• Our booking engine at tickets.railforums.co.uk (powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Engineering work on strike days?

Status
Not open for further replies.

Railcar

Member
Joined
27 Nov 2017
Messages
228
From the letters page of the i newspaper (9th June 2022)
'During the forthcoming rail strike, is there an opportunity to schedule engineering works for the days when no trins will be running?'
 
Last edited by a moderator:
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Peregrine 4903

Established Member
Joined
18 Aug 2019
Messages
1,455
Location
London
From the letters page of the i newspaper (9th June 2022)
'During the forthcoming rail strike, is there an opportunity to schedule engineering works for the days when no trins will be running?'
Ummm, I its more the opposite. If signallers are only on duty from 7 - 7, it means outside of those times you won't be able to signal engineering trains in and out of the possession.

Some engineering work will get cancelled because of the strikes.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
13,387
Location
Bristol
At this short notice, very little to no opportunity. The only things likely to get done are emergency repairs. And where signallers are on strike, nothing at all will get done.
 
Joined
21 Feb 2011
Messages
194
Location
Doncaster
Er, who is doing the work?
I was under the impression that Network Rail maintenance staff were also striking….
So, it is irrelevant if the signallers are there or not, if there are no staff on the ground
 

Peregrine 4903

Established Member
Joined
18 Aug 2019
Messages
1,455
Location
London
Er, who is doing the work?
I was under the impression that Network Rail maintenance staff were also striking….
So, it is irrelevant if the signallers are there or not, if there are no staff on the ground
There are still contractors that do the work. The signallers being on strike is the bigger issue and why a lot of the engineering work will be cancelled.
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,299
Without trains running there's a good opportunity to do surveys, inspections etc. which do not require engineering trains. But the bigger difficulty will be gaining possession access without a signaller
 

alxndr

Established Member
Joined
3 Apr 2015
Messages
1,475
At this short notice, very little to no opportunity. The only things likely to get done are emergency repairs. And where signallers are on strike, nothing at all will get done.
And even then emergency repairs are only likely to happen if sufficient non-striking staff can be found to complete the repair. That type of work is not typically done by contractors.
 

Signal_Box

Member
Joined
25 Dec 2021
Messages
654
Location
UK
With Red Zone working banned on the majority of the network even if there are no trains work can’t take place without a line block. No signaller, no line block, from what I’m hearing those who have been signed off as competent work signalling locations aren’t permitted to grant line blocks….
There will also be an issue with planned patrol works not being able to be taken again due to PWay staff, and signallers being on strike, a risk that patrols wont be carried out and sections of line having to be closed as safety inspections having not been undertaken within the specified times.

Without trains running there's a good opportunity to do surveys, inspections etc. which do not require engineering trains. But the bigger difficulty will be gaining possession access without a signaller
Almost all work now requires a line blockpage, even just for access. No signaller, no line block, no work.
 

Surreytraveller

On Moderation
Joined
21 Oct 2009
Messages
2,810
Indeed. Signallers need to give and take back line blocks. Electrical Control Rooms need to switch off and back on the traction current
 

Gems

Member
Joined
10 Nov 2018
Messages
656
Don't you just love letters pages in newspapers.
Letters pages are like twitter and online forums, they give people the opportunity to air their thoughts, that doesn't mean they are worth listening to.
 

Mintona

Established Member
Joined
8 Jan 2006
Messages
3,592
Location
South West
If those who are working signalling locations aren’t able to grant line blocks, what happens in the case of a broken down train where the driver needs to get out to examine/isolate cocks?
 

Val3ntine

Member
Joined
29 Apr 2015
Messages
376
Location
London
If those who are working signalling locations aren’t able to grant line blocks, what happens in the case of a broken down train where the driver needs to get out to examine/isolate cocks?

I may be confused, but how would the train be there in the first place?

