• Our booking engine at tickets.railforums.co.uk (powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Most/least successful recent large infrastructure project?

Status
Not open for further replies.

InOban

Established Member
Joined
12 Mar 2017
Messages
4,216
The increased costs include lots of things. But it’s important to note that this is the same for all the other electirifcation projects. For example The electrification costs for the Shotts line include platform lengthening, rebuilding Station Rd in Shotts, the access for all bridges, Briech station (!), the changes to clearances, and plenty more besides. And it was still less than half the cost per km of EGIP. (And on time / on budget).
But Shotts was essentially a fill-in scheme joining other electrified lines. EGIP included Queen Street and its tunnel, and Winchburgh.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

eastdyke

Established Member
Joined
25 Jan 2010
Messages
1,923
Location
East Midlands
I commissioned an office block that stood empty for some time. Everything worked. All the power, gas, electric, water, data, phones were ready to go the moment the new tenants signed on the dotted line.
Does that not count as commissioning? Perhaps, using you experience, you could explain why that is not commissioning. Perhaps you could explain what it is.
And if no tenants had ever 'signed on the dotted line' I have to ask would the money (spent on the project) have been wisely invested?
Brings to mind an old favourite of mine:
'The operation was successful but the patient died'
 

hwl

Established Member
Joined
5 Feb 2012
Messages
7,390
Having done some thinking, a project that went largely unnoticed, but delivered very significant benefits on programme and on budget was the Southern Metro platform extensions, enabling 10 car operation on most of the network. That must be a contender.
Agreed - the only negative was there was quite along snagging period with some of the platforms virtually complete but not signed off for quite a while.
 

DarloRich

Veteran Member
Joined
12 Oct 2010
Messages
29,278
Location
Fenny Stratford
And if no tenants had ever 'signed on the dotted line' I have to ask would the money (spent on the project) have been wisely invested?

Luckily they did! The originally proposed tenants went bust before completion and it was easier to finish the job than stop, so we did. The entire building was commissioned and ready to go on schedule and ( just) under budget.
 

tasky

Member
Joined
30 Oct 2018
Messages
381
Many would say Edinburgh. From the airport the bus is quicker off peak for example. But over budget and not delivered what it should.

Separating the delivery from the actual performance of the system though, the Edinburgh tram has been extremely popular and beaten all demand forecasts.
 

driver_m

Established Member
Joined
8 Nov 2011
Messages
2,248
Id hardly call Harbury landslip a small thing which stopped Watford North going back in, they are planned to go back in 2021.

there have been opportunities though, and I can’t be bothered digging through, but I seem to recall a few posts saying that some of the operators on the west coast weren’t happy with some alternative suggestions to get it put in. If you look long term, the disruption has been worse on the WCML because of not taking a short term hit of blocking it and getting it done.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
15,934
there have been opportunities though, and I can’t be bothered digging through, but I seem to recall a few posts saying that some of the operators on the west coast weren’t happy with some alternative suggestions to get it put in. If you look long term, the disruption has been worse on the WCML because of not taking a short term hit of blocking it and getting it done.
Unless its a christmas or bank holiday we get knocked back on taking all line blocks of the WCML, operators refuse the access. Watford isnt a weekend job.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
19,652
Location
Mold, Clwyd
Agreed - but, again, very popular with the customers and the politicos in particular. Could there be a trend here? ;)
(Scotland route are also very happy)

But less happy are those whose projects were deferred/cancelled because EGIP/GW/NW electrification projects stole their budget.
The railway is a zero-sum game, most of the time.
 

Taunton

Established Member
Joined
1 Aug 2013
Messages
10,069
That is good but my point remains. Perhaps you could answer my point. I will set it out again for you:

I commissioned an office block that stood empty for some time. Everything worked. All the power, gas, electric, water, data, phones were ready to go the moment the new tenants signed on the dotted line.

