• Our booking engine at tickets.railforums.co.uk (powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Great Western Electrification Progress

Status
Not open for further replies.

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,492
Location
Between Peterborough & Bedlington
From Network Rail's website:
Saturday, 3 August 2019 – Friday, 16 August 2019
Piling will be undertaken in the following locations:

  • Cardiff Central, Riverside (Cardiff)
Erecting masts and overhead line equipment will be undertaken in the following locations:

  • Rogiet, Magor (Monmouthshire)
  • Baneswell, Somerton, Maindee, Newport Station (Newport)
  • Rumney, Pengham, Wentloog, Adamsdown, (Cardiff)
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,492
Location
Between Peterborough & Bedlington
GWML Electrification: State of Play, as of week commencing 5/8/19.
All mileages given from Paddington, except where noted.
Paddington to Wootton Bassett Jct - LIVE
  • All main line tracks wired as far as Wootton Bassett Jct, and are to be considered "live" as such. From Wootton Bassett Jct, the envelope of "live" wires continues along the South Wales Main Line to Filton Jct (inc. Bristol Parkway), and to the Limits of Wiring on the Berks & Hants line and Reading-Basingstoke Line; details are given below.
  • TTCs have replaced/been replacing headspans at various locations within London - locations include Westway (beneath the A40), Acton Main Line, Ealing Broadway, and between Southall & H&H. These are part of the works for the Elizabeth Line.
  • Everything wired at Reading (bar P4-6 which were never in the plan). Includes the TCD & the curves, down to Reading West (see B&H section).
  • West of Didcot Parkway, all lines are wired & live heading towards Swindon.
  • Everything wired at Swindon (bar the goods lines north of P1, where provision is provided).

Small Points
  • ATF wires in operation from Maidenhead to Wootton Bassett; Kensal Green to Maidenhead currently only using return conductors but will be AT-ready in the near future. Some AT wires up along this stretch now; whether they are live remains to be seen.
  • Parapet Work extended upwards at Southbury Lane Bridge, Ruscombe; the wing walls remain unfinished. Original Coping stones have now been replaced.
  • Platforms all extended at Tilehurst, Pangbourne, Goring & Streatley and Cholsey; PIS systems still advertise them as being 7 coaches long.
  • Platform extension at Didcot Parkway (P2 & P3) is visually complete but barriered off.
  • Few masts and cantilevers now up on the Didcot Avoiding Line, which finish at Appleford; Appleford LC being the limit of structures for the time being.
  • Oxford Lines west of Didcot Pkwy wired as far as the loco fuelling sdg; Down Oxford as far as 53m 31ch, Up Oxford as far as 53m 42ch. Didcot avoiding lines have sprouted masts (4 portals, 2 TTCs), with a wire pair over the Down Didcot Avoider.
  • A note on Steventon: Wires up under the High St Bridge (aka the "Brunel Bridge"); however, the bridge may well be demolished in CP6. "Temporary" parapet work to protect passers-by from stray currents now complete. Wires west of Causeway Crossing are only authorised for passenger service on 80x trains in both directions, however, 387s are allowed to run empty to/from Cocklebury sidings under AC. The appeal to demolish the bridge is due to occur in the autumn (of 2019). The discussion continues.
  • Overruns through Swindon Jct (77m 36ch) onto the Golden Valley Line have also been wired.
  • Swindon Cocklebury Sidings in operation for Class 387 stabling as of 2/1/19.

The "Main Line"; Wootton Bassett Jct - Chippenham (Cocklebury Lane Bridge) - LIVE
Until further notice, the 25kV transmission wires will run in a trough from Cocklebury Lane Bridge (just east of Chippenham) to Thingley Jct. Large steelwork is expected to remain in situ until wiring is authorised west of Thingley, but some specific items may be poached if required elsewhere (and duplicates aren't stored at RAF Wroughton). Details given in the "Postponements" section.
  • Both lines are LIVE, signed off for passenger use, and in service from Wootton Bassett Jct to Christian Malford (93m 31ch) as of 0700 on 21/04/2019 (Easter Sunday).
  • Catenary, contact & Earth wires are up over/adj. to both lines from Cocklebury Lane to Wootton Bassett Jct.
  • Limit of AT Feeding: the Auto-Transformer at Christian Malford.

