Power outage at Basingstoke signalling centre

Status
Not open for further replies.

Thisisajm

Member
Joined
6 Oct 2014
Messages
57
Reading reports that there was a loss of power at the signalling centre resulting in the loss of control of signals between Farnborough and Weymouth causing major disruption on the mainline.
Would there be much in the way of backup power?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

SpacePhoenix

Established Member
Joined
18 Mar 2014
Messages
5,492
Reading reports that there was a loss of power at the signalling centre resulting in the loss of control of signals between Farnborough and Weymouth causing major disruption on the mainline.
Would there be much in the way of backup power?

Very strange, I'd have expected all large signalling centres to have backup generators that could power them for at least an hour.
 

najaB

Veteran Member
Joined
28 Aug 2011
Messages
30,770
Location
Scotland
Reading reports that there was a loss of power at the signalling centre resulting in the loss of control of signals between Farnborough and Weymouth causing major disruption on the mainline.
Would there be much in the way of backup power?
I believe that most (all?) signalling centres have backup power generators and/or UPSs.

That's no guarantee that you won't experience power outages though. A company I used to work for had both and still managed to lose all power to the building for a day and half because the box of magic that switches over to the batteries and then starts the generator in the event of mains failure (not sure what the technical name for it is) blew up when they did the monthly test of the backup generator.
 

SpacePhoenix

Established Member
Joined
18 Mar 2014
Messages
5,492
I heard a story once (don't know how true) that some company had a fully working backup diesel generator but then a new building got built next door to the generator so when the generator kicked in, it overheated and shutdown
 

lincolnshire

Member
Joined
12 Jun 2011
Messages
884
Very strange, I'd have expected all large signalling centres to have backup generators that could power them for at least an hour.

Usually a UPS to last in excess of the standby generator starting up and takeing load which then will run till the mains is restored.

Some times instead of a standby generator they have an alternative REC supply, so if the fault on the REC takes out both supplies then your up the creek without a paddle.

If you go for belt and braces back up then you would have UPS, two REC supplies and standby generator as back up .

A standby generator run for an hour? we had one run continuously for a least 2 weeks to keep the trains running, it just needed fuelling after about 5 days of running.
 

Thisisajm

Member
Joined
6 Oct 2014
Messages
57
There's a massive gas engine outside the building (just realised the building next to AA HQ is the signalling centre, isn't it?).
Would that be serving as a backup genny?
 

Attachments

  • IMG_2212.jpg
    IMG_2212.jpg
    70.7 KB · Views: 133
Last edited:

Top Cat

Member
Joined
6 Jan 2013
Messages
32
There's a massive gas engine outside the building (just realised the building next to AA HQ is the signalling centre, isn't it?).
Would that be serving as a backup genny?

The photograph appears to show the Basingstoke ROC, but this is NOT currently the signalling centre.

The current signal box is located adjacent to the station behind platform 5.
 

Thisisajm

Member
Joined
6 Oct 2014
Messages
57
The photograph appears to show the Basingstoke ROC, but this is NOT currently the signalling centre.

The current signal box is located adjacent to the station behind platform 5.

I may have jumped to conclusions on a Google search.
Am I right assuming the long term plan is to move into that building?
 
Last edited:

Sunset route

Member
Joined
27 Oct 2015
Messages
1,185
I may have jumped to conclusions on a Google search.
Am I right assuming the long term plan is to move into that building?

In geological terms, yes the aim is to use that building for signalling at some point in the long term future lmao :lol:
 

Paul180

Member
Joined
3 Jan 2010
Messages
188
Location
Do you mind I am from Surrey
I have received this email from SWT this morning and by the sounds of it there must have been a power spike of something and the protection systems must have failed big time or something similar.

Following a significant failure of the National Grid power supply to our signalling centre in Basingstoke yesterday, a large amount of signalling equipment became damaged and we were unable to run trains on some of key routes between Farnborough, Basingstoke, and the West and South West of England.

The damage to the equipment was extensive, and engineers have worked through the night to rectify the problems and bring the equipment back into working order.

The majority of signalling equipment was brought back into use at around 0600 this morning.

