SSR resignalling

CMS

Member
Joined
12 Aug 2009
Messages
181
Uxbridge 12tph
Watford 10tph
Amersham 4tph
Chesham 2tph
That would seem excessive to me unless they are peak frequencies and all of the Amersham/Cheshams are fast and all of the Watfords semi-fast.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

PeterC

Established Member
Joined
29 Sep 2014
Messages
4,066
That would seem excessive to me unless they are peak frequencies and all of the Amersham/Cheshams are fast and all of the Watfords semi-fast.
That is the same frequency as now for Chesham / Amersham. Two Amersham trains are stoppers the rest are fast. I know that local people are hoping for their fast trains back off peak once the resignalling is complete.
 

CMS

Member
Joined
12 Aug 2009
Messages
181
That is the same frequency as now for Chesham / Amersham. Two Amersham trains are stoppers the rest are fast. I know that local people are hoping for their fast trains back off peak once the resignalling is complete.
10tph Watford seems massive though, but I imagine it’s more for operational convenience compared to other potential reversal points than demand. I have also seen media around this and although I use the WCML far more than the Met line, I certainly believe re-introducing off-peak fasts is needed.
 

bramling

Veteran Member
Joined
5 Mar 2012
Messages
17,685
Location
Hertfordshire / Teesdale
Won’t be happening in November now.

From what I hear it’s now postponed for the time being, with new dates yet to be announced. One can’t help but wonder how a few months ago they thought things were sufficiently close to be going into revenue service on one of the test weekends, and now it keeps slipping more and more to the right.

To be fair this “third supplier lucky” contract was always going to be a challenge, however Thales do seem to be running into issues on this one.
 

simple simon

Member
Joined
13 Feb 2011
Messages
650
Location
Suburban London
copied from a railgen site...

Simon
----------------------------------

Another update.

The proposed software version for revenue use won't be mature enough until well into the New Year.

Hammersmith/ Finchley Road to Euston Square has been the suggested commissioning area to try and recover lost project milestones.

Most S8 stock has been kitted out with CBTC already so is achievable while a large chunk of S7 stock is already fitted.

Last Weekend's system testing possession between Euston Square to Whitechapel/ Tower Hill was successful.
 

bluegoblin7

Established Member
Joined
10 May 2011
Messages
1,356
Location
JB/JP/JW
This is the first suggestion I've heard of any combining of areas.

I'd take most of what gets posted on "gen sites" about 4LM with a pinch of salt.
 

DavyCrocket

Member
Joined
27 Oct 2006
Messages
614
Doubftul that there is the resource to provide familiarisation over such a large area. That is why smaller areas are chosen for the first of each line(s)
copied from a railgen site...

Simon
----------------------------------

Another update.

The proposed software version for revenue use won't be mature enough until well into the New Year.

Hammersmith/ Finchley Road to Euston Square has been the suggested commissioning area to try and recover lost project milestones.

Most S8 stock has been kitted out with CBTC already so is achievable while a large chunk of S7 stock is already fitted.

Last Weekend's system testing possession between Euston Square to Whitechapel/ Tower Hill was successful.
 

bramling

Veteran Member
Joined
5 Mar 2012
Messages
17,685
Location
Hertfordshire / Teesdale
This is the first suggestion I've heard of any combining of areas.

I'd take most of what gets posted on "gen sites" about 4LM with a pinch of salt.

It happened with the Jubilee, which among other things led to the Northern taking a "let's look at how they did things on the Jubilee and *not* do it that way" approach.

I can't see the current SSR management going with a combining approach, as the intention is to emulate the Northern Line delivery as far as possible - and many of the key players have come straight from the Northern to SSR. Having said that, pressure can always be applied from above to do things in undesirable ways.

Given the mess left over on the Northern, much of which is still there today, I'm pleased to see there does seem to be some effort to iron out software issues before "go live".
 

rebmcr

Established Member
Joined
15 Nov 2011
Messages
3,845
Location
St Neots
I note there is a closure for line modernisation this weekend between Hammersmith and Edgware Road — covering the SMA0.5 and SMA1 areas, plus some extra for sensible service patterns.

Is this for testing, or for a potential rollout?
 

Dstock7080

Established Member
Joined
17 Feb 2010
Messages
2,741
Location
West London
Is this for testing, or for a potential rollout?
“Operational Proving of SMA0.5”, ie. full testing of timetable, trains running without passengers but stopping at each station.
Hopefully ready for full commissioning 16-17 March.
 

rebmcr

Established Member
Joined
15 Nov 2011
Messages
3,845
Location
St Neots
“Operational Proving of SMA0.5”, ie. full testing of timetable, trains running without passengers but stopping at each station.
Hopefully ready for full commissioning 16-17 March.

Good news! Fingers crossed for a success.

Is anyone able to share any interesting detail about how the issue has been addressed with Hammersmith depot's disappearing/reappearing trains?
 

LU_timetabler

Member
Joined
5 Feb 2017
Messages
165
It's software issues. That seems to be the problem with new trains and new signalling these days - software issues!
 

bramling

Veteran Member
Joined
5 Mar 2012
Messages
17,685
Location
Hertfordshire / Teesdale
It's software issues. That seems to be the problem with new trains and new signalling these days - software issues!