Chippenham (Cocklebury Lane Bridge) - Thingley Jct
  • No piles in Chippenham station, nor any masts affixed to the viaduct.
  • All piles in and majority of masts (and cantilevers) up from the western end of the viaduct to Thingley Junction (where the feeder station will be). Most TTCs have booms from beyond the viaduct to Thingley East Junction. About 14 masts are up in the vicinity of Thingley Feeder Stn, 2 of which have TTC booms affixed. Another has an STC boom.
  • Piles continue westwards to the next bridge.

Thingley Jct - Keynsham
  • No wiring for the foreseeable future, but overbridges between Thingley Jct & Box Tunnel have all been rebuilt. Corsham Main Road Bridge needs its parapets raising. New aqueduct & footbridge at Corsham complete.
  • Both Box & Middle Hill Tunnels have had track lowered.
  • A new footbridge has been built at Ashley Box.
  • Piles also in (and have been for over a year) at Ashley (beyond Box Tunnel) - these might well be trial piles.
  • Bathampton Jct to beyond Sydney Gardens has had track lowered. A new signal gantry at Bathampton Jct was installed over Xmas 2017 and is now in use after the removal of the old gantry in May 2019.
  • Bath Spa platforms realigned & raised, with track also slewed.
  • Track through Oldfield Park & Keynsham now lowered.
  • A lot of piles are in along the embankment around Saltford and Keynsham in readiness for future wiring.

South Wales Main Line (Wootton Bassett Jct-Bristol Parkway-Severn Tunnel-Newport-Cardiff)

Wootton Bassett Jct to Patchway Jct (inc. Bristol Parkway) - LIVE
  • Wires from Wootton Bassett Jct to Bristol Parkway in passenger service since 30/12/18.
  • All 6 through Lines at Bristol Parkway have been wired and are live.
  • Live wires continue to Patchway Jct (112m 68ch) & Stoke Gifford IEP Depot; Chipping Sodbury Goods Loop and the Cheltenham Curve overrun (as far as the limit of wiring) are also fully wired and live.
    • Limit of Live Wires on the Filton Lines (+ Down Bristol Parkway Relief): 112m 23ch.
    • Limit of Live Wires on the Charfield Lines (from Westerleigh Jct): 120m 59ch.
  • Filton Bank bridge works (mileages all from Temple Meads):
    • Easton Rd Overbridge (1m 18ch) completely rebuilt.
    • Narroways FB (2m 12ch) & Ashley Hill FB (3m 11ch) replaced.
    • Bonnington Walk Overbridge (3m 62ch) - parapets raised.
    • FB south of Filton Abbey Wood (4m 18ch) will need work if wiring is to occur.
Filton Jct - Severn Tunnel - Newport - St. Brides: due to go LIVE on 14/9/19
  • Stoke Gifford IET Depot all wired and energised.
  • Patchway Tunnels conductor rail installed.
  • Wires extend westwards from Filton Jct through Patchway and Pilning (across all lines) to the Severn Tunnel (on BOTH lines).
  • Severn Tunnel Conductor rail in place.
  • Wires are now up over all lines (both Tunnel Lines, both Main Lines & the Down Relief) at STJ Station; this also includes the overruns on the mains towards Chepstow. Wires continue westwards to Somerton Rd Bridge (East Usk Yard); all 4 lines have C&C. In the Magor/Undy area, the Down side and Up side are missing short lengths of Earth wire and ATF wire.
  • The Up Tunnel Loop between STJ & the Tunnel is fully wired.
  • Ground trunking installed at STJ in preparation for the electrical feed.
  • Feeder cables now hang from both the eastern set and western set of Switchgear Masts at STJ Feeder.
  • 6-track portals, probably 'Vierendeels', going up around East Usk Yard (approx. MP157 1/2).
  • Switchgear installed on a TTC near Moorland Park, Newport.
  • Between the Maindee Jcts (157m 74ch to 158m 16ch), a cluster of piles is in beside the Down Relief; these are complemented by masted piles on the Main side (adjacent to the Up Main).
  • Both Up & Down Hereford Lines are wired between Maindee West Jct & Maindee North Jct (41m 03ch from the former Rotherwas Jct, just south of Hereford); the Limit of wires is just north of signal "NT 1559".
  • The gap between the Maindee Triangle (Caerleon Rd Bridge) & East Usk Yard (Somerton Rd Bridge) is closing, with the erection of a number of back-to-back non-Series 1 TTCs in East Usk Yard. The Reliefs are now fully wired between Somerton Rd & East Usk Yard.
  • At the AT Feeder Station at the Maindee Triangle, the tall masts have now gained their spanwires in readiness for the C&C below.
  • Wires are up over the Usk Bridge; C&C is now up over BOTH Relief lines from the Tensorex portal immediately east of the bridge, through P1 & the Through Lines at Newport and up to Hillfield Tunnel.

