I’m not sure linespeed improvements have ever been promised. Merely suggested.
I think that a linespeed increase to 75 mph and Winchelsea level crossing to 60 mph was promised in the justification for the Ore Tunnel Blockade in 2012. It was pointed out that it all wouldn't happen immediately as some further renewals had to happen, but it appears that 8 years later nothing has happened except the 20 mph restriction outside Ashford has gone.
This was said in an article in Rail Engineer:
Journey time improvements
But the tunnel is not the whole story. With a nine week blockade available, just about everyone wants to take advantage of this extraordinary opportunity.
Murray Motley is a Senior project sponsor with Network Rail. As sponsor for a longer term scheme to improve journey times between Ashford and Brighton he has a great interest in the blockade.
Murray explains that, “The journey time improvement scheme had been developed to a point where we knew what we needed to do and what it would cost – but the costs were fairly high and, given that this is a rural railway, we were struggling to justify it. But what has actually happened is that much of what we were going to have to do is being picked up as part of routine maintenance.
“So, for example, if track has been relayed then that’s part of a normal renewal maintenance cost rather than a discrete scheme cost and so the actual money we have had to provide is just the incremental cost of putting the track back at a higher speed. The line is currently 60mph throughout with permanent speed restrictions in various places, but the aspiration is to get it up to 75mph.
“Although we won’t be able to open at the higher speed because we still have work to do on some structures and level crossings, the track will be ready for it because we will have done a substantial part of the overall scheme.”