Great Western Electrification Progress

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

JN114

Established Member
Joined
28 Jun 2005
Messages
3,354
Any update on 387 workings tomorrow down to Newbury? Must be working some of the peak time Paddington to Newbury services.

Yes, posted the allocations for the next few days in the Class 387 thread.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,488
Location
Between Peterborough & Bedlington
GWML Electrification: State of Play, as of 2/1/19.
All mileages given from Paddington, except where noted.
Paddington to Wootton Bassett Jct - LIVE
  • All main line tracks wired as far as Wootton Bassett Jct, and are to be considered "live" as such. The envelope of "live" wires continues along the South Wales Main Line to Filton Jct (inc. Bristol Parkway), and to the Limits of Wiring on the Berks & Hants line and Reading-Basingstoke Line; details are given below.
  • TTCs have replaced/been replacing headspans at various locations within London - locations include Westway (beneath the A40), Acton Main Line, Ealing Broadway, and between Southall & H&H. These are part of the works for the Elizabeth Line.
  • Everything wired at Reading (bar P4-6 which were never in the plan). Includes the TCD & the curves, down to Reading West (see B&H section).
  • West of Didcot Parkway, all lines are wired & live heading towards Swindon.
  • Everything wired at Swindon (bar the goods lines north of P1, where provision is provided).

Small Points
  • ATF wires in operation from Maidenhead to Wootton Bassett; Kensal Green to Maidenhead currently only using return conductors but will be AT-ready in the near future. Some AT wires up along this stretch now; whether they are live remains to be seen.
  • At Ealing Broadway, the staircase to P2/3 has been demolished and replacement with a new structure as part of the Crossrail works is now complete.
  • Parapet Work extended upwards at Southbury Lane Bridge, Ruscombe; the wing walls remain unfinished. Original Coping stones have now been replaced. Butts Hill Rd is now complete & reopened; cladding is now also complete on the outer (i.e. rail) side.
  • Platforms are being extended at Cholsey (country end), Goring & Streatley (London end), Pangbourne (country end), & Tilehurst (1 & 4 country end; 2 & 3 London end).
  • Few masts and cantilevers now up on the Didcot Avoiding Line, which finish at Appleford; Appleford LC being the limit of structures for the time being.
  • Oxford Lines west of Didcot Pkwy wired as far as the loco fuelling sdg; Down Oxford as far as 53m 31ch, Up Oxford as far as 53m 42ch. Didcot avoiding lines have sprouted masts (4 portals, 2 TTCs), with a wire pair over the Down Didcot Avoider.
  • A note on Steventon: Wires up under the High St Bridge (aka the "Brunel Bridge"); however, the bridge may well be demolished in CP6. "Temporary" parapet work to protect passers-by from stray currents now complete. Wires west of Causeway Crossing are only authorised for passenger service on 80x trains in both directions, while 387s are allowed to run empty to/from Cocklebury sidings under AC (as of 2nd January 2019). The discussion continues.
  • Overruns through Swindon Jct (77m 36ch) onto the Golden Valley Line have also been wired.
  • Swindon Cocklebury Sidings live for electric traction as of 0700hrs on Sunday 9th December - no authorisation for its use has yet been given.

The "Main Line"; Wootton Bassett Jct - Chippenham (Cocklebury Lane Bridge)
Until further notice, the 25kV transmission wires will run in a trough from Cocklebury Lane Bridge (just east of Chippenham) to Thingley Jct. Large steelwork is expected to remain in situ until wiring is authorised west of Thingley, but some specific items may be poached if required elsewhere (and duplicates aren't stored at RAF Wroughton). Details given in the "Postponements" section.
  • Both lines are wired throughout from Cocklebury Lane to Wootton Bassett, and both earth wires have been fully run.
  • ATF wires are now up from Wootton Bassett as far as the transformer at Christian Malford. As yet, they do not continue west.

Chippenham (Cocklebury Lane Bridge) - Thingley Jct
  • No piles in Chippenham station, nor any masts affixed to the viaduct.
  • All piles in and majority of masts (and cantilevers) up from the western end of the viaduct to Thingley Junction (where the feeder station will be). Most TTCs have booms from beyond the viaduct to Thingley East Junction. About 14 masts are up in the vicinity of Thingley Feeder Stn, 2 of which have TTC booms affixed. Another has an STC boom.
  • Piles continue westwards to the next bridge.