Services between London Waterloo, Bournemouth and Weymouth will remain significantly disrupted for some time.

We are not able to run trains between Bournemouth and Weymouth at this time, and our engineers are still working on a estimate for the repairs to these systems.

A number of buses are in place and running between Weymouth and Poole, however, these are not running to a timetable at this time. You may face a significant wait for replacement transport to arrive. We are attempting to source more buses, and will work to arrange a timetabled service so that you are able to plan your journey more effectively.

Services between London Waterloo, Salisbury and Exeter St Davids are now able to run normally, but will remain heavily disrupted. Delays of up to 40 minutes and short-notice alterations will be likely whilst we try and get the service back to normal.

As soon as more information is available, it will be provided, so please check back here regularly.

In order to help you complete your journey, we have arranged for you to be able to use your tickets on the following routes:

London Underground - services between London Waterloo and London Paddington
Great Western Railway - services on routes between London Paddington and Exeter, Bath, Bristol and Westbury.

We are very sorry for the disruption to your journey yesterday, and the continued disruption to your journey today.
 

embers25

Established Member
Joined
16 Jul 2009
Messages
1,814
I have received this email from SWT this morning and by the sounds of it there must have been a power spike of something and the protection systems must have failed big time or something similar.

By "Services between London Waterloo, Salisbury and Exeter St Davids are now able to run normally" they meant all services from Exeter cancelled until 0925!
 

Domeyhead

Member
Joined
10 Nov 2009
Messages
386
Location
The South
I heard a story once (don't know how true) that some company had a fully working backup diesel generator but then a new building got built next door to the generator so when the generator kicked in, it overheated and shutdown

Working in IT business continuity I have some war stories
A company I worked for about 20+ years ago had a very large datacentre. Near to all exits were large red emergency power off buttons, shielded from accidental depression etc. Unfortunately it didn't shield them from a determined cleaner who for some unexplained reason thought it turned all the lights out, lifted up the protective flap and .... and the UPS didn't cut in.
An even larger IT company in Portsmouth with an even larger Datacentre realised that its existing diesel generating plant would not provide a stable supply quickly enough to maintain UPS (unless left running constantly) so they installed a high capacity battery array which would provide UPS for around 30 minutes. It was installed and placed inline. Some time later a huge flashover shorted out the entire datacentre to such effect that it took nearly a week to recover all the systems, one by one. The cause was condensation on the ceiling of the battery room dripping onto terminals eventually causing an arc and a fire. When the innoccent had been sacked and the guilty promoted, the subsequent recommendation was to "bring in yet another battery solution in case the first one failed". Yep, I thought, that'll do it.

I don't think I've known a backup UPS that actually worked without problems, nor an IT system.
 

tellytype

Member
Joined
25 Feb 2016
Messages
131
Ah that set of stories sounds familiar.

Let's just say a large online payments provider when we recount this story....had a genset to support the DC in a power failure. Except it'd never been tested. Or turned on since it was installed 10 years ago...or had its fuel polished...and the changeover switch wasn't connected to anything.

One of many.......
 

philjo

Established Member
Joined
9 Jun 2009
Messages
2,892
A friend of mine said at there was a power cut at their work once where the backup generator came in so seamlessly that no-one noticed that the mains was off and everyone continued working as normal - until the generator ran out of fuel about 6 hours later.
 

Elecman

Established Member
Joined
31 Dec 2013
Messages
2,893
Location
Lancashire
Usually a UPS to last in excess of the standby generator starting up and takeing load which then will run till the mains is restored.

Some times instead of a standby generator they have an alternative REC supply, so if the fault on the REC takes out both supplies then your up the creek without a paddle.

If you go for belt and braces back up then you would have UPS, two REC supplies and standby generator as back up .

A standby generator run for an hour? we had one run continuously for a least 2 weeks to keep the trains running, it just needed fuelling after about 5 days of running.

