adamedwards
Member
- Joined
- 4 Apr 2016
- Messages
- 796
Many thanks for this. So a big job is removing the redundant catenary posts. Hope you catch them doing it.
Many thanks for this. So a big job is removing the redundant catenary posts. Hope you catch them doing it.
It kind of looks like the rods used for mechanical control of points, would seem strange for points to be mechanically controlled in such an environment though.
What about temporary supports for the blue tubular fencing of working zones, that clips to the rails?Even the connection to the sidings and head shunt are remote controlled, and that's a lot of metal work for a couple of points... my original thought was some form of barrier / fence.... but the line has been without an such thing for years....
Won’t they be removing portal uprights on the up side? Of course it might also be for other routine work that’s not directly connected to the turnback?Might be... but given its on the opposite side of the turnback, and I've had verification that the only turnout that is being installed is just the one that will be adjacent to the existing turnout, so no track work will be change on the up side of the line.
What about temporary supports for the blue tubular fencing of working zones, that clips to the rails?
Good thinking.First prize goes to that person.....
I sent out a request for info over the grapevine and received confirmation that is indeed Vortok fence arms (safety fencing to keep personnel 1.2m away from the track)
Interesting that it wasn't erected the same time as the other fencing on the opposite side....
I'll have to keep an eye on this
The actual removal of the uprights would be under a possession so there would be no need for separation fencing. But there are probably associated works that need to be done with the line open.Won’t they be removing portal uprights on the up side? Of course it might also be for other routine work that’s not directly connected to the turnback?
It’s possibly been manufactured to meet an earlier plan, and the S&C manufacturer may have wanted to keep to that plan, and it was getting in his way?That's interesting, but then as most of these projects tend to be a Just In Time basis, why have the point work made and delivered to site three / four months ahead of the install date.
That will be part of the issue the other half is that the there are very fewer of the special tilted S&C carrier wagons hence some S&C is transported to site upto 6 months early if there is space to store them and there is a mid-week unloading opportunity.It’s possibly been manufactured to meet an earlier plan, and the S&C manufacturer may have wanted to keep to that plan, and it was getting in his way?
That will be part of the issue the other half is that the there are very fewer of the special tilted S&C carrier wagons hence some S&C is transported to site upto 6 months early if there is space to store them and there is a mid-week unloading opportunity.
A huge number of the special wagons will be needed wagons for the Kings Cross throat works so everything else at the same time will have to be pre-delivered. Ditto anything for Xmas works this is the ideal delivery window.
Could they be reloaded onto a waggon and taken by train towards Watton, across the points and back down to the worksite?
Could they be reloaded onto a waggon and taken by train towards Watton, across the points and back down to the worksite?
A simple job with a Kirow CraneBut why not do that in the first place, saves having to load and unload another train with all that logistics. If the panels had been dropped on land between the down slow and stevenage bound side of the hertford loop then having one of those rail based cranes would make short work of moving each panel the 100m or so to where the point will be installed.