Joseph Locke's, Wrinkley's and ALX400's findings enable us to amend the worry list as follows:
1. Missing bases Salford Crescent Platform 2
2. Missing bases Pendleton Old to Cockrobin Bridge
3. Missing bases North of Agecroft Road bridge
4. Structure to be installed between Agecroft Road bridge and Clifton station?
5. Power lines oversailing between M60 and Kearsley?
6. Foot crossings either side of M60, close or bridge? Work bases appear to be in place
7. Stalactites in Farnworth Tunnel? Yes
8. Missing bases Farnworth station to Squeeze Belly Entry footbridge
9. Lever Street footbridge, demolish, replace, leave as is?
10. Missing base Bolton Platform 5
11. Stalactites in Bullfield Tunnel?
12. Missing base(s) between Bullfield Tunnel and Newport Street, Bolton?
13. Big electric kit Lostock Junction
14. Incomplete footbridge Anderton Hall Lane
15. Foot crossing between Horwich and M61, close or bridge? Foundation work may be imminent
16. Missing bases on viaduct south of Chorley? (there may be fixings on the outside of the structure)
17. Stalactites in Chorley Tunnel?