Thingley Jct - Keynsham
  • No wiring for the foreseeable future, but overbridges between Thingley Jct & Box Tunnel have all been rebuilt. Corsham Main Road Bridge needs its parapets raising. New aqueduct & footbridge at Corsham complete.
  • Both Box & Middle Hill Tunnels have had track lowered.
  • A new footbridge has been built at Ashley Box.
  • Piles also in (and have been for over a year) at Ashley (beyond Box Tunnel) - these might well be trial piles.
  • Bathampton Jct to beyond Sydney Gardens has had track lowered. A new signal gantry at Bathampton Jct was installed over Xmas 2017 but is not yet in use.
  • Bath Spa platforms realigned & raised, with track also slewed.
  • Track through Oldfield Park & Keynsham now lowered.
  • A lot of piles are in along the embankment around Saltford and Keynsham in readiness for future wiring.

South Wales Main Line (Wootton Bassett Jct-Bristol Parkway-Severn Tunnel-Newport-Cardiff)

Wootton Bassett Jct to Filton Jct (inc. Bristol Parkway) - LIVE
  • Wires from Wootton Bassett Jct to Bristol Parkway now in passenger service, as of 30/12/18. Live wires continue to Filton Jct & Stoke Gifford IEP Depot; Chipping Sodbury Goods Loop and the Cheltenham Curve overrun (as far as the limit of wiring) are also fully wired and live.
  • BPW Platforms fully wired, along with the Down Goods Loop & Up Passenger Loop.
    • A number of masts & booms (now all wired up) are up on the line towards Filton Abbey Wood, between Stoke Gifford Jct No.1 (111m 79ch) and Filton Jct No.1 (113m 01ch); these end just short of Filton Jct 1 and will presumably act as an overrun until electrification continues into Temple Meads.
    • Section Isolator Masts installed immediately east of Stoke Gifford Jct No. 1, for the neutral section just west of BPW. This is the current live limit.
  • Filton Bank bridge works (mileages all from Temple Meads):
    • Easton Rd Overbridge (1m 18ch) completely rebuilt.
    • Narroways FB (2m 12ch) & Ashley Hill FB (3m 11ch) replaced.
    • Bonnington Walk Overbridge (3m 62ch) - parapets raised.
    • FB south of Filton Abbey Wood (4m 18ch) will need work if wiring is to occur.
Filton Jct - Severn Tunnel
  • The Patchway/Severn Tunnel Blockade is now complete.
  • Stoke Gifford IEP Depot all wired.
  • Patchway Tunnels conductor rail installed.
  • Masts, booms and SPS up through Patchway. No wires yet.
    • Cattybrook Brickworks Bridge closed as of 18/3/18.
  • At Pilning, during the Summer Tunnels blockade, all portals and masts have now been erected, and wires have gone up (west of the station). Earth wires and C&C wires are now up eastwards from this wired section, through the station, to the split-level section before the Patchway Tunnels. The Down line is fully wired here, while the Up line still needs finishing work in a few places.

