• Our booking engine at tickets.railforums.co.uk (powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Aberdeen - Inverness £170m Upgrade

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Deltic1961

Member
Joined
30 May 2018
Messages
645
Are the trains going to be using the double track or will that only take place at the December timetable change?
 

Ben.A.98

Member
Joined
13 Feb 2013
Messages
227
Are the trains going to be using the double track or will that only take place at the December timetable change?

All trains will be using the new track as it is no longer bi-directional. Passengers won't feel the effect of being able to run more trains till the December timetable change takes place.
 

hwl

Established Member
Joined
5 Feb 2012
Messages
7,390
All trains will be using the new track as it is no longer bi-directional. Passengers won't feel the effect of being able to run more trains till the December timetable change takes place.
But hopefully services will recover better when things have gone wrong in the interim.
 

Class 170101

Established Member
Joined
1 Mar 2014
Messages
7,933
So tight working with Dyce terminators though now having to shunt from one side to the other rather than heading straight back as before. Some late starts towards berdeen look likely
 

D6975

Established Member
Joined
26 Nov 2009
Messages
2,867
Location
Bristol
So tight working with Dyce terminators though now having to shunt from one side to the other rather than heading straight back as before. Some late starts towards berdeen look likely
That does seem like a strange decision not to put a trailing crossover in to the east of Dyce given the number of services that reverse there.
 

Altnabreac

Established Member
Joined
20 Apr 2013
Messages
2,414
Location
Salt & Vinegar
That does seem like a strange decision not to put a trailing crossover in to the east of Dyce given the number of services that reverse there.

I suspect in the December timetable there won’t be many services reversing at Dyce any longer.
 

Deltic1961

Member
Joined
30 May 2018
Messages
645
I seem to remember this project having a price tag of £170m, but lately Aberdeen Journals have been quoting the project as having a cost of £300m.

Confused!
 

CEN60

Member
Joined
17 Dec 2018
Messages
267
That does seem like a strange decision not to put a trailing crossover in to the east of Dyce given the number of services that reverse there.

I suspect in the December timetable there won’t be many services reversing at Dyce any longer.

Was looked at and designed as far as I remember - along with other jcn options north of Raiths Farm / other Inverurie options also - rejected as not required by NR. As was bi-di both lines all the way from Aberdeen to Raiths Farm.
 

Altnabreac

Established Member
Joined
20 Apr 2013
Messages
2,414
Location
Salt & Vinegar
I seem to remember this project having a price tag of £170m, but lately Aberdeen Journals have been quoting the project as having a cost of £300m.

Confused!

£170m was the price in 2014:
https://www.bbc.co.uk/news/uk-scotland-highlands-islands-26784570
£330m is the price in 2019:
https://www.networkrail.co.uk/runni...tes/scotland/aberdeen-inverness-improvements/

And that's one of the reasons why we're moving from a Control Period based project system where early cost estimates get signed off without full cost details being available. Idea is the new pipeline model for schemes where the detail is worked up before schemes have to be fully signed off will give more certainty of costs and when schemes are no longer tied to the Control Period they can progress more organically.

We shall see if this leads to better cost control (or perhaps more realistic costs at outset of schemes).
 

Tobbes

Established Member
Joined
12 Aug 2012
Messages
1,242
Oops.
We shall see if this leads to better cost control (or perhaps more realistic costs at outset of schemes).

With a near-doubling of costs (general inflation has been low), would anyone care to apportion this increase between (i) increased scope; (ii) over-optimistic initial costings; (iii) rail-specific inflation being higher than general inflation (and if so, why); (iv) other - e.g., poor cost management.

For a bonus mark, would A2I have been approved in the first place if the bill was £300m +/- 10%?
 

takno

Established Member
Joined
9 Jul 2016
Messages
5,066
So tight working with Dyce terminators though now having to shunt from one side to the other rather than heading straight back as before. Some late starts towards berdeen look likely
On the face of it they could still turn them in the platform given that there's a crossover on the Aberdeen side of the station. Don't know if that's the plan or not
Oops.


With a near-doubling of costs (general inflation has been low), would anyone care to apportion this increase between (i) increased scope; (ii) over-optimistic initial costings; (iii) rail-specific inflation being higher than general inflation (and if so, why); (iv) other - e.g., poor cost management.