Newport
  • All canopies now cut back.
  • All steelwork in Newport is complete.
  • All wires are now up through the station; some wires on P3/4 may still only have temporary registration with pulleys & webbing straps.

Newport - Cardiff
  • Plenty masts up around Gaer Jct (159m 32ch) north of Cardiff Rd Bridge (the B4237):
    • one by the Down Relief;
    • two by the Up Main (one of which is a boomed TTC with SPS);
    • three by the Gaer Jct - Park Jct Chord.
  • Currently unknown if Alexandra Dock Jct Yard will be electrified. The Reliefs appear to be wired past ADJ Yard.[/COLOR]
  • Lots of steelwork up immediately behind the signal gantry adjacent to the Up Main at Ebbw Jct; this includes a full portal boom and a TTC acting as an overrun mast on the Ebbw Vale branch.
  • Almost all steelwork up from Ebbw Jct to Long Dyke Jct (169m 35ch) east of Cardiff Central; most SPS is now up too.
  • ATF wire installed on the Up Main between Lighthouse Rd & New Dairy Farm bridges. In the Up direction, the Earth Wire is in place until just before the bridge over the Ebbw River.
  • Wires up through Duffryn on both Main lines between the Ebbw River Bridge & New Dairy Farm Bridge, after which it switches to both Relief Lines. At the MPA Portal at Duffryn, the Reliefs are fully wired, the Down Main is unwired, and the Up Main is fully wired (bar the MPA Jumper & Z-dropper). The Up side ATF wire is also missing.
  • Wires up across all 4 tracks between Pengam Jct (168m 40ch) & Marshfield.
  • The western limit of live wires is due to be at St. Brides Feeder Station, just east of Green Lane (Heol Las) Overbridge, from 14th of September 2019.
  • About 4 or 5 portals have been erected just west of Pengam Jct; 5 masts are up on the Up side east of Rover Lane bridge, complemented by 2 on the Down side.
  • 1 run of C&C has gone up between Moorland Road Jct (168m 65ch) and Long Dyke Jct (169m 35ch) over the Reliefs; this is assumed to be a crossover as it crosses from one Relief line to the other.
  • At Long Dyke Jct, all masts are up, and the ATF wire is now up over the Relief Lines.
  • In the Pellet St area, a Mid Point Anchor Portal Boom has now gone up.
  • Just east of St. Mary's St Bridge, 2 hexagonal Tensorex Portals have been erected over all tracks.
  • Over the bridge over St. Mary's Street in Cardiff (just east of Central), and immediately to the west of the bridge, 5 portal booms spanning all tracks have gone up.
  • Similar bespoke mast foundations are going in just east of Bute St Bridge, near the junction with the line from Queen Street.
  • Splott Rd Bridge upgrade work now complete.
Cardiff Central - Platforms 0-4 to be wired
  • Re-signalling completed. Platform 0 now open. 3 masts now up over P0/1 with TTC booms.
  • An Anchor Portal (of the hexagonal "TGBU" variety) has gone up over P2/3, just east of the canopies.
  • All large steelwork for P4 is now in position.
  • Most (if not all) TTC masts for P2 & the Up Through Line, along with P3 & the Down Through Line have gone up at the station. Some already have SPS.
  • Brackets appear to be in place on the coping stones on the Taff Viaduct (at the western end of the station).
  • Plenty piles up adjacent to Cardiff Canton. Increasing numbers of these now appear to have masts on them, as seen from a westward-facing shot from Central. A portal boom has gone up over the P2, P3 & Through lines immediately west of the station, behind the signal gantry.
  • Brickwork Sidings to be increased in length (and electrified) to accommodate GWR Class 387s; the first masts and cantilevers have now gone up, with around 2 boomed TTCs and 2 STCs in position.
  • Proposed Limit of Wiring: Leckwith Loop North Jct (171m 55ch) at a guess.
Swansea IEP Depot
  • New IEP Depot at Maliphant Sidings, Swansea now complete; all steelwork up. SPS, such as Insulators, Switchgear and Cantilevers have all been taken down, leaving only bare masts/booms in situ.