Severn Tunnel - Newport
Due to have IETs in AC service by next year - hopefully sooner!
  • Severn Tunnel Conductor rail in place. A number of masts on both sides of the line are now up at Caldicot, just before the Western tunnel mouth; these now extend westwards towards the eastern end of the platforms at STJ.
  • Part of the central island platform at Severn Tunnel Junction has been fenced off - a possible mast location?
  • Many masts now up west of STJ, and many of them have portal/TTC booms.
  • Feeder cables now hang from the eastern set of Switchgear Masts; the western set are all up, but uncabled.
  • All bridge rebuilding complete from Severn Tunnel Jct (149m 14ch) to Bishton Flyover (152m 30ch).
  • Masts going up between Severn Tunnel Jct & Bishton Flyover. These include:
    • At least 11 between Undy (Church Rd Bridge) and the M4 viaduct over the mains; one just east of the "white house" has a TTC boom. It can be assumed that its 8 comrades will be similarly adorned. Another mast over the Reliefs west of the "white house" has now gained a TTC boom with 1 SPS assembly; it has a twin over the Mains.
    • Two opposing pairs of TTC masts have gone up between Church Rd Bridge & the Playing Fields Footbridge.
    • Two large uprights have gone up between Undy Playing Fields footbridge & "the ramp" bridge at Magor on opposite sides of the line; these may well take a portal boom.
    • Another 3 masts (two for a portal boom, one a TTC with boom up) have appeared east of "the ramp" bridge at Magor; these join the sole TTC on the Up side by the bridge.
    • 3 of the 4 TTCs west of "the ramp" bridge (2 on the Down side, 1 on the Up side) bear SPS; a 4th TTC has been boomed on the up, opposite the more western boom on the Down side.
    • The signal gantry at Magor (west of the West End Footbridge) has been replaced by 4 signals on posts; this should mean its removal prior to electrification is imminent. A TTC with SPS is up over the Mains there too.
    • 1 mast is up to the west of Redwick Rd Bridge (by the Down Relief), and a mast due to bear a portal is up to the east of Whitewall Footbridge (by the Up Main). A "Slim" TTC is up over the centre pair of lines just east of Redwick Rd bridge. OTP is in place for a masting operation by Redwick Rd compound.
    • One 4-track portal is up between the A4810 and the bridge over the eastern end of Bishton Flyover.
    • Masts (with SPS fitted) up between Bishton Flyover (including over it) and Llanwern West Jct (156m 20ch). 5 masts are currently up on the curve down from the flyover at its eastern end.
    • Plenty single masts (with SPS fitted & folded) up along the Mains between the Flyover and Bishton LC. A run of Earth wire is now up on the Up side at Bishton.
  • Between Bishton LC (153m 01ch) and Llanwern Golf Course, masts are around 90-95% up (all bar a few have booms and SPS), with the main gap at Llanwern Works East Connection (153m 05ch). This continues west towards Llanwern Works West Connection/Llanwern West Junction (156m 03ch to 156m 20ch). 4 masts (3 over the Mains, 1 over the Reliefs) also have booms & SPS immediately west of the LC.
  • A run of Earth Wires & ATF wires have been strung up on the Relief side (adjacent to the DR) between Llanwern Works East Connection & Llanwern West Jct.
  • All 4 lines are now wired past Llanwern Steelworks.
  • Some masts have sprouted near Lliswerry pond.
  • Piling taking place until Christmas Eve between Lliswerry & Maindee - presumed complete.
  • 6-track portals, probably TGBUs (aka Thumpin' Great Big-Uns) going up aroung East Usk Yard (approx. MP157 1/2).
  • Between the Maindee Jcts (157m 74ch to 158m 16ch), a cluster of piles is in beside the Down Relief; these are complemented by masted piles on the Main side (adjacent to the Up Main).
  • Caerleon Rd Overbridge to be refurbished in 2 phases - 20/7 to 30/11, and then January ‘19 to March ‘19. Not sure what impact on wiring this will have.
  • Some SPS has now gone up between Maindee West & Maindee East; between Maindee West Maindee North Jct (41m 03ch from the former Rotherwas Jct, just south of Hereford; the ELR for the southern part of the Marches Line), masts with TTCs on are also going up (as overruns) over the Marches Line; the termination mast & associated TTC are just north of signal "NT 1559".
  • Fixings for masts have now been installed on the Usk Bridge.

Newport
  • All canopies now cut back.
  • Masts and portals now appearing at the western end of the station, some with SPS attached. More started to appear in mid-April; additionally, two at the Cardiff end & two through the P1 canopy on the weekend of April 28th/29th.
  • 4-track portal now up over the southern 4 tracks, just east of the new station footbridge.
  • Two six-track portals have now gone up over the western throat of the station, just short of a 4-track portal (uprights of) & a TTC (with SPS) adjacent to Clytha Park Rd.
  • Old stn footbridge now removed; 4-track portal of the "TGBU" (Thumpin' Great Big 'Un) variety has been installed in its place.
  • A new portal has gone up at the east end of Newport, with all the fixings for switchgear affixed at the top. Droptubes for registration arms are also on.