Which is what Manchester and Rugby ROCs and WMSCC have
 

QueensCurve

Established Member
Joined
22 Dec 2014
Messages
1,912
Working in IT business continuity I have some war stories
A company I worked for about 20+ years ago had a very large datacentre. Near to all exits were large red emergency power off buttons, shielded from accidental depression etc. Unfortunately it didn't shield them from a determined cleaner who for some unexplained reason thought it turned all the lights out, lifted up the protective flap and .... and the UPS didn't cut in.
An even larger IT company in Portsmouth with an even larger Datacentre realised that its existing diesel generating plant would not provide a stable supply quickly enough to maintain UPS (unless left running constantly) so they installed a high capacity battery array which would provide UPS for around 30 minutes. It was installed and placed inline. Some time later a huge flashover shorted out the entire datacentre to such effect that it took nearly a week to recover all the systems, one by one. The cause was condensation on the ceiling of the battery room dripping onto terminals eventually causing an arc and a fire. When the innoccent had been sacked and the guilty promoted, the subsequent recommendation was to "bring in yet another battery solution in case the first one failed". Yep, I thought, that'll do it.

I don't think I've known a backup UPS that actually worked without problems, nor an IT system.

I worked on a plant with a safety critical ventilation system sopposed to switch between A and B supplies if the supply failed. When this was reuired in anger it turn out tha both supplies were fed from the same point. The was also a problem with automatic switchover to thr DG.:(
 

infobleep

Veteran Member
Joined
27 Feb 2011
Messages
12,634
Working in IT business continuity I have some war stories
A company I worked for about 20+ years ago had a very large datacentre. Near to all exits were large red emergency power off buttons, shielded from accidental depression etc. Unfortunately it didn't shield them from a determined cleaner who for some unexplained reason thought it turned all the lights out, lifted up the protective flap and .... and the UPS didn't cut in.
An even larger IT company in Portsmouth with an even larger Datacentre realised that its existing diesel generating plant would not provide a stable supply quickly enough to maintain UPS (unless left running constantly) so they installed a high capacity battery array which would provide UPS for around 30 minutes. It was installed and placed inline. Some time later a huge flashover shorted out the entire datacentre to such effect that it took nearly a week to recover all the systems, one by one. The cause was condensation on the ceiling of the battery room dripping onto terminals eventually causing an arc and a fire. When the innoccent had been sacked and the guilty promoted, the subsequent recommendation was to "bring in yet another battery solution in case the first one failed". Yep, I thought, that'll do it.

I don't think I've known a backup UPS that actually worked without problems, nor an IT system.
My UPS at home has always worked during power outage, touch wood but I'm not running a large data centre or signalling system. I also have it plugged into an extension lead that is surge protected.

Perhaps we need to bring back semaphore signals which don't need a USP. What could possibly go wrong with those! <D

It's interesting to note that around 17.30 last night why had expected the disruption to clear by 20.00. No such luck however.

Sent from my SM-G925F using Tapatalk
--- old post above --- --- new post below ---
A friend of mine said at there was a power cut at their work once where the backup generator came in so seamlessly that no-one noticed that the mains was off and everyone continued working as normal - until the generator ran out of fuel about 6 hours later.
Haha. Oops.

Sent from my SM-G925F using Tapatalk
 
Last edited:

09065

Member
Joined
20 Jan 2013
Messages
77
By "Services between London Waterloo, Salisbury and Exeter St Davids are now able to run normally" they meant all services from Exeter cancelled until 0925!

Just because they can 'run trains normally' it does not mean trains are in the right place.

Anything sat in Exeter New Yard was probably stabled and in need of a crew to travel by road or special ECS to prep the unit. What would be the point of sending crews west by road 'just in case' the line re-opened? They would have had to come back by road is the line stayed shut!
 

infobleep

Veteran Member
Joined
27 Feb 2011
Messages
12,634
Just because they can 'run trains normally' it does not mean trains are in the right place.

Anything sat in Exeter New Yard was probably stabled and in need of a crew to travel by road or special ECS to prep the unit. What would be the point of sending crews west by road 'just in case' the line re-opened? They would have had to come back by road is the line stayed shut!
Perhaps they need to reword the statement to read, trains can run normally on the line but due to X reason, we can't run trains until x time. Then no confusion.

