Temporary earthing of OHLE: Codes, guidelines and standards?

Status
Not open for further replies.

GrandBean

Member
Joined
28 Nov 2019
Messages
5
Location
Sleaford
I'm looking for information on on-site temporary earthing of OHLE during construction / maintenance work including what guidelines / codes / standard we work to in the UK.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

thecrofter

Member
Joined
16 Dec 2011
Messages
176
That'll be NR/L3/ELP/29987 Working on or about 25 kV Electrified Lines - aka the Green Book
 

GingerSte

Member
Joined
26 May 2010
Messages
255
I'm not sure if I need to say it, but...

Get somebody competent! Don't be messing about with it yourself!
 

GrandBean

Member
Joined
28 Nov 2019
Messages
5
Location
Sleaford
The contractor is claiming that he's working in accordance with the green book but, they tell pork pies so, I need to read the relevant section on isolation so that I can demonstrate that, once again, they're full of hot air.
 

thecrofter

Member
Joined
16 Dec 2011
Messages
176
The contractor is claiming that he's working in accordance with the green book but, they tell pork pies so, I need to read the relevant section on isolation so that I can demonstrate that, once again, they're full of hot air.

The Green Book is made up of a number of Modules with various activities contained across such e.g. Module 6 (Planning of) through to 9 (when constructing). It can be a minefield as with most NR standards as they often cross reference and in some cases contradict!

Current Version is Issue 5 but that is due to be superseded by a new version to be known as (ironically) 25000.

If you need any help drop me a PM.
 

GrandBean

Member
Joined
28 Nov 2019
Messages
5
Location
Sleaford
The Green Book is made up of a number of Modules with various activities contained across such e.g. Module 6 (Planning of) through to 9 (when constructing). It can be a minefield as with most NR standards as they often cross reference and in some cases contradict!

Current Version is Issue 5 but that is due to be superseded by a new version to be known as (ironically) 25000.

If you need any help drop me a PM.


Thanks, very much, I'll message as soon as I manage to find the PM button
 

bluenoxid

Established Member
Joined
9 Feb 2008
Messages
2,461
Thanks, very much, I'll message as soon as I manage to find the PM button
I think there is a minimum number of posts that you need to make before you can PM people. I think it is 5 and you have made 4 posts so far.

If I am wrong, please advise.
 