GWML/SWML Blockade Works (2018):
  • 6/7 to 3/12: Reduced capacity (2 lines only) for wiring work between Newport & Cardiff Ctl.
  • 15/9 to 6/10, and 13/10 to 14/10: Bristol Parkway electrified.
  • 27/10 to 18/11, 24-25/11, 1-2/12: Filton Bank 4-tracked.
  • 11/11: Bristol TM to Bath Spa resignalled.
  • December blockades at Bristol Parkway & Didcot Parkway done.
  • Christmas-New Year Blockade at Severn Tunnel Jct done.

GWML/SWML Blockade Works (2019):
  • 20/1/19, and 10/2/19: Newport to Bridgend blockaded (inc. Cardiff Central) for electrification work AT Cardiff Central; both done.
  • 17/2/19: Bristol Parkway to Newport blockaded for electrification work over the Usk Bridge at Newport; done.
  • 31/3/19: Newport to Bridgend blockaded (inc. Cardiff Central) for electrification work AT Cardiff Central; done.
  • 19/4/19 to 22/4/19, and 27/4/19 to 28/4/19: Bristol Parkway to Newport blockaded for electrification work in the Severn Tunnel Junction area; done.
  • 9/6/19, and 16/6/19: Newport to Bridgend blockaded (inc. Cardiff Central) for electrification work; done.
  • 27/7/19 to 28/7/19: Bristol Parkway to Cardiff Central blockaded for electrification work; done.
  • 25/8/19 until 14:00: Bristol Parkway to Cardiff Central blockaded for electrification work.
  • 8/9/19 until 14:00: Bristol Parkway to Cardiff Central blockaded for electrification work.
  • 14/9/19 to 15/9/19: Newport to Bridgend blockaded (inc. Cardiff Central) for electrification work.
  • 22/9/19 until 14:00: Newport to Bridgend blockaded (inc. Cardiff Central) for electrification work.
  • 29/9/19 until 14:00: Newport to Bridgend blockaded (inc. Cardiff Central) for electrification work.
  • 13/10/19 until 14:00: Newport to Bridgend blockaded (inc. Cardiff Central) for electrification work.
  • 20/10/19 until 14:00: Newport to Bridgend blockaded (inc. Cardiff Central) for electrification work.
  • Details of any further OLE-related blockades will be added as they are made available.

Berks & Hants Line (Reading-Newbury) - LIVE
Electric trains in squadron service.
  • Wires from Oxford Rd Jct are LIVE to the limits of electrification (53m 42ch on the Newbury Lines, 38m 07ch on the Basingstoke Lines) since 0650 on 21/10/18.
  • Class 387s are now in service on Reading-Newbury services as of 31/12/18.
  • Within Reading West, piles for the new footbridge (under Murphy's remit) are in, but have been "decapitated" (i.e. shortened) and capped until a new footbridge solution is found.
  • Immunised signalling continues to about MP55 1/2.