For a bonus mark, would A2I have been approved in the first place if the bill was £300m +/- 10%?
It's only about 50% over with inflation taken into account (although tbh I don't know if the final price is in 2014 prices or not). I'm not saying that's nothing, but IIRC it's not massively over the optimism bias that was being applied at the time.

Either way, I don't think it's a bad idea to be doing more planning and costing upfront
 

Tobbes

Established Member
Joined
12 Aug 2012
Messages
1,242
It's only about 50% over with inflation taken into account (although tbh I don't know if the final price is in 2014 prices or not). I'm not saying that's nothing, but IIRC it's not massively over the optimism bias that was being applied at the time.

Either way, I don't think it's a bad idea to be doing more planning and costing upfront
Fair enough - and yes, more risk reduction and accrate costings would be very welcome!
 

Deltic1961

Member
Joined
30 May 2018
Messages
645
I'm no expert in railways or infrastructure however the price tag when they announced the project did seem a bit low for all the work that was to be done.

Mind you most other projects that involve ACC or SG end up the same. At least this one was completed on time however!
 

Ben.A.98

Member
Joined
13 Feb 2013
Messages
227
On the face of it they could still turn them in the platform given that there's a crossover on the Aberdeen side of the station. Don't know if that's the plan or not

There isn't, closest crossover to Dyce now is just before Raiths Farm.
 

InOban

Established Member
Joined
12 Mar 2017
Messages
4,216
AIUI, the future service plan is for HST or other IC services from Inverness to Aberdeen, some continuing to Edinburgh or Glasgow, and a local service between Inverurie and Montrose. Therefore there won't be any trains terminating at Dyce. More useful would have been a third platform at Inverurie.
 

CEN60

Member
Joined
17 Dec 2018
Messages
267
AIUI, the future service plan is for HST or other IC services from Inverness to Aberdeen, some continuing to Edinburgh or Glasgow, and a local service between Inverurie and Montrose. Therefore there won't be any trains terminating at Dyce. More useful would have been a third platform at Inverurie.
Remember there is now a facility to turnback at Inverurie (at least there will be from Tuesday)

What would the benefit if a 3rd platform at Inverurie bring?
 
Last edited:

Tobbes

Established Member
Joined
12 Aug 2012
Messages
1,242
AIUI, the future service plan is for HST or other IC services from Inverness to Aberdeen, some continuing to Edinburgh or Glasgow, and a local service between Inverurie and Montrose. Therefore there won't be any trains terminating at Dyce. More useful would have been a third platform at Inverurie.

For £50m you can have it at Oldmeldrum...
 

InOban

Established Member
Joined
12 Mar 2017
Messages
4,216
Remember there is now a facility to turnback at Inverurie (at least there will be from Tuesday)
I know, but it would be better if the local service could terminate off the through tracks.
 

CEN60

Member
Joined
17 Dec 2018
Messages
267
I know, but it would be better if the local service could terminate off the through tracks.

There is now effectively back to back crossovers north of Inverurie - allowing a terminator into the new turnback & the facility to put southbound into either existing Platform from the siding or one from Huntleyetc (and given the age of the track in the non town platform, believe me you don't want to use that platform (NR didn't want to touch the track in the existing platforms as it would have driven an almost complete rebuild of both platforms) - you can also depart from the town platform south and use the new 50mph down to up crossover to get onto the up to run south. I am not sure how the service will operate in the immediate future, but the installed layout at Inverurie is quite flexible.
 
Joined
7 Aug 2011
Messages
245
There is now effectively back to back crossovers north of Inverurie - allowing a terminator into the new turnback & the facility to put southbound into either existing Platform from the siding or one from Huntleyetc (and given the age of the track in the non town platform, believe me you don't want to use that platform (NR didn't want to touch the track in the existing platforms as it would have driven an almost complete rebuild of both platforms) - you can also depart from the town platform south and use the new 50mph down to up crossover to get onto the up to run south. I am not sure how the service will operate in the immediate future, but the installed layout at Inverurie is quite flexible.

Why would replacing the track at Inverurie require rebuilding the platforms?
 

CEN60

Member
Joined
17 Dec 2018
Messages
267
Wild guess: if it’s replaced under this project, might it “trigger” needing to meet a more modern standard, whereas if it’s done as a “routine renewal” it can remain as-is?

