Status
Not open for further replies.

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
8,686
Trains were replaced by buses earlier today and it will now continue into tommorow due to an operational incident at grosmont. Anyone any idea what iit is, i must admit i first thought have NYMR done something.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

DarloRich

Veteran Member
Joined
12 Oct 2010
Messages
29,264
Location
Fenny Stratford
Never heard of buses replacing trains for a points failure! Haven't seen that listed as operational incident either before!

it might on a single track to double track connection or if a train was blocking a crossing!

Are the nymr trains still running tto whitby at this time of year

 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
8,686
it might on a single track to double track connection or if a train was blocking a crossing!

Are the nymr trains still running tto whitby at this time of year


No i dont think they are but that doesnt mean they arnt testing anything. I did think points failure but i thought that came under signal failure, i take operation incident to be something else...
 

Pumbaa

Established Member
Joined
19 Feb 2008
Messages
4,982
Have a look on ORR - there was a directive to a volunteer run railway put up recently about improving standards, but I have no idea who it was. It may have been North Yorks.
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
8,686
Have a look on ORR - there was a directive to a volunteer run railway put up recently about improving standards, but I have no idea who it was. It may have been North Yorks.

think it was wendsleydale i heard that recently in relation to sighting on crossings.
Yes it was, doesnt give much detail on ORR website but i know that crossings had something to do with it.
 
Last edited:

AlterEgo

Veteran Member
Joined
30 Dec 2008
Messages
20,153
Location
No longer here
Operational incident can usually be taken as "miscellaneous" - it is used when other standard reasons for delay don't fit.

Could be anything!
--- old post above --- --- new post below ---
Runaway carriage, according to other forums such as WNXX.

On NYMR or on NR metals?

Hmm!
 

anthony263

Established Member
Joined
19 Aug 2008
Messages
6,531
Location
South Wales
Operational incident can usually be taken as "miscellaneous" - it is used when other standard reasons for delay don't fit.

Could be anything!
--- old post above --- --- new post below ---


On NYMR or on NR metals?

Hmm!

Will have a look now although I will have to be careful as this hasn't been confirmed.

I would suggest those commenting on this thread who are registered on the wnxx forum take a look on there as there is more information.
 

theblackwatch

Established Member
Joined
15 Feb 2006
Messages
10,713
The incident occurred on NYMR metals. I understand a crane is due to attend at some point tomorrow. With this and what happened at Pontypool at the weekend, it hasn't been a good few days for preservation. I feel extrememly sorry for those involved in the preservation of the rolling stock involved who have seen their vehicles damaged, it must be heartbreaking after putting in so many hours restoration work. At least nobody was (as far as I know) injured in what happened.
 

alanf

Member
Joined
9 Jan 2010
Messages
129
Ive had an email saying a bridge bash Does this suggest a coach has hit a bridge?

Alan
 

The 39 Steps

Member
Joined
19 Jun 2011
Messages
56
2Z99 2320 (15.11.11) Knottingley to Grosmont is shown to have a crane in the consist. It was due into Grosmont at 0315 and shown with 66099 in charge. I understand a coach has gone through the buffer stop on no.2 road. It is about six feet from the NR line and not foul of it.
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
8,686
One of the Gresleys has, apparently, suffered considerable damage.

From one news report both revceived considerable damage and one may be written off... Not good news for such historic carriges. Hopefully they will get repaired but it remains to be seen.
--- old post above --- --- new post below ---
could simply be a points failure!

Well it certainly wasnt a points failure :P
 
Last edited:

The 39 Steps

Member
Joined
19 Jun 2011
Messages
56
2Z99 1830 (16.11,11) Grosmont to Tees Yard. Shown booked at Whitby 1900 to 2330 but departed 53 minutes early at 2237, Battersby 0042/0121 (Actual 2343/0014) and into Tees Yard 65 minutes early at 0045. 66099 with ADRC 96710 ZIB, ADB 975477 QPA, ADB 975087 QQA and ADB 971004 QQA in tow.
 

sidmouth

Member
Joined
11 Aug 2010
Messages
197
Location
Peterborough
Seems like some one speculates (makes a pure guess) on one forum, is then copied onto another forum as fact, then is quoted back onto the original forum as evidence...

I don't think speculation is helping any one but is damaging to the preservation movement.
 

142094

Established Member
Joined
7 Nov 2009
Messages
8,789
Location
Newcastle
That's the problem with the information age - we all want and in some cases expect the information to be there quickly but half the time it is incorrect.
 

E&W Lucas

Established Member
Joined
21 Jan 2010
Messages
1,358
Posted on the NYMR's Unofficial Forum, and others:

INCIDENT AT GROSMONT – Tuesday 15 November 2011

While attaching a locomotive to a train at Grosmont Station, the coaches ran away into a siding demolishing the buffer stop, and coming to rest having struck the parapet of an adjoining bridge on Network Rail’s Esk Valley Line. The end coach was partially derailed angled towards the Esk Valley Line. There were no staff injuries. NYMR were not running public services on this day with the train movement concerned being for internal purposes.

Unfortunately the end vehicle (Gresley Brake Third Open No 43567) has suffered significant damage, although the full extent will only be known once the coach has been recovered and examined. Although not actually foul of their running line, because of uncertainty about any possible impact on the bridge, and fears about vibration disturbing the derailed coach, Network Rail suspended the passage of trains past the site.

Recovery work was managed by DBS on behalf of Network Rail using their breakdown crane from Knottingley. Because of the difficult site location access has to be from the Esk Valley running line. NYMR participated in the recovery, which was completed late afternoon on 16th November 2011.

NYMR very much regret the incident, and the affect it had on both Northern Rail train services and Network Rail infrastructure. We especially extend our apologies for the inconvenience to Northern’s passengers. NYMR will, of course, be carrying out a full investigation, with enquiries focused on the derailed coach. Early indications suggest the incident was not due to an error on the part of any staff engaged in the train movement who acted in an exemplary manner.

The Rail Accident Investigation Branch and Office of Rail Regulation have been advised.


Philip Benham
General Manager 17 November 2011
 