Project Postponements
  • Thames Valley Branches:
    • Windsor & Henley deferred to at least CP6. The first few yards of the Windsor branch (Not the Henley Branch) have been wired as an overrun.
    • Marlow removed from scope of current programme. The first few yards of the branch have been wired as an overrun.
    • Southcote Jct to Basingstoke deferred to at least CP6. The first few yards of the Basingstoke Lines have been wired as an overrun.
  • Appleford LC to Oxford paused; if CP6 accounts allow for wiring to be extended to Oxford, it would be very likely to happen now that Oxford has been remodelled.
  • Catenary & Contact wires between Chippenham (Cocklebury Lane Overbridge) & Thingley Jct have been deferred until at least some point in CP6. All Large steelwork to remain, unless required elsewhere.
  • Bristol Temple Meads to Bath & Bristol Parkway paused, dependent on Bristol resignalling:
    • Taunton-Bristol Parkway completed over Easter 2018;
    • Bristol Temple Meads to Bath Spa completed in November 2018;
    • The WSM stretch from Flax Bourton Tunnel to Cogload Jct remains outstanding;
    • Track remodelling of Bristol East Jct remains outstanding;
    • Filton Bank 4-tracking completed Autumn 2018.
    • Further Signalling works due in 2019: Bath Spa due to be resignalled over the 11th/12th of May, and the 23rd of June (both done).
  • Bristol Temple Meads' "Midland Shed" to be reopened in CP6 at the earliest, after Bristol resignalling is complete and the PSB is demolished.
As always, do let me know if I've missed anything!
(apologies to anyone who saw it in a state of source code chaos too).
 

Legolash2o

Member
Joined
27 Sep 2018
Messages
601
Here's maps showing my interpretation.

Note: I don't currently have the IED layout at Bristol Parkway, but I will draw it soon.
 

Attachments

  • Electrified-GW.png
    Electrified-GW.png
    1.3 MB · Views: 158
  • Electrified-GW-Bristol.png
    Electrified-GW-Bristol.png
    1.1 MB · Views: 152
  • Electrified-GW-Reading.png
    Electrified-GW-Reading.png
    1.2 MB · Views: 132
  • Electrified-GW-Reading2.png
    Electrified-GW-Reading2.png
    2 MB · Views: 130

cle

Established Member
Joined
17 Nov 2010
Messages
4,033
Given that all of the Bristol and Oxford works have been redone - when will we know about the wires being finished?

Second question - would there be any journey time improvements at all? Given that there aren't many stops/gains - especially on just to Parkway, but might the TM-Bath-Chippenham-Swindon route be cut down a little if wired?
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
24,918
Location
Nottingham
Given that all of the Bristol and Oxford works have been redone - when will we know about the wires being finished?

Second question - would there be any journey time improvements at all? Given that there aren't many stops/gains - especially on just to Parkway, but might the TM-Bath-Chippenham-Swindon route be cut down a little if wired?
Bristol Temple Meads has been re-signalled keeping the same track layout, but at the very least the eastern junctions need re-modelling before any electrification.

At a wild guess the saving with electric power via Bath might be in the tens of seconds from better acceleration and hill-climbing, but I doubt Filton Bank would save more than a handful of seconds.
 

JamesT

Established Member
Joined
25 Feb 2015
Messages
2,691
Given that all of the Bristol and Oxford works have been redone - when will we know about the wires being finished?

Second question - would there be any journey time improvements at all? Given that there aren't many stops/gains - especially on just to Parkway, but might the TM-Bath-Chippenham-Swindon route be cut down a little if wired?

Once the new ministers get their feet under the table and decide how much money for investment they’re going to make available?

Oxford to Didcot feels like it should have some scope for improvement, replacing Turbos with Electrostars on the stoppers. I don’t know if there will be any scope for the 387s to use their higher top speed too? (110 vs 90)
 

The Ham

Established Member
Joined
6 Jul 2012
Messages
10,325
Once the new ministers get their feet under the table and decide how much money for investment they’re going to make available?

Oxford to Didcot feels like it should have some scope for improvement, replacing Turbos with Electrostars on the stoppers. I don’t know if there will be any scope for the 387s to use their higher top speed too? (110 vs 90)

I do wonder, given the ability to remove diesel workings, if there's going to be electrification to Oxford whether the cost of going to Didcot Banbury would be worth doing. It would certainly make the case for XC getting bimodal trains better.

Edited to correct to Banbury.
 