Correct
 

Deltic1961

Member
Joined
30 May 2018
Messages
645
Is there a speed restriction on the new track? On the 18:06 Dyce to Aberdeen crawling along at 39mph.

Also, I noticed EE are now quoting the project as £330m. It's gone up 30 million since last week.
 
Last edited:

Altnabreac

Established Member
Joined
20 Apr 2013
Messages
2,414
Location
Salt & Vinegar
Is there a speed restriction on the new track? On the 18:06 Dyce to Aberdeen crawling along at 39mph.

Also, I noticed EE are now quoting the project as £330m. It's gone up 30 million since last week.

£330M is the price that has been quoted since last year.
 

47271

Established Member
Joined
28 Apr 2015
Messages
2,983
Dalcross station update from today's P&J, and for anyone who's wondering what's happened to it.

www.pressandjournal.co.uk/fp/news/inverness/1825924/new-designs-for-inverness-airport-rail-station-will-be-bigger-and-better/amp/

Fresh plans for a “bigger and better” rail station for Inverness Airport are due to be lodged – more than a decade after the idea was first tabled.

Transport chiefs have confirmed they are in the final stages of drawing up revised designs for an enlarged station with two platforms and a double-track at Dalcross.

The move emerged as the agencies involved were accused of “dropping the ball” on the vital infrastructure project for the north, amid growing frustration at long delays.

After more than a decade on the drawing board, proposals put forward by transport partnership Hitrans for a £5 million station won planning permission in 2017 amid hopes it would finally be operational the following year.

The scheme – which included a 568ft platform and a 150-space car park – has long been viewed as vital to accommodate growing airport passenger numbers, as well as improving links to the nearby business park and the thousands of new homes being built at Tornagrain.

Forecasts predicted that within 50 years it would overtake Elgin to become the second busiest stop-off in the north, after Inverness city centre.

But construction work did not start on the project in 2017 as expected and the planning permission is now just a few months away from expiring.

The scheme was taken over by Transport Scotland and it has now confirmed that a new design is currently being completed by Network Rail.

Unlike the original proposals, which envisaged opening a first platform and then building a second a few years later, the new design will feature two platforms and double-tracking from the outset.

It is expected to be similar to the recently relocated Forres station and the new Kintore station, both of which are also being delivered as part of a major upgrade of the Inverness to Aberdeen rail line.

A Network Rail spokesman said: “The project to deliver a new station for Dalcross is progressing well and we are currently finalising our proposed design for the facility.

“The development is being expanded to deliver a bigger and better station with two platforms and a double-track railway which will mean increased capacity on the line.

“As we are expanding the development, we will require fresh planning permission.”

However, Transport Scotland and Network Rail have been unwilling to confirm an anticipated start date for work at Dalcross.


Douglas Ross, Conservative MP for Moray, said last night he had written to ministers to demand a “firm timetable”, claiming the Scottish Government had “completely dropped the ball on this vital project”.

He said: “Last year, after writing to the cabinet secretary for transport, about delays with the project and when works would begin I was told it would be delivered ‘in the very near future’.

“Here we are nearly a year later and they are still no further forward as the Scottish Government haven’t even announced a start date and there is now a danger of having to go back to the start with this project.

“It would seem that since Transport Scotland and ministers became involved this important project has slipped even further.

“The Scottish Government really needs to prioritise the north of Scotland for a change.”

A Scottish Government spokesman said the existing planning permissions were “being updated to reflect enhanced plans for Dalcross Station”.

He added: “We expect the station to be delivered in first half of the current five year rail funding period and will be a position to confirm the starting and opening dates once Network Rail has completed its feasibility work and third party funding has been secured.”

The current rail funding period runs from 2019 to 2024.
 

och aye

Member
Joined
21 Jan 2012
Messages
802
Dalcross station update from today's P&J, and for anyone who's wondering what's happened to it.

www.pressandjournal.co.uk/fp/news/inverness/1825924/new-designs-for-inverness-airport-rail-station-will-be-bigger-and-better/amp/
Thanks for the update.

Whoops! Well, in some ways this is a good thing as it will mean the station will be built with 2 platforms in one go.

Surely Network Rail must be able to pick a CAD designed station they've already built from the shelf and make a few tweaks to it, then "hey, presto" design job done. :E
 
Status
Not open for further replies.

Top