just short of a 4-track portal (uprights of) & a TTC (with SPS) adjacent to Clytha Park Rd.
  • Old stn footbridge now removed; 4-track portal of the "TGBU" (Thumpin' Great Big 'Un) variety has been installed in its place.
  • A new portal has gone up at the east end of Newport, with all the fixings for switchgear affixed at the top. Droptubes for registration arms are also on.

Newport - Cardiff
  • Plenty masts up around Gaer Jct (159m 32ch) north of Cardiff Rd Bridge (the B4237):
    • one by the Down Relief;
    • two by the Up Main (one of which is a boomed TTC with SPS);
    • three by the Gaer Jct - Park Jct Chord.
  • Around 6 piles are in adjacent to the Up Main between Gaer Jct and Ebbw Jct (160m 07ch); these will probably take masts for portal booms. One such boom appears to have gone in! Currently unknown if Alexandra Dock Jct Yard will be electrified.
  • Lots of steelwork up immediately behind the signal gantry adjacent to the Up Main at Ebbw Jct; this includes a full portal boom and a TTC acting as an overrun mast on the Ebbw Vale branch.
  • Over 100 masts from Ebbw Jct to Marshfield (163m 60ch). Booms & SPS starting to appear in the area too.
  • Green Lane Bridge, nr Marshfield (164m 57ch) reopened to traffic after reconstruction. Masts (with SPS) up around here too.
  • Lots of masts (with booms, SPS & ATF brackets) now up near Mardy Rd Bridge, Rumney.
  • Two TTCs, one on each side of the tracks, have been erected by the bridge at Rhymney River Bridge Jct (167m 61ch).
  • About 4 or 5 portals have been erected just west of Pengam Jct (168m 40ch); 5 masts are up on the Up side east of Rover Lane bridge, complemented by 2 on the Down side. Some of the portals now have booms, and bear SPS; one of these has all its registration arms up.
  • First Welsh Wire Run: 1 run of C&C has gone up between Moorland Road Jct (168m 65ch) and Long Dyke Jct (169m 35ch) over the Reliefs on the 15-16th September 2018; this is assumed to be a crossover as it crosses from one Relief line to the other.
  • A handful of masts are also up around Long Dyke Jct; some have now gained TTC booms and SPS as well.
  • Substantial mast foundations have appeared at each corner of the bridge over St. Mary's Street in Cardiff, along with work behind the nearby OU building. Masts may be imminent.
  • Splott Rd Bridge upgrade work now complete.
Cardiff Central - Platforms 0-4 to be wired
  • Re-signalling completed. Platform 0 now open. 3 masts now up over P0/1 with TTC booms.
  • Piling underway at the extreme ends of P1/2 & P3/4 for future masts. One can assume portals will bridge the gap between P2 & P3, over the Through lines.
  • Canopy cut-back work now underway on P2.
  • Brackets appear to be in place on the coping stones on the Taff Viaduct (at the western end of the station).
  • Plenty piles up adjacent to Cardiff Canton.
  • Brickwork Sidings to be increased in length (and electrified) to accommodate GWR Class 387s.
  • Proposed Limit of Wiring: Leckwith Loop North Jct (171m 55ch) at a guess.
Swansea IEP Depot
  • New IEP Depot at Maliphant Sidings, Swansea now complete; all steelwork up but no wires.

GWML/SWML Blockades:
  • 6/7 to 3/12: Reduced capacity between Newport & Cardiff Central while electrification progresses; assume only 1 pair of lines open at a time.
  • 15/9 to 6/10, and 13/10 to 14/10: Bristol Parkway blockaded to allow OLE to be installed within the station; done.
  • 27/10 to 18/11: Filton Bank blockaded for 4-tracking; worth posting on here as *some* OLE works might occur - not that I know for certain.
  • 11/11: Bristol TM to Bath Spa blockaded until 13:00 while the resignalling work is completed on this stretch; done.
  • 24/11 to 25/11: Filton Bank blockaded for further work to the 4-tracking.
  • 1/12 to 2/12: Filton Bank blockaded for further work to the 4-tracking.
  • 9/12: Bristol Parkway blockaded.
  • 16/12: Didcot Parkway blockaded.
  • 25/12/18 to 1/1/19: Bristol Parkway - Newport will be blockaded again, due to electrification work at Severn Tunnel Junction.
  • More Blockades will follow; details as they become available.

