• Our booking engine at tickets.railforums.co.uk (powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Crossrail opening delayed (opening date not yet known)

Status
Not open for further replies.

Ken H

On Moderation
Joined
11 Nov 2018
Messages
6,287
Location
N Yorks
Commonly known a "Greenshifting" where at every tier of management there is a preference to report the good news (green) rather than the bad (red). The further the reports go up the ladder the more the news shifts to the green so by time it reaches board/ministerial level it looks like everything is going fine... until it's too late.

It's probably not surprising that the whole project is going to be late and over budget considering how big and complicated it was but maybe the warning signs should have been recognised and addressed earlier
If thats allowed to happen it shows appalling project management. Checking each component is on time properly is more then asking staff if everything is going OK. Its actually checking real progress. Line managers should show they have checked stuff is actually done, and regular scrums allow peers to see if there is an issue somewhere.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

samuelmorris

Established Member
Joined
18 Jul 2013
Messages
5,121
Location
Brentwood, Essex
No, they meant Siemens.

Siemens is installing the signalling equipment and these days a lot of it is in the train and has to 'talk' to the train's control system.

Because Bombardier's software was late, Siemens could not complete or test the integration of their on-board systems with Bombardier's kit.

So Siemens knew the trains were late.
From very much an outsider's perspective it sounds like if there were issues in Siemens' area, they have been overshadowed by the issues with the trains themselves, which in turn are overshadowed by the infrastructure delays at Crossrail's end. Doesn't sound like Siemens are that much in the wrong, at least not yet. They took the effort to warn about delays the earliest and seem to have been fairly forthright about the issues they're dealing with.
 

GreatAuk

Member
Joined
16 Jan 2018
Messages
60
Oh dear :D. I did enjoy it at the time though... I wonder how many people they talked to for the 'final countdown' (season 2) already had an inkling things might not be going quite according to plan even as they gushed about the artistic station design.

I suspect a lot of media Crossrail has put out won't have aged very well, as looking back they've been quite good at completely ignoring certain issues whuch are now apparent, and repeatedly unleashing the 'on time and on budget' catchphrase whenever possible.
 

plcd1

Member
Joined
23 May 2015
Messages
788
That BBC documentary The Fifteen Billion Pound Railway is back on iPlayer. It hasn't aged very well.

I only caught the tail end but it did feel like a massive and sad anticlimax given where we've ended up. It was nice seeing the Farringdon project manager again - I've met her on a visit and she's quite a character. Seeing them sort of "crowing" about "progress" at Whitechapel made me a tad cross because it's been evident for a long time it was way way behind schedule and still is.

I suppose there is a bit of a warning for future big infrastructure projects about letting the cameras in while you're building stuff. There's no doubt there's a public interest in seeing how stuff is built but the risk of appearing a bit glib or smug is ever present if things later go pear shaped. I wonder if we will see a change in approach which focuses more on pure technical achievement and less on wider project promotional "upside" which was clearly part of the Crossrail plan in supporting this TV series?
 

ijmad

Established Member
Joined
7 Jan 2016
Messages
1,810
Location
UK
I wonder if they actually did the filming for the third series. I feel like it should eventually be broadcast, as while it might seem like a bit of an anticlimax, it would show people how difficult things really have been and make explaining what went wrong much more personal and relatable. After all, we can't learn from others if problems are constantly brushed under the carpet and forgotten about.

Perhaps it will be aired along with a final opening episode when the thing does eventually get off the ground.
 

Malcolmffc

Member
Joined
19 Mar 2017
Messages
300
I wonder if they actually did the filming for the third series. I feel like it should eventually be broadcast, as while it might seem like a bit of an anticlimax, it would show people how difficult things really have been and make explaining what went wrong much more personal and relatable. After all, we can't learn from others if problems are constantly brushed under the carpet and forgotten about.

Perhaps it will be aired along with a final opening episode when the thing does eventually get off the ground.

Perhaps with the title changed to The Seventeen Billion Pound Railway?
 

iphone76

Member
Joined
6 Nov 2010
Messages
917
Location
South Essex
I wonder if they actually did the filming for the third series. I feel like it should eventually be broadcast, as while it might seem like a bit of an anticlimax, it would show people how difficult things really have been and make explaining what went wrong much more personal and relatable. After all, we can't learn from others if problems are constantly brushed under the carpet and forgotten about.

Perhaps it will be aired along with a final opening episode when the thing does eventually get off the ground.

They did and still are filming.
 

matt_world2004

Established Member
Joined
5 Nov 2014
Messages
4,504
The documentary is still a valuable historical record of how they built a railway line in early 21st century London.
 

samuelmorris

Established Member
Joined
18 Jul 2013
Messages
5,121
Location
Brentwood, Essex
Another great article from London Reconnections here:

https://www.londonreconnections.com/2019/crossrail-getting-a-grip/

Looks like 2020 will be the earliest. Huge problem with NR needing to reconfigure platforms 16-18 in Summer 2019 for longer trains - and potentially Liv St Low Level will be used for Shenfield trains and then reversed!