Newport - Cardiff
  • Plenty masts up around Gaer Jct (159m 32ch) north of Cardiff Rd Bridge (the B4237):
    • one by the Down Relief;
    • two by the Up Main (one of which is a boomed TTC with SPS);
    • three by the Gaer Jct - Park Jct Chord.
  • Around 6 piles are in adjacent to the Up Main between Gaer Jct and Ebbw Jct (160m 07ch); these will probably take masts for portal booms. One such boom appears to have gone in! Currently unknown if Alexandra Dock Jct Yard will be electrified.
  • Lots of steelwork up immediately behind the signal gantry adjacent to the Up Main at Ebbw Jct; this includes a full portal boom and a TTC acting as an overrun mast on the Ebbw Vale branch.
  • Over 100 masts from Ebbw Jct to Marshfield (163m 60ch). Booms & SPS starting to appear in the area too.
  • Green Lane Bridge, nr Marshfield (164m 57ch) reopened to traffic after reconstruction. Masts (with SPS) up around here too.
  • Lots of masts (with booms, SPS & ATF brackets) now up near Mardy Rd Bridge, Rumney.
  • Two TTCs, one on each side of the tracks, have been erected by the bridge at Rhymney River Bridge Jct (167m 61ch).
  • Wires up across all 4 tracks between Pengam Jct & Wentloog FLT - legnths of these are all unknown.
  • About 4 or 5 portals have been erected just west of Pengam Jct (168m 40ch); 5 masts are up on the Up side east of Rover Lane bridge, complemented by 2 on the Down side. Some of the portals now have booms, and bear SPS; one of these has all its registration arms up.
  • 1 run of C&C has gone up between Moorland Road Jct (168m 65ch) and Long Dyke Jct (169m 35ch) over the Reliefs; this is assumed to be a crossover as it crosses from one Relief line to the other.
  • A handful of masts are also up around Long Dyke Jct; some have now gained TTC booms and SPS as well.
  • Over the bridge over St. Mary's Street in Cardiff (just east of Central), and immediately to the west of the bridge, 5 portal booms spanning all tracks have gone up.
  • Similar bespoke mast foundations are going in just east of Bute St Bridge, near the junction with the line from Queen Street.
  • Splott Rd Bridge upgrade work now complete.
Cardiff Central - Platforms 0-4 to be wired
  • Re-signalling completed. Platform 0 now open. 3 masts now up over P0/1 with TTC booms.
  • Piling underway at the extreme ends of P1/2 & P3/4 for future masts. One can assume portals will bridge the gap between P2 & P3, over the Through lines.
  • Canopy cut-back work now underway on P2.
  • Brackets appear to be in place on the coping stones on the Taff Viaduct (at the western end of the station).
  • Plenty piles up adjacent to Cardiff Canton.
  • Brickwork Sidings to be increased in length (and electrified) to accommodate GWR Class 387s.
  • Proposed Limit of Wiring: Leckwith Loop North Jct (171m 55ch) at a guess.
Swansea IEP Depot
  • New IEP Depot at Maliphant Sidings, Swansea now complete; all steelwork up but no wires.

GWML/SWML Blockade Works (2018):
  • 6/7 to 3/12: Reduced capacity (2 lines only) for wiring work between Newport & Cardiff Ctl.
  • 15/9 to 6/10, and 13/10 to 14/10: Bristol Parkway electrified.
  • 27/10 to 18/11, 24-25/11, 1-2/12: Filton Bank 4-tracked.
  • 11/11: Bristol TM to Bath Spa resignalled.
  • December blockades at Bristol Parkway & Didcot Parkway done.

GWML/SWML Blockade Works (2019):
  • 25/12/18 to 1/1/19: Bristol Parkway - Newport will be blockaded again, due to electrification work at Severn Tunnel Junction; done.
  • More Blockades will follow; details as they become available.

Berks & Hants Line (Reading-Newbury) - LIVE
Electric trains are set to be in squadron service from January 2019.
  • Wires from Oxford Rd Jct are now LIVE to the limits of electrification (53m 42ch on the Newbury Lines, 38m 07ch on the Basingstoke Lines) as of 0650 on 21/10/18.
  • Class 387s are now in service on Reading-Newbury services as of 31/12/18. What a way to ring in the New Year!
  • Within Reading West, piles for the new footbridge (under Murphy's remit) are in, but have been "decapitated" (i.e. shortened) and capped until a new footbridge solution is found.
  • Extension to Reading West Up platform complete, but not yet authorised for use. A new camera of sorts has appeared, and new station signs (GWR-style) have been erected.
  • Parapet work for Tilehurst Rd overbridge is now underway; the bridge has now been reduced to single-lane working for road traffic.
  • Platforms extended at Theale, Aldermaston and Thatcham.
  • Newbury's new footbridge is now open - the lifts are not yet working, causing much local amusement/bemusement.
  • Immunised signalling continues to about MP55 1/2. Bedwyn Turnback Siding now extended to accommodate 5-car IETs.

