• Our booking engine at tickets.railforums.co.uk (powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Glasgow Queen Street refurbishment and remodelling

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

och aye

Member
Joined
21 Jan 2012
Messages
802
Does anybody know if there has been any further development on Network Rail's attempt to bring the former St Enoch's station clock from Cumbernauld to the station?
 

PaxVobiscum

Established Member
Joined
4 Feb 2012
Messages
2,397
Location
Glasgow
Network Rail will be stepping up their coverage shortly with their own team on site so I will be mainly covering developments that they will already have announced (minor example – gold cladding on the Dundas Street building that NetworkRailGQS tweeted on Friday https://twitter.com/networkrailgqs/status/1215647889222983681 )

A couple of photos of mine from today

F23E767C-321D-40A9-B821-7C15CE50E0D6.jpeg
0239025E-F295-403B-B64F-F751407AAE30.jpeg

The seagull, however, only works for me :lol: and I have recently increased his piece ;) rate.

C874D741-9EA1-431A-BEA6-0A939D2A5B63.jpeg
 

mcmad

Member
Joined
11 Mar 2015
Messages
979
Interesting that the roof looks complete but still lots of water ingress around the old to new join today.
 

Rick1984

Member
Joined
23 Aug 2012
Messages
1,034
Not sure about the gold cladding. Hopefully will weather down a bit.
Personally I would've liked to have seen corten steel used.
Will see what it looks like finished though
 

PaxVobiscum

Established Member
Joined
4 Feb 2012
Messages
2,397
Location
Glasgow
Where are they going to be placed?
My understanding is the departure boards will be above the gateline facing south so that the punters queue in the main concourse (under the new roof) and don’t clutter up the platforms. :)
 
Last edited:

PaxVobiscum

Established Member
Joined
4 Feb 2012
Messages
2,397
Location
Glasgow
My understanding was correct - here’s the back view (the single display unit fitted so far is at the top, about 1/3 of the way along from the left):
4821A98F-D57C-4AD3-909F-FA811BBDF839.jpeg
 

PaxVobiscum

Established Member
Joined
4 Feb 2012
Messages
2,397
Location
Glasgow
It’s not as high as the previous photo might have suggested. Here’s another angle:
3906C93D-69F1-47B2-BED8-B3BC9A821E98.jpeg
 

Attachments

  • A58736FE-743D-4AAE-8790-CFBF078BF89B.jpeg
    A58736FE-743D-4AAE-8790-CFBF078BF89B.jpeg
    124.6 KB · Views: 27

PaxVobiscum

Established Member
Joined
4 Feb 2012
Messages
2,397
Location
Glasgow
When are they due to finish, is it still to schedule?
According to Network Rail GQS it’s on schedule, and that seems to be agreed by any of the hard hats I’ve spoken to. I’m hoping to get more details fairly soon.
 

mcmad

Member
Joined
11 Mar 2015
Messages
979
Had a look at the new departure boards today, standing right at the back of the temporary concourse they're at a steep angle. Not sure how much room further back there is behind the hoardings but its not ideal placement (but no doubt looks good on the architects sketches, neatly hidden away. They've multiplied overnight too, are now 4 or 5 hanging there but not all together.

The 'old' boards were having some sort of IT melt down this morning and were all blank, much manual announcements over the top of the automated announcements....
 

applepie2100

Member
Joined
16 Aug 2011
Messages
167
Has there been any mention of what work, if any will be undertaken on the access to low level platforms as well as the platforms themselves? There was nothing shown in any of the flythroughs or documents I've seen. I'm guessing that it would be too much hope for them to refurbished and for access to be improved in ways such as installing escalators? I'm pretty sure that was suggested a few years ago and never followed through.
 

PaxVobiscum

Established Member
Joined
4 Feb 2012
Messages
2,397
Location
Glasgow
No escalators in the current plan, though that was in the original scheme. There will be extra fire exits and slightly longer platforms – basically just a reopening of part of the existing sections that have been fenced off since the last refurb of the Low Level. The Low Level station itself is basically outwith the EGIP works.
 

applepie2100

Member
Joined
16 Aug 2011
Messages
167
No escalators in the current plan, though that was in the original scheme. There will be extra fire exits and slightly longer platforms – basically just a reopening of part of the existing sections that have been fenced off since the last refurb of the Low Level. The Low Level station itself is basically outwith the EGIP works.

I can't say that I'm really surprised. The low level part of the station hasn't seen a proper upgrade in many years. Unfortunately it's not what you would term a very pleasant station so better lighting, escalators, new tiling/cladding etc would be a welcome upgrade. It looks like it will have to wait a while for any of that.
 

47271

Established Member
Joined
28 Apr 2015
Messages
2,983
I can't say that I'm really surprised. The low level part of the station hasn't seen a proper upgrade in many years. Unfortunately it's not what you would term a very pleasant station so better lighting, escalators, new tiling/cladding etc would be a welcome upgrade. It looks like it will have to wait a while for any of that.
A few platform end screens to slow that freezing movement of air through the tunnels would be good. There's been a few times when I've been down there when I've been convinced that it's the coldest place in the world!
 
Joined
11 Jun 2018
Messages
72
A few platform end screens to slow that freezing movement of air through the tunnels would be good. There's been a few times when I've been down there when I've been convinced that it's the coldest place in the world!
Ohh man yes I hear you there! Often blowing an absolutely freezing gale down there! Anything to minimise that would be massively welcomed.
 

applepie2100

Member
Joined
16 Aug 2011
Messages
167
I'm starting to become concerned that despite all this work we're not actually going to see a huge increase in circulating space on the concourse side of the gates. I know that things are very tight at the moment but it just seems like we're still going to have a very crowded station. If they're going to persist with the idea of the dateline then they need to change their policy for announcing platforms as it seems like this will be one of the few ways of dealing with what I fear will be inadequate circulating space.
 

Scotrail314209

Established Member
Joined
1 Feb 2017
Messages
2,353
Location
Edinburgh
I'm starting to become concerned that despite all this work we're not actually going to see a huge increase in circulating space on the concourse side of the gates. I know that things are very tight at the moment but it just seems like we're still going to have a very crowded station. If they're going to persist with the idea of the dateline then they need to change their policy for announcing platforms as it seems like this will be one of the few ways of dealing with what I fear will be inadequate circulating space.

Totally agree on this, sometimes a train heading out on an Edinburgh or an Stirling service will sit for ages without a platform, and it would then be platformed a few minutes before departure, which clogs up the concourse.
 

gghdeo

Member
Joined
21 Jan 2019
Messages
20
Totally agree on this, sometimes a train heading out on an Edinburgh or an Stirling service will sit for ages without a platform, and it would then be platformed a few minutes before departure, which clogs up the concourse.

Why does that happen, by the way? I’ve never understood late platform announcements (and changes). Surely the decisions aren’t being made in a mad rush?
 

scotraildriver

Established Member
Joined
15 Jun 2009
Messages
1,628
Why does that happen, by the way? I’ve never understood late platform announcements (and changes). Surely the decisions aren’t being made in a mad rush?
To give the cleaners a clear, quick run through every train. Trying to clean a train while passengers are getting on is nigh on impossible. Hitachi fitters also doing checks during turnaround and need access to areas of the train.
 
Status
Not open for further replies.