It doesn't exactly help when you twice change your mind as to who's going to do a job, and then want it done asap!

The Victoria Line is the only one of the PPP-era resignalling projects which has been delivered in a manner which could be described as smooth and orderly.
 

rebmcr

Established Member
Joined
15 Nov 2011
Messages
3,845
Location
St Neots
The Victoria Line is the only one of the PPP-era resignalling projects which has been delivered in a manner which could be described as smooth and orderly.

I wonder if that's down to luck? They might well have encountered many fewer difficulties purely through the good fortune of working on a line with an already-established ATO method of working.
 

bramling

Veteran Member
Joined
5 Mar 2012
Messages
17,685
Location
Hertfordshire / Teesdale
I wonder if that's down to luck? They might well have encountered many fewer difficulties purely through the good fortune of working on a line with an already-established ATO method of working.

Possible. To be fair the Victoria Line was likely to be a slightly easier line to work on, and of course it’s rather shorter and less complex than any of the others, and of course didn’t involve open-air running which does simplify things a bit. Having said that, I get the feeling this project was run by a much better project team, and of course with the benefit of a much more clued-up and experienced supplier - Westinghouse as opposed to Thales. They didn’t seem to make all the schoolboy errors that Thales did on the Jubilee and Northern.

Without being on the inside of the project it’s hard to know for sure, however this is the feel I’ve picked up, and the Vic Line’s sublime solid 36tph peak service would seem to back this feeling up.
 

rebmcr

Established Member
Joined
15 Nov 2011
Messages
3,845
Location
St Neots
“Operational Proving of SMA0.5”, ie. full testing of timetable, trains running without passengers but stopping at each station.
Hopefully ready for full commissioning 16-17 March.

How did it go? I know there were faults at KXSP on Sunday, did that affect testing?
 

Mojo

Forum Staff
Staff Member
Administrator
Joined
7 Aug 2005
Messages
20,382
Location
0035
How did it go? I know there were faults at KXSP on Sunday, did that affect testing?
That was the normal service, nowhere near the test area, described as "Operational Proving" and used a special test train, with the normal service terminating at Edgware Rd and the Circle line running a 'traditional' service.

This differs from any commissioning will which involve a near-normal service[1] running to and from Hammersmith, with trains simply running empty from Paddington Suburban to Hammersmith, this is planned for, as stated above by @Dstock7080 the weekend of 16-17 March.

[1] A different timetable with earlier closures, etc, applies for this weekend but broadly the daytime service sees both Circle & Hammersmith/City line trains running to Hammersmith.
 
Last edited:

rebmcr

Established Member
Joined
15 Nov 2011
Messages
3,845
Location
St Neots
That was the normal service, nowhere near the test area, described as "Operational Proving" and used a special test train, with the normal service terminating at Edgware Rd and the Circle line running a 'traditional' service.

This differs from any commissioning will which involve a near-normal service[1] running to and from Hammersmith, with trains simply running empty from Paddington Suburban to Hammersmith, this is planned for, as stated above by @Dstock7080 the weekend of 16-17 March.

[1] A different timetable with earlier closures, etc, applies for this weekend but broadly the daytime service sees both Circle & Hammersmith/City line trains running to Hammersmith.

I see — the previous post made it sound like that was already last weekend's plan.
 

Mikey C

Established Member
Joined
11 Feb 2013
Messages
6,830
It doesn't exactly help when you twice change your mind as to who's going to do a job, and then want it done asap!

The Victoria Line is the only one of the PPP-era resignalling projects which has been delivered in a manner which could be described as smooth and orderly.

The Northern Line scheme didn't go badly, it was massively smoother and less disruptive than say the Jubilee Line one
 

bramling

Veteran Member
Joined
5 Mar 2012
Messages
17,685
Location
Hertfordshire / Teesdale
The Northern Line scheme didn't go badly, it was massively smoother and less disruptive than say the Jubilee Line one

Only after rescheduling, IIRC the original completion date was 2011, so the final completion was roughly three years late. To be fair this was largely due to the legacy of the Jubilee Line issues and perhaps partly due to the Tube Lines uncertainty. The ultimate Northern Line implementation phase went reasonably well, however there has been a legacy of issues left over, which are now LU’s problem, and have at times required assistance to be enlisted from consultants. Ultimately this and other factors has resulted in failure to deliver a new timetable which was planned to come in last year.
 

Dstock7080

Established Member
Joined
17 Feb 2010
Messages
2,741
Location
West London
Great news! Is the exact same plan in place — i.e. opening it up to passengers mid-Sunday?
A ‘soft-launch’ into passenger operation will hopefully occur sometime this weekend.

As at 0730 trains already operating to full timetable and no issues presented themselves.
 

ijmad

Established Member
Joined
7 Jan 2016
Messages
1,810
Location
UK
CBTC Hammersmith-Latimer Road went live for passenger operation at 14.06 today.

Great news. Hopefully the next phases will be easier now they've got a real live system proved and in daily passenger service. Roll on SMA1!
 