Diesels under the wires counts as a form of chaos?!
It could be if they are running 75mph Sprinters on services timed for 90/100mph EMUs and that either causes congestion or results in services being part cancelled.
Diesels under the wires counts as a form of chaos?!
My only question is how much funding has the DfT put in up front in order to get this project moving. What pressing need did GWR have that pushed them down the 769 route rather than a brand new Bi-mode, some more 387s or just use the 319s as is? The only logical answer I can see is DfT pressure, which could well be the DfT looking at the money they have already thrown at the Flex project for Northern and looking to extract more value from their investment.Porterbrook are a commercial company. They'll be a limit to how much money they can get from the government either directly or indirectly but no limit to how much of their own money they put towards it. Perhaps getting the agreement for 19 x 769s for GWR has meant they are willing to put more of their own money in?
Interesting how you set yourself up as apologist in chief for Porterbrook and Wabtec. All your posts seem to consist of 'move along, nothing to see here' and rubbish sh any post that suggests what is patently obvious - this project is turning into a total dog's breakfast.
I would suggest that rail journalists act like journalists, if I want to read pr guff from Roscos I'll get it straight from the horse's mouth, I don't expect to pay the thick end of a fiver for the privilege.
Remember a train typically lasts 30-50 years...
To add to this, and to add some background to the extent of the work which has to be done to the 319s.Load sharing between paralleled DC generators is indeed a well-established technology. The current of each generator is measured and a bias fed back to each voltage regulator to null the difference. However, it can be tricky to implement. As with any feedback loop, there is a risk of dynamic instability, such that the load oscillates between the generators until one trips out. This is particularly likely if the load is non-linear, such as a 319 traction control package. And the problem becomes more complex if the generators are driven by dedicated prime movers, such as diesel engines, which have their own feedback loops to maintain constant generator speed.
I would be surprised if the 769 designers failed to anticipate the need for load sharing, but not surprised if it has proved difficult to implement successfully.
To add to this, and to add some background to the extent of the work which has to be done to the 319s.
I attended a meeting of the IMechE in Swindon last April when a Porterbrook representative gave some details of the re-engineering necessary in turning an EMU into a DMU:
Engineering challenges included:
- a new fire barrier and fire suppression equipment has to be added under the floor of both coaches with the diesel engines
- a new 750v dc return conductor has to be fitted for the case when the train is off electrified territory as the track won't necessarily be bonded for the return current flows
- a track circuit actuator
- stuff like 1000 litre fuel tanks, exhausts and the genset rafts.
The number of design engineers and installation technicians varied between 30 and 60 people and some 45,000 engineering hours had been expended.
- Moving underfloor equipment to allow engine rafts and associated gubbins to be fitted
- design of exhaust system
- weight and balance management
- the limited equipment space envelope available
- system complexity necessary to 'trick' the control circuits into thinking the train is on a 750v dc supply
- power control systems to balance power outputs from the two ABB alternators
- the Approvals process.
One reason given for the lower power than one might expect for the train when under diesel power is that the weight of the intercoolers that would be needed to boost the power output would take the total weight over the limits allowed for an unaltered suspension.
So seems simple on the surface - but the devil is in the detail.
...who would rightly point out:The problem is South Cumbria has a group of particularly vocal MPs...
The GWR 769s are also intended to allow the North Downs route to release turbos for use in the south-west, in turn releasing 150/158s (?) that are needed elsewhere. And 387s or 319s as-is, aren't going to work well between Wokingham and Reigate...What pressing need did GWR have that pushed them down the 769 route rather than a brand new Bi-mode, some more 387s or just use the 319s as is? The only logical answer I can see is DfT pressure, which could well be the DfT looking at the money they have already thrown at the Flex project for Northern and looking to extract more value from their investment.
From what I can see the GWR 769s are only being created to allow them to take over heathrow express with an internal cascade.
You might well be right! But I would point out that:Which just confirms to me that the time, effort and money being spent on a 30 year old train which doesn't compare particularly well with a new train is just crazy.
It's difficult to not talk about the merits of the project when so little progress has been made by Porterbrook!Can I remind everyone that this is a construction and project progress thread, and that discussion of the merits or otherwise of the project is off topic!
thanks
You don't have to post if you don't have anything on-topic to say.It's difficult to not talk about the merits of the project when so little progress has been made by Porterbrook!
Porterbrook plainly don't share the pessimism on this thread as they and Wabtec are putting money and effort (and their reputations) into the project. Surely if it were impossible it would have been obvious by now?
OK, let's get back on topic...
... they're not going to be ready for fleet service for Northern by December, are they?