Project Postponements
  • Thames Valley Branches: Windsor & Henley deferred to CP6. Marlow removed from scope of current programme. The first few yards of each branch (bar the Henley Branch) have been wired as an overrun.
  • Southcote Jct to Basingstoke has also been deferred to CP6.
  • Appleford LC to Oxford paused; if CP6 accounts allow for wiring to be extended to Oxford, it would be very likely to happen now that Oxford has been remodelled.
  • Catenary & Contact wires between Chippenham (Cocklebury Lane Overbridge) & Thingley Jct have been deferred until (presumably) CP6. All Large steelwork to remain, unless required elsewhere.
  • Bristol Temple Meads to Bath & Bristol Parkway paused, dependent on Bristol resignalling (Taunton-Parkway over Easter 2018, Temple Meads to Bath in November 2018 - both done; the WSM stretch from Flax Bourton Tunnel to Cogload Jct remains outstanding), track remodelling and Filton Bank 4-tracking (done).
  • Bristol Temple Meads' "Midland Shed" to be reopened in CP6, after Bristol resignalling is complete and the PSB is demolished.
As always, do let me know if I've missed anything!
(apologies to anyone who saw it in a state of source code chaos too).
 
Last edited:

Kite159

Veteran Member
Joined
27 Jan 2014
Messages
19,226
Location
West of Andover
Sounds like theret is overhead wire problems between Midgham & Thatcham, or has a 387 broken down?
 
Last edited:

317362

Member
Joined
7 Sep 2017
Messages
202
Looks like 1z99 heading to p1 Newbury to rescue a stopper, so interested if it is a Turbo or 387 (and what's rescuing...)
 

Thatcham Xing

Member
Joined
1 Nov 2016
Messages
173
Sounds like theret is overhead wire problems between Midgham & Thatcham, or has a 387 broken down?

Not sure what's happened but 2K46 (a 387) has made it slowly to Newbury around an hour late.

Another 387, headcode 1Z99 has just arrived in Newbury and looks to be attaching to the problem one, from what I can see on the Newbury Railcam.

EDIT: Looks like the resulting 8-car will leave Newbury as 5Z71.
 
Last edited:

Kite159

Veteran Member
Joined
27 Jan 2014
Messages
19,226
Location
West of Andover
A slightly poor picture (window on this 165 of isn't that clean) of the 2 units (387151 & 387171) attached at Newbury
 

Attachments

  • IMG_20190102_131439993.jpg
    IMG_20190102_131439993.jpg
    2.9 MB · Views: 159

Thatcham Xing

Member
Joined
1 Nov 2016
Messages
173
Here's the 8-car 5Z71 leaving Newbury (from Newbury Railcam), pan was clearly down on the rear unit as it passed the camera.387troubleNewbury020118.png

Not great on one of the first days of electric ops :'(
 

Dren Ahmeti

Member
Joined
17 Oct 2017
Messages
550
Location
Bristol
“2K46 (1114 Reading to Newbury) has come to a stand for a 2nd time on approach to Thatcham after a reported loss of line light and now unable to raise pantograph.
1st report was in Midgham area.“
 

FGW_DID

Established Member
Joined
23 Jun 2011
Messages
2,727
Location
81E
Last GWR units to stable at Maidenhead Carriage Sidings left this morning, Swindon Cocklebury Sidings in use as of tonight.
 

Dren Ahmeti

Member
Joined
17 Oct 2017
Messages
550
Location
Bristol
Last GWR units to stable at Maidenhead Carriage Sidings left this morning, Swindon Cocklebury Sidings in use as of tonight.
Lots of sitting around in the loops at Wantage Road/at Didcot West End on the ECS paths!
Interesting to see how the ECS will be affected by late running down the Swindon - Didcot Parkway section.
 

DidcotDickie

Member
Joined
12 Mar 2017
Messages
159
Location
Oxfordshire
Lots of sitting around in the loops at Wantage Road/at Didcot West End on the ECS paths!
Interesting to see how the ECS will be affected by late running down the Swindon - Didcot Parkway section.