Does that not count as commissioning? Perhaps, using you experience, you could explain why that is not commissioning. Perhaps you could explain what it is.
Well I'm glad you had all the building services up and running. You probably had the roof on as well. A railway viaduct with no track (and hence no signalling) installed on it is obviously not yet a railway viaduct. There are no rails. The clue is in the name :)

For the best "it's not my department" claim about a project I always like this one. Nothing to do with railways though
 

DarloRich

Veteran Member
Joined
12 Oct 2010
Messages
29,278
Location
Fenny Stratford
But less happy are those whose projects were deferred/cancelled because EGIP/GW/NW electrification projects stole their budget.
The railway is a zero-sum game, most of the time.

You are talking like politicians care about other parts of the country. They got the money. That is all that matters ;)

A railway viaduct with no track (and hence no signalling) installed on it is obviously not yet a railway viaduct. There are no rails. The clue is in the name

But if the scope of your project is to only construct a viaduct then you have delivered your project. You can commission that viaduct to receive the rails later. Perhaps we should look at programme management ;)
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
29,178
But Shotts was essentially a fill-in scheme joining other electrified lines. EGIP included Queen Street and its tunnel, and Winchburgh.

And GW included Box Tunnel, Severn Tunnel, etc etc. Guess which was the more expensive?

My point is that every electrification scheme has some big issues to deal with. Some more than others. But at the end of the day EGIP was late, over budget and expensive, as was GWEP. So why is the former thought of as a success and the latter a failure?
 

thenorthern

Established Member
Joined
27 May 2013
Messages
4,114
Can you give some examples of light rail projects/tramway that have been unsuccessful?
Sam

Sure

Edinburgh Tram - Over budget and late, yes passenger numbers are good but the network is still small.

Midland Metro - For many years was not getting anywhere near as many passengers as projected and was costing much more to run that it was expected to.

Sheffield Supertram - at first was losing massive amounts of money and still not doing as well as it was expected to.

Merseytram, Leeds Supertram, Bristol Supertram and others canceled after millions spent on them.
 

Old Yard Dog

Established Member
Joined
21 Aug 2011
Messages
1,482
The Ordsall chord has been disappointing because the powers-that-be have given TPE paths to run Leeds - Huddersfield - Manchester Airport trains via Victoria before allocating paths to Calder Valley trains. Huddersfield - Manchester Airport trains do not need to run via Victoria. Calder Valley trains do and should have been given first dibs.
 

ohgoditsjames

Member
Joined
16 Jun 2019
Messages
379
Location
Sheffield & Shipley
Electrification of the GWL has to be one of the biggest failures. It has caused the cancellation of multiple electrification schemes and ended the “electric spine” aspiration. Not only that but it’s jeopardised any possibility of future electrification.

I’m pretty sure at one point the business case for the electrification of the MML was stronger than the GWL and the MML was due to be electrified before the GWL yet it somehow leap frogged it.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
29,178
I’m pretty sure at one point the business case for the electrification of the MML was stronger than the GWL and the MML was due to be electrified before the GWL yet it somehow leap frogged it.

That’s correct, based on early estimates (which were woefully wrong, because they weren’t done properly) but the GWML fleet needed replacing, whilst the MML fleet didn’t. Hence the former came first.
 

Deepgreen

Established Member
Joined
12 Jun 2013
Messages
6,375
Location
Betchworth, Surrey
This may be too small to qualify, but Redhill's platform 0 has been very poor. It is badly-designed, and was the result of a half-baked scheme which could have achieved so much more if it had been funded properly. The signalling and junction alterations to permit all platforms to be through ones could not be afforded so we now have a sub-optimal layout, with platform 1 a 10 car bay. The new platform itself has a ridiculously short canopy, and, for the want of a simple 2/3car stopping board, all GWR trains stop at the GTR 4/5car board, outside the canopy and a long way from the exit, meaning passengers get wet, have to walk far further than necessary and are more likely to miss connections. There is also not a single poster frame on the platform, so posters are taped to cabinets, etc!

The train indicators on p0 are placed in very poor positions such that passengers are simply not provided with the information they need where they need it. For example, passengers coming up the stairs to the platform are presented with a screen listing all trains from the whole station, when what they really need is confirmation of the next train from p0. I've witnessed people trying to establish from the long list of all departures if the GWR train they can see way down the platform is the one they want, only for it to leave without them! Conversely, passengers arriving by train at the platform have to go towards the exit and turn round (it faces away from the platform) to read that same screen for their connections, causing obstructions in the process!