It's going to be a pretty dead thread without the background speculation. Without that it boils down to:
"Are they ready yet?"
"No"
Rinse and repeat roughly once each week.
Precisely, - there are threads that go into snooze mode for weeks, months even years when there isn't any progress to report on the topic. They can be read by anyone at any time but there's no need for posters to take the discussion onto a different subject just because they posters haven't got anything on-topic to contribute.I think some people come back onto these threads sporadically, looking for updates on the thread topic, but end up seeing endless posts of unrelated or semi - related things. A coomon issue with forums. Maybe we need a breaking news thread.!
I get the impression that Porterbrook might have been somewhat unprepared for the commercial interest in the 769. They may well have floated the idea to see if anybody bites, or thinking that they might get a handful of orders. When they found they had a considerable number of orders on their hands, it might have made more sense to go back to the drawing board and put in a whole lot more development than they intended when they started, because a handful of "prototypes" in service they could cope with but not a whole fleet worth!To add to this, and to add some background to the extent of the work which has to be done to the 319s.
I attended a meeting of the IMechE in Swindon last April when a Porterbrook representative gave some details of the re-engineering necessary in turning an EMU into a DMU:
Engineering challenges included:
- a new fire barrier and fire suppression equipment has to be added under the floor of both coaches with the diesel engines
- a new 750v dc return conductor has to be fitted for the case when the train is off electrified territory as the track won't necessarily be bonded for the return current flows
- a track circuit actuator
- stuff like 1000 litre fuel tanks, exhausts and the genset rafts.
The number of design engineers and installation technicians varied between 30 and 60 people and some 45,000 engineering hours had been expended.
- Moving underfloor equipment to allow engine rafts and associated gubbins to be fitted
- design of exhaust system
- weight and balance management
- the limited equipment space envelope available
- system complexity necessary to 'trick' the control circuits into thinking the train is on a 750v dc supply
- power control systems to balance power outputs from the two ABB alternators
- the Approvals process.
One reason given for the lower power than one might expect for the train when under diesel power is that the weight of the intercoolers that would be needed to boost the power output would take the total weight over the limits allowed for an unaltered suspension.
So seems simple on the surface - but the devil is in the detail.
I get the impression that Porterbrook might have been somewhat unprepared for the commercial interest in the 769. They may well have floated the idea to see if anybody bites, or thinking that they might get a handful of orders. When they found they had a considerable number of orders on their hands, it might have made more sense to go back to the drawing board and put in a whole lot more development than they intended when they started, because a handful of "prototypes" in service they could cope with but not a whole fleet worth!
I get the impression that Porterbrook might have been somewhat unprepared for the commercial interest in the 769. They may well have floated the idea to see if anybody bites, or thinking that they might get a handful of orders. When they found they had a considerable number of orders on their hands, it might have made more sense to go back to the drawing board and put in a whole lot more development than they intended when they started, because a handful of "prototypes" in service they could cope with but not a whole fleet worth!
I can’t see how you have managed to work that out. The problem isn’t that they are lagging behind on follow on orders but that they haven’t delivered anything and are months behind schedule. The sizeable follow on order for GWR will be an issue if they don’t deliver but the current issue is they haven’t delivered any of the initial order for Northern.I get the impression that Porterbrook might have been somewhat unprepared for the commercial interest in the 769. They may well have floated the idea to see if anybody bites, or thinking that they might get a handful of orders. When they found they had a considerable number of orders on their hands, it might have made more sense to go back to the drawing board and put in a whole lot more development than they intended when they started, because a handful of "prototypes" in service they could cope with but not a whole fleet worth!
I get the impression that Porterbrook might have been somewhat unprepared for the commercial interest in the 769. They may well have floated the idea to see if anybody bites, or thinking that they might get a handful of orders. When they found they had a considerable number of orders on their hands, it might have made more sense to go back to the drawing board and put in a whole lot more development than they intended when they started, because a handful of "prototypes" in service they could cope with but not a whole fleet worth!
Indeed, a more sensible plan would have been to get a prototype up and running before even accepting any orders. They could've spoken to people on the management of TOC groups (i.e parent companies rather than TOCs) to say, we're working on this idea, would you be interested? That way, they know what sort of demand there's likely to be if it works.They obviously can't cope with the 8 units they promised for Northern because they haven't been produced and the deadline for delivery has passed. The fact that GWR require 19 is irrelevant in terms of delivery of the Northern units as production on those isn't due to start until the Northern and ATW ones are in service.
Roger Ford's reported that 'dynamic testing' will occur at the end of the next week. However, he's admitted that he doesn't know what the 'dynamic testing' will entail.