Doesn't really make a lot of sense to me. If you can run the trains through the tunnel at all, why stop at Liverpool Street? If Farringdon station is due to be handed over in the Spring and that work's scheduled for the summer, you may as well terminate them at Farringdon and get some utility out of it. (assuming Fisher Street crossover is west of Farringdon station, if it's underneath the street of that name I imagine it is but I haven't seen the track diagram).
The TfL Rail peak service may not be as intensive as the full Crossrail core service but it's busy enough that the signalling system will have to be operational down there. Given we're supposed to have a full year of testing ahead, I can't see that being very realistic. I'm not even sure it'd be safe to send them west of Stratford down there to turn around empty with no signals.

Personally I only see two outcomes - either the Liverpool St remodel and all projects reliant on it slip back a year, or it carries on regardless and for the few months it takes to complete the TfL Rail peak service is reduced to 6tph terminating at Stratford with replacement buses in continuous operation to supplement the service frequency via Newbury Park as they currently do during engineering works. I think the former is probably more likely.

The other possibility is of course that the December 2019 PRM derogation doesn't happen and with a large proportion of Anglia services suspended until new rolling stock arrives, 345s get clearance to use platforms 8-14 at Liverpool St as well.
 

Taunton

Established Member
Joined
1 Aug 2013
Messages
10,066
Well since the announcement last summer of the delay, there seems to have been no testing at all. I haven't seen a single train on the open section through Custom House.

For the hundreds of staff recruited and trained for the start last December, what are they doing?
 

bramling

Veteran Member
Joined
5 Mar 2012
Messages
17,747
Location
Hertfordshire / Teesdale
Well since the announcement last summer of the delay, there seems to have been no testing at all. I haven't seen a single train on the open section through Custom House.

For the hundreds of staff recruited and trained for the start last December, what are they doing?

I know the control room staff have been doing some knowledge-gathering out and about elsewhere within TFL - spending time in LU control rooms and with incident response staff. No doubt they’ve been spending time with similar staff around the big railway too.
 

Taunton

Established Member
Joined
1 Aug 2013
Messages
10,066
It does surprise me that there are potentially hundreds of trained staff standing by here (they will start to lose them), while the Goblin train issues cannot temporarily redeploy surplus stock from other places because there are not staff of the "right type" apparently to handle the half a dozen or so trains in circuit.
 

700007

Established Member
Joined
6 May 2017
Messages
1,195
Location
Near a bunch of sheds that aren't 66s.
The staff that have been recruited particularly for the Central Section stations have been temporarily deployed at Eastern/Western stations (and Abbey Wood) on extra duties to help out around various stations during the day. So for example, stations that have had only the one staff member now have two or three rostered at the same time. Similarly, those originally with two or three now have had a top up if necessary of one or two extra people.
 

colchesterken

Member
Joined
12 Oct 2010
Messages
764
From what little I have seen they seemed to lack " get up and go " I used to live in Forest Gate and go back from time to time, for meetings etc.
The Job there was to demolish the staircases and rebuild 1/2 as wide with a lift taking up the other half, It has taken 3 yrs
Not been back but I assume it was finished in the Christmas works shutdown
 

matt_world2004

Established Member
Joined
5 Nov 2014
Messages
4,504
Platform 5 has been further extended in length at Hayes.the buffers are still in the same position
 

pacenotes

Member
Joined
4 Mar 2017
Messages
104
Platform 5 at West Drayton is getting built and 3 and 4 are also getting lengthened.


I seen a walkway went in at West Eailing over Christmas too.
 

theironroad

Established Member
Joined
21 Nov 2014
Messages
3,697
Location
London
The staff that have been recruited particularly for the Central Section stations have been temporarily deployed at Eastern/Western stations (and Abbey Wood) on extra duties to help out around various stations during the day. So for example, stations that have had only the one staff member now have two or three rostered at the same time. Similarly, those originally with two or three now have had a top up if necessary of one or two extra people.

Interesting, that probably explains why at the tfl platform at Ealing Broadway there always seem to be a group of 4 near rear of train on the platform.
 

TFN

Member
Joined
17 Aug 2017
Messages
353
Location
London
Ealing Broadway is a weird one in itself as they have shut the main staircase leading to the NR platforms since December. I think they're installing a lift shaft or foundations there. So access to Platform 3 is via the footbridge on Platform 4.

There's close to 5/6 staff in the peaks on the two platforms with megaphones. Got shouted at once for walking outside of the yellow line trying to overtake some slow people.

Is the staircase reopened? I haven't been to the station since before Christmas.
 

iphone76

Member
Joined
6 Nov 2010
Messages
917
Location
South Essex
From what little I have seen they seemed to lack " get up and go " I used to live in Forest Gate and go back from time to time, for meetings etc.
The Job there was to demolish the staircases and rebuild 1/2 as wide with a lift taking up the other half, It has taken 3 yrs
Not been back but I assume it was finished in the Christmas works shutdown

The stairs opened at the end of November / beginning of December, but the lifts still say "Lifts Coming Soon". I saw on twitter today they said they would be operational by the end of February.

They took away the temporary stairs from Manor Park over the Christmas break, but the temporary bridge and stairs at FG are still present.
 

Sebastian O

Member
Joined
18 Feb 2015
Messages
164
Platform 5 at West Drayton is getting built and 3 and 4 are also getting lengthened.


I seen a walkway went in at West Eailing over Christmas too.
Where/why is WD having a fifth platform added? Is this not just the freight avoiding line?

On this, was the freight avoiding line added for XR or was this already in place for the Colnbrook line?
 
Status
Not open for further replies.

Top