I spent a most enjoyable day on the platforms at Newton Abbot on Friday and there was quite a bit of work being done there. Can anyone enlighten me as to why please.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

221129

Established Member
Joined
21 Mar 2011
Messages
6,520
Location
Sunny Scotland
I spent a most enjoyable day on the platforms at Newton Abbot on Friday and there was quite a bit of work being done there. Can anyone enlighten me as to why please.
I believe it is getting a new entrance. So could be to do with that?
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,266
I believe it is getting a new entrance. So could be to do with that?
I think this is the planning application, on Teignbridge council planning website:
19/00883/DCR3
“This Planning Statement has been prepared by Jacobs UK Ltd (Jacobs) in support of a full planning application for the ‘Newton Abbot Bridge Access’ project at Newton Abbot Railway Station (Grid Reference SX 867753 712236). The proposal includes a new footbridge that will form an extension to the existing station footbridge and a new station building located in Brunel Industrial Estate. The proposal also includes some landscaping and minor highway works around the new building.”
 

fgwrich

Established Member
Joined
15 Apr 2009
Messages
9,250
Location
Between Edinburgh and Exeter
I think this is the planning application, on Teignbridge council planning website:
19/00883/DCR3
“This Planning Statement has been prepared by Jacobs UK Ltd (Jacobs) in support of a full planning application for the ‘Newton Abbot Bridge Access’ project at Newton Abbot Railway Station (Grid Reference SX 867753 712236). The proposal includes a new footbridge that will form an extension to the existing station footbridge and a new station building located in Brunel Industrial Estate. The proposal also includes some landscaping and minor highway works around the new building.”

Interesting, thanks for that. I wonder if there is any provision, and space at either end, for a re-instated 4th platform? You could then separate the Paignton and Plymouth services east of the station.
 

dk1

Veteran Member
Joined
2 Oct 2009
Messages
15,822
Location
East Anglia
Interesting, thanks for that. I wonder if there is any provision, and space at either end, for a re-instated 4th platform? You could then separate the Paignton and Plymouth services east of the station.
It could've been done by leaving platform 4 many moons ago & having two separate islands. Times where different however on the railways in the 70s & 80s with only thoughts of less traffic & line closures unlike the very opposite picture we see today.
 
Last edited:

RichmondCommu

Established Member
Joined
23 Feb 2010
Messages
6,912
Location
Richmond, London
That cou

It could've been done by leaving platform 4 many moons ago & having two separate islands. Times where different however on the railways in the 70s & 80s with only thoughts of less traffic & line closures unlike the very opposite picture we see today.
Signalling done on the cheap in the 1980s.
 

Buffer68

Member
Joined
3 Jun 2009
Messages
272
Location
Bournemouth
Thanks for your replies and information. Newton Abbot deserves some development and TLC. Hopefully the works will benefit the station and will certainly give much better access to those working on Brunel estate.
 

youngiecj

Member
Joined
26 Feb 2012
Messages
365
Was a surprise to me when I visited in August, that Newton Abbot had ticket barriers installed? Manned quite frequent as well. How long have they been in ? Barriers in operation all year round? Or just Summer ?
 

dk1

Veteran Member
Joined
2 Oct 2009
Messages
15,822
Location
East Anglia
Was a surprise to me when I visited in August, that Newton Abbot had ticket barriers installed? Manned quite frequent as well. How long have they been in ? Barriers in operation all year round? Or just Summer ?
All year round. Installed a couple of years ago.
 

MarkyT

Established Member
Joined
20 May 2012
Messages
6,232
Location
Torbay
The additional entrance could plausibly also function as access to a new platform for the branch on that side. Alternativly, by allowing station parking to be relocated to the other side of the railway, space might be made available to restore the previous twin island configuration.

The minimal track layout at Newton Abbot is a direct result of the savage capital spending cuts imposed on BR by the first Thatcher Government in the early 1980s. Original plans for the resignalling had a more comprehensive layout, retaining the four platforms, through lines, and a double junction onto the Torbay branch. A similar cost saving over-simplication occurred at Taunton, although some of the drawbacks of that have been mitigated by the subsequent reinstatement of the centre island platform there.
 