Sent from my SM-G925F using Tapatalk
 

embers25

Established Member
Joined
16 Jul 2009
Messages
1,814
Perhaps they need to reword the statement to read, trains can run normally on the line but due to X reason, we can't run trains until x time. Then no confusion.

Sent from my SM-G925F using Tapatalk

Exactly. Also, if they had no crew in Exeter they'd have known in advance and so why did they only the cancel the 0725 and 0825 at the last minute. Also this should have been put on Journey Check and in the email instead of the statement saying things were running when they weren't.
 

infobleep

Veteran Member
Joined
27 Feb 2011
Messages
12,634
Exactly. Also, if they had no crew in Exeter they'd have known in advance and so why did they only the cancel the 0725 and 0825 at the last minute. Also this should have been put on Journey Check and in the email instead of the statement saying things were running when they weren't.
Perhaps they hoped to have someone down their but found they couldn't. However you'd hope that would be known lore than a minute in advance of the service running.

Sent from my SM-G925F using Tapatalk
 

LeylandLen

Member
Joined
28 Oct 2013
Messages
779
Location
Leyland Lancs
Did the failure of the National Grid power supply to the signalling centre in Basingstoke affect only Network Rail and TOCs? I assume the public power supply was unaffected ? No doubt there will be a big claim for compensation from National Grid ? Passengers will be making claims under Delay/Repay.
 

infobleep

Veteran Member
Joined
27 Feb 2011
Messages
12,634
Did the failure of the National Grid power supply to the signalling centre in Basingstoke affect only Network Rail and TOCs? I assume the public power supply was unaffected ? No doubt there will be a big claim for compensation from National Grid ? Passengers will be making claims under Delay/Repay.
Only if they were delayed by more than an hour. I don't know what the compensation deal would be between National Grid and Network Rail however. I've also lost track of how the finances work between South West Trains and Network Rail. Someone else is bound to know.

Sent from my SM-G925F using Tapatalk
 

embers25

Established Member
Joined
16 Jul 2009
Messages
1,814
Perhaps they hoped to have someone down their but found they couldn't. However you'd hope that would be known lore than a minute in advance of the service running.

Sent from my SM-G925F using Tapatalk

Given the 0641 is worked from the 0552 from Axminster which comes wmpty from Salisbury they would have known at 0450 when it didn't run. Equally the 0835 is formed from the 0551 from Gillingham that also didn't run and so again they would have know a long time before and yet both cancellations were not warned until the last minute. The 0725 starts from Exeter so i assume the crew for that come down on the 0552 but I could be wrong.
 

noddingdonkey

Member
Joined
2 Nov 2012
Messages
774
Interesting that SWT talk about "our" signaling centre in that email, when they could legitimately blame NR for this one

Sent from my Moto G (4) using Tapatalk
 

infobleep

Veteran Member
Joined
27 Feb 2011
Messages
12,634
Interesting that SWT talk about "our" signaling centre in that email, when they could legitimately blame NR for this one

Sent from my Moto G (4) using Tapatalk
I thought the worked along side NR, hence the we.

Sent from my SM-G925F using Tapatalk
 

lincolnshire

Member
Joined
12 Jun 2011
Messages
884
I thought the worked along side NR, hence the we.

Sent from my SM-G925F using Tapatalk

They won,t be bothered who,s signalling it is as long as they are getting the train delay payments from Network Rail into there bank account.

Hope they don,t have any train breakdowns as Network Rail will be getting some money back off them.

The joys of privatisation.
 

Elecman

Established Member
Joined
31 Dec 2013
Messages
2,893
Location
Lancashire
Only if they were delayed by more than an hour. I don't know what the compensation deal would be between National Grid and Network Rail however. I've also lost track of how the finances work between South West Trains and Network Rail. Someone else is bound to know.

Sent from my SM-G925F using Tapatalk

There is no compensation arrangement between the DNO and NR above that for any other commercial company as no DNO would enter any such agreement. In this country if you need an absolute guaranteed power supply it is upto you to make that provision for yourself. Belt braces and bits of string with multiple redundancy built into your own distribution systems. The ROCS in general are designed that way.
 