Booster Transformers - Scotland OLE Work

Status
Not open for further replies.

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,477
Location
Between Peterborough & Bedlington
Seeing as the old thread was closed last September, I couldn't think of where to put this.
The RSAS (Rail Systems Alliance Scotland; NR + Babcock + Arcadis) have started a relatively low-profile project nr Carstairs Jn (I say low-profile as I can't find any detailed info); piling specialists Van Elle have installed the first 4 of 210 piles in the area. https://www.linkedin.com/posts/van-elle_engineering-rail-activity-6782257371306713089-oh_b

Additionally, looking at NR's Air Ops, I've noticed all Booster Transformer locations on the Scottish network on the Carstairs-Haymarket route (ECA1-ECA3), the North Clyde Corridor west of Bathgate (NEM1-NEM7 + YKR), the Milngavie branch (MGE) and the Balloch branch (BCH) have been captured on the site.

I wonder - could the removal of these transformers be a project to keep the delivery teams busy until 'new wiring' projects arrive?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

najaB

Veteran Member
Joined
28 Aug 2011
Messages
30,692
Location
Scotland
I wonder - could the removal of these transformers be a project to keep the delivery teams busy until 'new wiring' projects arrive?
I suspect a bit of that, and a bit of "Let's do this work while we've got the skilled people around to complete it."
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,477
Location
Between Peterborough & Bedlington
I suspect a bit of that, and a bit of "Let's do this work while we've got the skilled people around to complete it."
Indeed. I'm fairly sure that booster removal was required anyway for the new feeder at Currie(hill) to improve power on the Shotts line; I can't recall where the existing feeder is on the WCML side, but it was being fed from Portobello on the ECML side.
 

MadMac

Member
Joined
13 Jun 2008
Messages
955
Location
Moorpark, CA
Indeed. I'm fairly sure that booster removal was required anyway for the new feeder at Currie(hill) to improve power on the Shotts line; I can't recall where the existing feeder is on the WCML side, but it was being fed from Portobello on the ECML side.
Trawling the memory banks here, but isn’t there a feeder at Gowkthrapple (Wishaw South)?
 

mcmad

Member
Joined
11 Mar 2015
Messages
977
The works at Carstairs are in conjunction with the renewals works coming in a year or so.
 

Scotrail88

Member
Joined
21 Jul 2014
Messages
316
is there any finalised plans for Carstairs - must be if works are contracted.
Seen multiple iterations of proposals but nothing definitive
 

Watershed

Veteran Member
Associate Staff
Senior Fares Advisor
Joined
26 Sep 2020
Messages
11,945
Location
UK
is there any finalised plans for Carstairs - must be if works are contracted.
Seen multiple iterations of proposals but nothing definitive
Last I heard it's just going to be a like-for-like renewal...
 

najaB

Veteran Member
Joined
28 Aug 2011
Messages
30,692
Location
Scotland
Last I heard it's just going to be a like-for-like renewal...
I thought that it was going to be more than like-for-like but less than what was proposed in the past (so no 100mph turnouts from the WCML to Edinburgh, etc.)?
 

InOban

Established Member
Joined
12 Mar 2017
Messages
4,208
Indeed. I'm fairly sure that booster removal was required anyway for the new feeder at Currie(hill) to improve power on the Shotts line; I can't recall where the existing feeder is on the WCML side, but it was being fed from Portobello on the ECML side.
Is Currie still happening? I thought it was associated with the wiring of the Sub and the operation of electric freights to Mossend via the ECML but that's gone very quiet.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
7,674
Location
Leeds
A question not specific to Scotland: is there a good explanation somewhere of why booster transformers are out of fashion (on non-AT lines)?

I get the impression that newly electrified lines are generally boosterless and that boosters are being actively removed on some existing lines.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,477
Location
Between Peterborough & Bedlington
A question not specific to Scotland: is there a good explanation somewhere of why booster transformers are out of fashion (on non-AT lines)?

I get the impression that newly electrified lines are generally boosterless and that boosters are being actively removed on some existing lines.
Booster transformer systems have fallen out of favour as the transformers increase the impedance of the system, thereby limiting the power capacity.
Simply converting the ECML to a boosterless classic system (using the old RC as an earth wire) and disconnecting the boosters gave enough of an increase in supply to allow an uplift in electric operation (i.e. Azumas replacing HSTs). I think A2B & Paisley Canal might well have been the last schemes to have booster transformers from new.
 

mcmad

Member
Joined
11 Mar 2015
Messages
977
Given that then what is/was the benefit to the boosters? Longer sections between feeds back when traffic volumes were low?
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,477
Location
Between Peterborough & Bedlington
Given that then what is/was the benefit to the boosters? Longer sections between feeds back when traffic volumes were low?
Maximised return current and minimised electrical interference. Section 9.4 of Garry Keenor's excellent "Overhead Line Electrification for Railways", on AC Feeding & Immunisation Methods, gives an excellent detailed explanation.
 