• Our booking engine at tickets.railforums.co.uk (powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Stevenage platform 5

Status
Not open for further replies.

adamedwards

Member
Joined
4 Apr 2016
Messages
796
Many thanks for this. So a big job is removing the redundant catenary posts. Hope you catch them doing it.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

malc-c

Member
Joined
1 Dec 2017
Messages
990
From what I've been able to find out the turnout will go in after the trackwork... All I've been told is "before Christmas"
 

malc-c

Member
Joined
1 Dec 2017
Messages
990
I heard on the grapevine that removal of the old OHL mast were to be removed during a possession tonight. I've just popped down there and there is no activity at all. so guess it's not going to happen, unless it's going to be in the small hours. I'll pop down there tomorrow to see if anything has happened, but would have thought that the sire would have been rigged with lights, etc in readiness to remove the masts as soon as they had possession in place. One thing I did notice was a lot of lengths of rail laying between DS and DF and UF lines. Not sure if this was old rail that has been renewed, or new rail placed in readiness for fitting... I'll have to wait until tomorrow so I can take a look in daylight.
 

Hadders

Veteran Member
Associate Staff
Senior Fares Advisor
Joined
27 Apr 2011
Messages
13,138
Something’s going on this afternoon. I can see flashing orange lights and hi-viz as I wait on the platform for a train.
 

malc-c

Member
Joined
1 Dec 2017
Messages
990
I stopped of on the way home from having lunch with out daughter and the masts appear to still be in place, but there was activity. Quite a few seems to be loading up flat bed transits with plastic barriers, and odds and ends as if having a tidy up rather than setting something out. Maybe the line possession is for tonight rather than last night and the masts will be taken down over night ? I'll try and get down there tomorrow with the camera and upload a further update
 

malc-c

Member
Joined
1 Dec 2017
Messages
990
Well seems I missed it when I last looked. A mast has been removed - just the one.

Latest update


I would be interested to hear what all that metal work is that the guys were carrying under the bridge, most deposited on the bank on the other side.
 

plugwash

Established Member
Joined
29 May 2015
Messages
1,563
It kind of looks like the rods used for mechanical control of points, would seem strange for points to be mechanically controlled in such an environment though.
 

malc-c

Member
Joined
1 Dec 2017
Messages
990
It kind of looks like the rods used for mechanical control of points, would seem strange for points to be mechanically controlled in such an environment though.

Even the connection to the sidings and head shunt are remote controlled, and that's a lot of metal work for a couple of points... my original thought was some form of barrier / fence.... but the line has been without an such thing for years....
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,383
Even the connection to the sidings and head shunt are remote controlled, and that's a lot of metal work for a couple of points... my original thought was some form of barrier / fence.... but the line has been without an such thing for years....
What about temporary supports for the blue tubular fencing of working zones, that clips to the rails?
 

malc-c

Member
Joined
1 Dec 2017
Messages
990
Might be... but given its on the opposite side of the turnback, and I've had verification that the only turnout that is being installed is just the one that will be adjacent to the existing turnout, so no track work will be change on the up side of the line.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,383
Might be... but given its on the opposite side of the turnback, and I've had verification that the only turnout that is being installed is just the one that will be adjacent to the existing turnout, so no track work will be change on the up side of the line.
Won’t they be removing portal uprights on the up side? Of course it might also be for other routine work that’s not directly connected to the turnback?
 

malc-c

Member
Joined
1 Dec 2017
Messages
990
What about temporary supports for the blue tubular fencing of working zones, that clips to the rails?

First prize goes to that person..... :)

I sent out a request for info over the grapevine and received confirmation that is indeed Vortok fence arms (safety fencing to keep personnel 1.2m away from the track)

Interesting that it wasn't erected the same time as the other fencing on the opposite side....

I'll have to keep an eye on this :)
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
24,880
Location
Nottingham
First prize goes to that person..... :)

I sent out a request for info over the grapevine and received confirmation that is indeed Vortok fence arms (safety fencing to keep personnel 1.2m away from the track)

Interesting that it wasn't erected the same time as the other fencing on the opposite side....

I'll have to keep an eye on this :)
Good thinking.