It looks like four services are stabled at Swindon Cocklebury overnight

http://www.realtimetrains.co.uk/search/advanced/DID/2019/01/03/0000-2359?stp=WVS&show=all&order=wtt

5P01 05:00 and 3P08 05:45 from Swindon Cocklebury appears to be scheduled to run on the mains from Highworth Junction to Didcot (the latter waits at Didcot West End).
http://www.realtimetrains.co.uk/train/C53027/2019/01/03/advanced
http://www.realtimetrains.co.uk/train/C53010/2019/01/03/advanced

The other two - 5P06 05:30 and 5P15 06:15 are both looped at Challow and wait at Wantage Road.
http://www.realtimetrains.co.uk/train/C53029/2019/01/03/advanced
http://www.realtimetrains.co.uk/train/C58502/2019/01/03/advanced

As you say, it'll be interesting to see how badly affected these ECS workings are by late-running IETs.
 

ATW158Xpress

Member
Joined
6 Dec 2016
Messages
287
Seen 2 800 running on diesel only between Bristol Parkway and Swindon. Are all trains being temporarily barred running on electric between these stations today?
 

Dren Ahmeti

Member
Joined
17 Oct 2017
Messages
550
Location
Bristol
As you say, it'll be interesting to see how badly affected these ECS workings are by late-running IETs.
By late-running HST’s, you mean? :lol:
The IET’s are performing pretty flawlessly on electric, bar today’s Helium balloon fiasco that tripped the OLE at Paddington :oops:
 

Thatcham Xing

Member
Joined
1 Nov 2016
Messages
173
“2K46 (1114 Reading to Newbury) has come to a stand for a 2nd time on approach to Thatcham after a reported loss of line light and now unable to raise pantograph. 1st report was in Midgham area.“

Perhaps an isolated problem with that unit earlier as 387's appear to be running to time down to Newbury now?
 

FGW_Lad

Member
Joined
19 Mar 2011
Messages
142
Location
Berkshire
Are the wires on the B&H line set higher up than the GW mainline as the pantograph on the video shows the 387 at a higher setting?

 

Thatcham Xing

Member
Joined
1 Nov 2016
Messages
173
Are the wires on the B&H line set higher up than the GW mainline as the pantograph on the video shows the 387 at a higher setting?


The second 387 in that clip was going at some lick past Colthrop Crossing if it was going to stop at Thatcham!
 

cambsy

On Moderation
Joined
6 Oct 2011
Messages
899
Will an IET on the Berks and Hants put its pan up and down in Newbury platforms and on the through lines when passing through non stop at speed? Or is there a point like Moreton cutting where they do it instead?.
 

spark001uk

Established Member
Joined
20 Aug 2010
Messages
2,325
I had just arrived at nby (wrong road p2) on 1C81, when the stricken unit was just being dragged out of p1.
 

Kite159

Veteran Member
Joined
27 Jan 2014
Messages
19,226
Location
West of Andover
I had just arrived at nby (wrong road p2) on 1C81, when the stricken unit was just being dragged out of p1.

It isn't wrong road going into platform 2 from the racecourse direction as the signalling allows it (and it gets used at least once a day when the 16:49 Reading - Bedwyn service gets overtaken by the 16:33 Paddington - Exeter service).
 

JN114

Established Member
Joined
28 Jun 2005
Messages
3,354
There are some 387/OHLE compatibility issues on the B&H - they’re very minor; and should be rectified within coming days; but various units banned from B&H work until rectified.

Expect occasional Turbo vice Electrostar substitutions over coming days.

As far as I’m aware the issues do not effect IETs, which will continue to use AC power between Kennet Viaduct (East of Racecourse) and London.
 

Grumbler

Member
Joined
27 Mar 2015
Messages
508
There are some 387/OHLE compatibility issues on the B&H - they’re very minor; and should be rectified within coming days; but various units banned from B&H work until rectified.
So, another cock-up by NR!
 

Thatcham Xing

Member
Joined
1 Nov 2016
Messages
173
Expect occasional Turbo vice Electrostar substitutions over coming days.

Looks like one 387 and one Turbo on the Reading-Newbury shuttles so far today.

1K04/1K11 was also a Turbo today (a first I think!) after being a 387 yesterday (and an HST or 5-car IET over the previous few weeks)
 

JN114

Established Member
Joined
28 Jun 2005
Messages
3,354
So, another cock-up by NR!

I think it’s a bit 50/50 to be fair to NR - in short the over height sensors on some 387 pans are too sensitive; but if the OHLE is all built to design geometry it shouldn’t be over height anywhere.
 