Last edited:

hwl

Established Member
Joined
5 Feb 2012
Messages
7,398
A lot of piling already done (circa 50%) on Didcot - Oxford, so the cost to complete won't be that high.
 

kevin_roche

Member
Joined
26 Feb 2019
Messages
930
Given that all of the Bristol and Oxford works have been redone - when will we know about the wires being finished?

Second question - would there be any journey time improvements at all? Given that there aren't many stops/gains - especially on just to Parkway, but might the TM-Bath-Chippenham-Swindon route be cut down a little if wired?

There is some discussion of the December 2019 Timetable changes on the thread
GWR Dec 19 timetable
 

JamesT

Established Member
Joined
25 Feb 2015
Messages
2,691
I do wonder, given the ability to remove diesel workings, if there's going to be electrification to Oxford whether the cost of going to Didcot would be worth doing. It would certainly make the case for XC getting bimodal trains better.

Do you mean going on to Banbury rather than Didcot?
 

cle

Established Member
Joined
17 Nov 2010
Messages
4,033
I'd prefer Bletchley!

But a sensible organization would keep rolling, for sure. Banbury, and then Coventry. Snow Hill lines and Marylebone... both ways to Taunton....
 

Jurassicjewel

Member
Joined
26 Sep 2018
Messages
27
Extract from the July 2019 Minutes from Steventon Parish Council

Looks like modelling suggests that IEP's and 387's can travel at reduced speeds under the bridge without a need to demolish the Bridge. It will be interesting to see what the results will be from actual testing presumably with ECS.

"PUBLIC PARTICIPATION Talk by Network Rail on the bridge and electrification Nick Preston and Toby Elliot from Network Rail informed the meeting that the modelling undertaken to establish the heights required for clearance of the pantographs to enable full electrification of the railway had progressed faster than anticipated. It now seemed almost certain that the railway bridge would not be demolished as with some restrictions on speed of trains it would be possible to operate under the existing height. The pantographs on the 387 were different and results were still awaited. The parapets already installed were suitable for permanent use and would not require modification"
 

HowardGWR

Established Member
Joined
30 Jan 2013
Messages
4,983
Bit strong...

I’m all for non-disruptive improvements like this. And in time if it’s proven that 110 is possible; 125 may well be as well.
We don't know whether this is NR's plan B or whether they've decided to use the situation to save budget and achieve gratuitous positive PR. After all, the chance of the Inquiry Inspector recommending listed building consent refusal is remote, given that English Heritage has not objected and that the council's own officers recommended approval to its members.
 

Mordac

Established Member
Joined
5 Mar 2016
Messages
2,309
Location
Birmingham
Bit strong...

I’m all for non-disruptive improvements like this. And in time if it’s proven that 110 is possible; 125 may well be as well.
It's not an improvement, though. It's worse than what was there before, which was 125mph line speed.

Worse, though, is that it'll just embolden the next group of NIMBYs who think keeping their listed building untouched (and the heritage lobby would list a ham sandwich) is more important than essential national infrastructure.
 

takno

Established Member
Joined
9 Jul 2016
Messages
5,070
It's not an improvement, though. It's worse than what was there before, which was 125mph line speed.

Worse, though, is that it'll just embolden the next group of NIMBYs who think keeping their listed building untouched (and the heritage lobby would list a ham sandwich) is more important than essential national infrastructure.
For safety reasons the bridge should be painted bright yellow and all passing trains should have to sound their horn for a minimum of 10 seconds. Purely for safety reasons, you understand.
 

Grumbler

Member
Joined
27 Mar 2015
Messages
508
For safety reasons the bridge should be painted bright yellow and all passing trains should have to sound their horn for a minimum of 10 seconds. Purely for safety reasons, you understand.
20 seconds at night.
 

hwl

Established Member
Joined
5 Feb 2012
Messages
7,398
20 seconds at night.
Why not just automate it to reduce driver workload with a connection to the signalling system and attaching a large air raid siren directly to the shaft of a gas turbine?
 

JN114

Established Member
Joined
28 Jun 2005
Messages
3,354
It's not an improvement, though. It's worse than what was there before, which was 125mph line speed.

No, the current line speed for electric trains is, and always has been 60. It is being raised to 110 for electrics. The Diesel speed limit has been 125mph since the 1970s, and isn’t changing.