Some GWR trains are diagrammed to use platform 0, even though nothing is scheduled at platform 1 at those times, meaning a needless change of platform for the many people needing to change trains to those using p2 (to London), when a cross-platform interchange would be easily achievable.

In short, the under-funded project has been designed purely from an operator's (and an 'armchair' operator at that!) viewpoint, rather than including the passengers' needs properly. When I've raised the issues with GTR, they aren't interested even in the tiny things like the 2/3car stop board, let alone the bigger design failings. GWR simply say it's GTR's station and they can do nothing, which is clearly nonsense as they could easily ask GTR to consider improvements which would cost almost nothing. Privatised silo thinking has meant GTR has looked after itself and ignored the 'irritant' of GWR!
 
Joined
18 May 2012
Messages
411
East West Rail Phase 1 (Oxford - Bicester - Chiltern Line - Marylebone) has been a success for passenger options, flexibility and capacity.

Project Evergreen Phase 1 (Birmingham - Bicester - Marylebone) has also been a success for passenger options, flexibility and capacity.

Proof House Junction (Birmingham New Street North/East approach) has been a success for capacity and operational resilience.
 

Mogster

Member
Joined
25 Sep 2018
Messages
905
Can't think of anything worse than the Brandenburg Airport fiasco in Berlin!

Polish airports funded by the EU?

https://www.reuters.com/article/us-...nd-build-ghost-airports-idUSKBN0JS06K20141214

LODZ, Poland (Reuters) - The European Union has given Poland more than 100 million euros ($125 million) to built. The problem is most striking at the recently rebuilt Lodz passenger terminal, where passenger numbers in 2013 fell almost one million short of forecasts, according to European Commission documents examined by Reuters at least three “ghost” airports in places where there are not enough passengers to keep them in business.

Poland received 615.7 million euros in EU support for airports between 2007 and 2013, according to figures supplied to Reuters by the European Commission. That was almost twice as much as the next biggest recipient, Spain, and more than a third of all member states’ money for airports. The government declined to provide all the information on which it based its decisions to invest in the airports, but Reuters has reviewed data on three sites where traffic fell dramatically short of forecasts.

The problem is most striking at the recently rebuilt Lodz passenger terminal, where passenger numbers in 2013 fell almost one million short of forecasts, according to European Commission documents examined by Reuters.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
29,178
Proof House Junction (Birmingham New Street North/East approach) has been a success for capacity and operational resilience.

It was indeed. Fortunately people have forgotten about the big cable cut on day 1 of the blockade, the overrun at the end, it being rather more than the original budget, and a year late!
 

Tetchytyke

Veteran Member
Joined
12 Sep 2013
Messages
13,305
Location
Isle of Man
Huddersfield - Manchester Airport trains do not need to run via Victoria. Calder Valley trains do and should have been given first dibs.

The Ordsall Chord was brought in to relieve congestion across the Piccadilly station throat. That was the whole point of it. And to that aim, it has worked. There is less congestion across the throat.

The downside is that the Castlefield corridor doesn't quite work, but some of the operational decisions seem odd. If they used platforms 1 and 3 at Oxford Road it'd help, and if 13/14 were split in half it'd help with crowding.
 
Last edited:

tsr

Established Member
Joined
15 Nov 2011
Messages
7,400
Location
Between the parallel lines
Redhill-Tonbridge electrification - done so that Channel Tunnel freight could be electrically hauled from Willesden.
Never used as such because the use of 92s needed a further signalling upgrade (like the other CTR routes) but was not implemented.

Quite so. Probably the one route in the south-east which has always been least-suited for electrification. It freezes up numerous times even during a mild winter, the third rail is so badly installed that it occasionally falls over (literally - last occasion was in Bletchingley Tunnel a couple of weeks ago), it’s got numerous foot crossings and entirely unstaffed stations where people have historically come to grief on the third rail - and virtually all the freight needs to be diesel-hauled anyway, with only an hourly passenger train service most of the time, too.
 
Status
Not open for further replies.

Top