Berks & Hants Line (Reading-Newbury) - LIVE
Electric trains are set to be in squadron service from January 2019 - ORR sign-off due around Christmas.
  • Wires from Oxford Rd Jct are now LIVE to the limits of electrification (53m 42ch on the Newbury Lines, 38m 07ch on the Basingstoke Lines) as of 0650 on 21/10/18.
  • EMUs to Newbury on test SOON - IETs likely to be first (as they're already route-cleared), with 387s and 319s to follow. Platforms will need to be gauged.
  • Within Reading West, piles for the new footbridge (under Murphy's remit) are in, but have been "decapitated" (i.e. shortened) and capped until a new footbridge solution is found.
  • Extension to Reading West Up platform nearly complete. A new camera of sorts has appeared, but no further visible work on the platform extension has taken place since the 29th of October.
  • Parapet work now complete on the A4 (Bath Rd) overbridge. Similar works for Tilehurst Rd overbridge are now underway; the bridge has now been reduced to single-lane working for road traffic.
  • Platform extension works complete (and now opened) at Theale, Aldermaston and Thatcham.
  • Newbury's new footbridge is now open (not the lifts yet).

Limit of Wiring: 53m 42ch.
  • Gives Ample room to reverse a 12-car 387 formation.
  • Immunised signalling continues to about MP55 1/2. Bedwyn Turnback Siding now extended to accommodate 5-car IETs.

Project Postponements
  • Thames Valley Branches: Windsor & Henley deferred to CP6. Marlow removed from scope of current programme. The first few yards of each branch (bar the Henley Branch) have been wired as an overrun.
  • Southcote Jct to Basingstoke has also been deferred to CP6.
  • Appleford LC to Oxford paused; if CP6 accounts allow for wiring to be extended to Oxford, it would be very likely to happen now that Oxford has been remodelled.
  • Catenary & Contact wires between Chippenham (Cocklebury Lane Overbridge) & Thingley Jct have been deferred until (presumably) CP6; presumably this will wait until Bath-Bristol resignalling is complete. All Large steelwork to remain, unless required elsewhere.
  • Bristol Temple Meads to Bath & Bristol Parkway paused, dependent on Bristol resignalling (Taunton-Parkway over Easter 2018, Temple Meads to Bath in November 2018 - both done), track remodelling and Filton Bank 4-tracking (underway - to be completed by December 2018).
  • Bristol Temple Meads' "Midland Shed" to be reopened in CP6, after Bristol resignalling is complete and the PSB is demolished.
As always, do let me know if I've missed anything!
(apologies to anyone who saw it in a state of source code chaos too).
 
Last edited:

FGW_DID

Established Member
Joined
23 Jun 2011
Messages
2,728
Location
81E
13.29 SWA PAD 800 317 was electric from Swindon to Causeway LC then again from Moreton.

That surprised me as I hadn’t seen any briefs issued, had a look at this mornings Late Notice and see that it was authorised for use as from 0830 11/11/18.
 

deltic08

On Moderation
Joined
26 Aug 2013
Messages
2,718
Location
North
That surprised me as I hadn’t seen any briefs issued, had a look at this mornings Late Notice and see that it was authorised for use as from 0830 11/11/18.
That is great news. All we need now is extension to Bristol Parkway by Christmas.
More than half the distance from Parkway to Newport is wired already so we could see energisation by early February and trains in March.
 

superkev

Established Member
Joined
1 Mar 2015
Messages
2,686
Location
west yorkshire
With the various project's drawing to a close I hope the electrification teams with there hard earned knowledge are not disbanded awaiting Grayling to stop sitting on his hands. Presumably the piles and mast teams are already starting to be layed off.
K
 

3973EXL

Established Member
Joined
2 Feb 2017
Messages
2,446
Minor updates from around Reading.

Tilehurst Rd bridge parapets no further progress.

Reading West platform some minor progress.
DSC01574.JPG

Butts Hill Rd bridge, new steelwork being attached to the outside of the parapets.
DSC01577.JPG

Southbury Lane bridge, original coping stones replaced.
Work rebuilding wing walls ongoing.
DSC01576.JPG
 

50031

Member
Joined
28 Aug 2013
Messages
168
It should! I've updated it on my offline .txt document, and I'll correct it here too.

No, that's misleading. Filton bank set to reopen this Monday (18th Nov) but subsequent weekend blockades to follow.

Plenty of updates and videos on Network Rail Western's twitter account.
 

3973EXL

Established Member
Joined
2 Feb 2017
Messages
2,446
Stations from Reading to Didcot are still waiting for platform work to be completed.

Cholsey, country end.
DSC01602.JPG DSC01603.JPG DSC01604.JPG

Goring, London end.
DSC01605.JPG

Pangbourne, country end.
DSC01606.JPG DSC01607.JPG DSC01608.JPG

Tilehurst, 1&4 country end. 2&3 London end.
DSC01609.JPG DSC01610.JPG DSC01611.JPG
 