You probably need a block of the relevant track to install these, which might not have been possible on both sides at the same time.
Won’t they be removing portal uprights on the up side? Of course it might also be for other routine work that’s not directly connected to the turnback?
The actual removal of the uprights would be under a possession so there would be no need for separation fencing. But there are probably associated works that need to be done with the line open.
 

malc-c

Member
Joined
1 Dec 2017
Messages
990
No track yet. A good section has had ballast laid and graded as a foundation, but given restrictions in access under six hill road bridge I'm doubtful that track will be laid for another few months, unless they do it in sections and start laying track in that middle part which can be seen in my 313 drag video

 

malc-c

Member
Joined
1 Dec 2017
Messages
990
Due to a bereavement in the family I've not been able to pop down and check on things until today.

I went to Langley junction to video 66419 and whilst waiting for it noticed something tucked away in the unloading siding of the aggregate plant.

Not sure if they arrived by road or rail (notice the red and white markers on the ends of the sleepers which may suggest by road), but there is a row of protective fencing installed between the slow and fast up lines (bottom right of the image).


points.png
 

InOban

Established Member
Joined
12 Mar 2017
Messages
4,216
The announcement of the closure of KX for two weekends (end Jan and end Feb) made particular reference to work on this project.
 

malc-c

Member
Joined
1 Dec 2017
Messages
990
That's interesting, but then as most of these projects tend to be a Just In Time basis, why have the point work made and delivered to site three / four months ahead of the install date.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,383
That's interesting, but then as most of these projects tend to be a Just In Time basis, why have the point work made and delivered to site three / four months ahead of the install date.
It’s possibly been manufactured to meet an earlier plan, and the S&C manufacturer may have wanted to keep to that plan, and it was getting in his way?
 

hwl

Established Member
Joined
5 Feb 2012
Messages
7,390
It’s possibly been manufactured to meet an earlier plan, and the S&C manufacturer may have wanted to keep to that plan, and it was getting in his way?
That will be part of the issue the other half is that the there are very fewer of the special tilted S&C carrier wagons hence some S&C is transported to site upto 6 months early if there is space to store them and there is a mid-week unloading opportunity.

A huge number of the special wagons will be needed wagons for the Kings Cross throat works so everything else at the same time will have to be pre-delivered. Ditto anything for Xmas works this is the ideal delivery window.
 
Last edited:

malc-c

Member
Joined
1 Dec 2017
Messages
990
That will be part of the issue the other half is that the there are very fewer of the special tilted S&C carrier wagons hence some S&C is transported to site upto 6 months early if there is space to store them and there is a mid-week unloading opportunity.

A huge number of the special wagons will be needed wagons for the Kings Cross throat works so everything else at the same time will have to be pre-delivered. Ditto anything for Xmas works this is the ideal delivery window.

That makes sense...
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
29,173
Almost certainly be rail delivery, if only because each of those panels will weigh 7-15 tonnes, and would have been maximum 2 per lorry, and then craning them into position from the other side of the fence would have been very tricky. They are also the right size for using the tilters.
 

malc-c

Member
Joined
1 Dec 2017
Messages
990
The bit that puzzles me is that if they came via rail would it not have made more sense to have brought the panels on the Hertford loop near to where they will be installed. There is plenty of space they could have been placed on the line near the junction.

I'm wondering how they are going to move each panel from that yard area, across four tracks and under the wires.
 

Fred26

Member
Joined
5 Mar 2010
Messages
1,107
Could they be reloaded onto a waggon and taken by train towards Watton, across the points and back down to the worksite?
 

malc-c

Member
Joined
1 Dec 2017
Messages
990
Could they be reloaded onto a waggon and taken by train towards Watton, across the points and back down to the worksite?

But why not do that in the first place, saves having to load and unload another train with all that logistics. If the panels had been dropped on land between the down slow and stevenage bound side of the hertford loop then having one of those rail based cranes would make short work of moving each panel the 100m or so to where the point will be installed.
 

hwl

Established Member
Joined
5 Feb 2012
Messages
7,390
Could they be reloaded onto a waggon and taken by train towards Watton, across the points and back down to the worksite?
But why not do that in the first place, saves having to load and unload another train with all that logistics. If the panels had been dropped on land between the down slow and stevenage bound side of the hertford loop then having one of those rail based cranes would make short work of moving each panel the 100m or so to where the point will be installed.
A simple job with a Kirow Crane
 
Status
Not open for further replies.

Top