If IETs run at 110mph Electric rather than Diesel 125:-

1) Trains departing Didcot westbound on Electric will make significant time saving (perhaps as much as 2 or 3 minutes, I haven’t seen the modelling) vs current situation where they must depart Didcot on Diesel.

2) Trains passing Didcot in either direction, or stopping eastbound on Diesel won’t have to undergo a traction changeover. During the changeover process the speed will usually bleed down to 100/105 anyway, the GUs not having the grunt to regain/sustain 125mph running in such a short section. On Electric theylll be able to hold 125 right until they need to brake for the bridge (quarter of a mile tops), and have the power on tap to quickly return to 125 running after the bridge. Again time savings to be had.

There is no quantifiable downside to the solution vs the status quo. Yes. Demolishing and replacing the bridge would have allowed 125 electric; but not in the timeframe that linespeed improvements are required. And there’s nothing ruling out 125mph Electric on existing infrastructure after further modelling and testing; although NR aren’t going there yet.

Meanwhile the local residents - who would have suffered significant disruption of the bridge were demolished - don’t have to bear any disruption at all. It is correct that their objection had no legal basis; but it made Network Rail think about non-disruptive methods of solving the problem.
 

S-Bahn

Member
Joined
2 Nov 2018
Messages
263
Meanwhile the local residents - who would have suffered significant disruption of the bridge were demolished - don’t have to bear any disruption at all. It is correct that their objection had no legal basis; but it made Network Rail think about non-disruptive methods of solving the problem.

I agree. Whilst I'm all for knocking down old infrastructure and building new, NR seem to be working on a sensible win-win for both parties. An IET slowing briefly to 110 to clear this bridge isn't going to cause the passengers any inconvenience.
 

nickswift99

Member
Joined
7 Apr 2013
Messages
273
I agree. Whilst I'm all for knocking down old infrastructure and building new, NR seem to be working on a sensible win-win for both parties. An IET slowing briefly to 110 to clear this bridge isn't going to cause the passengers any inconvenience.
But it is going to increase wear and tear on the rolling stock (which NR don't care about).
 

The Ham

Established Member
Joined
6 Jul 2012
Messages
10,325
But it is going to increase wear and tear on the rolling stock (which NR don't care about).

I would have thought probably not by very much when the trains are on time as the drivers should just ease of the power to slow down before increasing back up to full linespeed.

If in cab signalling comes along and the linespeed is increased then it could be more of a concern.
 

squizzler

Established Member
Joined
4 Jan 2017
Messages
1,903
Location
Jersey, Channel Islands
No solution as yet. Some talk about permanently earthing the tunnel section and running on diesel through it.
Seriously? That the tunnel is wet and corrosive definitely falls under under the "known knowns" category engineers could design around, surely. By contrast poor soil conditions for piling might be a "known unknown" for which sympathy might be a little more forthcoming!
 

stj

Member
Joined
15 Apr 2019
Messages
315
Should have not bothered with this project and spent the money on decent DMUs instead.
 

JN114

Established Member
Joined
28 Jun 2005
Messages
3,354
Flash notice in this week’s WON stating equipment from the current limit of electrification at Patchway Junction to St Brides Feeder station (between Ebbw Junction and Marshfield) is to be considered live from 1100 hours on Saturday September 14th 2019.

As with previous I’ll reiterate this is not entry into service of OHLE on this section - that I understand is still slated for December 2019. But it’s the first big step on the road to getting it all signed off.

With regards to the Severn Tunnel itself, I’ve heard some scare stories and rumours as above of permanently earthing it; and also completely contrary rumours that the “fix” required isn’t that difficult; they’ll have to suffer a greatly reduced lifespan (numbers of 5-10 vs 30 years mooted) of the conductor rail system currently installed; and at whatever point x years down the line that turns out to be they’ll renew it with something that will have a much better resilience to the conditions.

Given the flash notice is for all overhead line equipment from Patchway to St Brides I’d go with the latter (they’d be no point livening it up for it to be permanently earthed) - but we shall see...
 
Status
Not open for further replies.

Top