Edit.. Actually ignore me, I see now you mean the contingency signallers may not have the authority to grant line blocks! My apologies.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
13,387
Location
Bristol
If those who are working signalling locations aren’t able to grant line blocks, what happens in the case of a broken down train where the driver needs to get out to examine/isolate cocks?
I would hope that the only places where signallers who can't grant line blocks are rostered for are multi-staffed boxes, and the Shift Manager or a signaller from another workstation can take over the panel for the bits the rostered signaller isn't able to do.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
15,954
They will take them on a contingency basis, but planned ones are unlikely to keep the workload down.
 

Amlag

Member
Joined
8 Jul 2018
Messages
228
They will take them on a contingency basis, but planned ones are unlikely to keep the workload down.

Engrs etc Possessions, that do not require a Signal Box to be open during a possession, can be taken just before a S.Box closes and given upon just after the S.Box opens.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
15,954
Engrs etc Possessions, that do not require a Signal Box to be open during a possession, can be taken just before a S.Box closes and given upon just after the S.Box opens.
Had it on good authority that at a lot of locations, unless its the resident signaller then the possession gets binned.
 

Signal_Box

Member
Joined
25 Dec 2021
Messages
654
Location
UK
If those who are working signalling locations aren’t able to grant line blocks, what happens in the case of a broken down train where the driver needs to get out to examine/isolate cocks?

I don’t think they’ve got that far in their thinking….a case of fingers crossed

I would hope that the only places where signallers who can't grant line blocks are rostered for are multi-staffed boxes, and the Shift Manager or a signaller from another workstation can take over the panel for the bits the rostered signaller isn't able to do.

There is no way another signaller will be helping out a CS, their competent after all.
 

Horizon22

Established Member
Associate Staff
Jobs & Careers
Joined
8 Sep 2019
Messages
7,573
Location
London
From the letters page of the i newspaper (9th June 2022)
'During the forthcoming rail strike, is there an opportunity to schedule engineering works for the days when no trins will be running?'

Unlikely considering many of those maintenance grades are also on strike. Not to mention that in my area they need Shift Signaller Managers (SSMs) to ensure possessions go ahead, and they’ll probably be on the panel during strikes. If at all, considering they’re might not be any staff availability overnight if it’s just 0700-1900 as has been mooted.
 

Signal_Box

Member
Joined
25 Dec 2021
Messages
654
Location
UK
Had it on good authority that at a lot of locations, unless its the resident signaller then the possession gets binned.

As far as I’m concerned if you sign your name as competent you should take on all duties of a full signaller.
 

BrummieBobby

Member
Joined
16 May 2022
Messages
94
Location
Birmingham
As far as I’m concerned if you sign your name as competent you should take on all duties of a full signaller.

Exactly- if you are competent to sign a signal box / panel then you are competent to grant a line block. As you have stated, line blocks don't just cover planned work, they also cover failed trains, stop and examine, items dropped from platforms and fault / incident responses.

If you are not competent to grant a line block, you should not be signing the book to take the controls. It is a highly dangerous development to allow unqualified people to take the controls without supervision.
 

alxndr

Established Member
Joined
3 Apr 2015
Messages
1,475
Yes, but there is no semi qualified state. You are qualified or not no middle ground.
The covid contingency plans did have several scenarios where trains could be run but no blockages could be taken, e.g. one signaller covering two workstations. Whether they could bring back those plans and risk assessments to cover the strike action or not I don't know.
 

Signal_Box

Member
Joined
25 Dec 2021
Messages
654
Location
UK
The covid contingency plans did have several scenarios where trains could be run but no blockages could be taken, e.g. one signaller covering two workstations. Whether they could bring back those plans and risk assessments to cover the strike action or not I don't know.

We bent over backwards to help out during Covid allowing a lot of local agreements to be amended etc.

Industrial action isn’t covid, the latter couldn’t of been helped - industrial action can be.
 

Facing Back

Member
Joined
21 May 2019
Messages
904
We bent over backwards to help out during Covid allowing a lot of local agreements to be amended etc.

Industrial action isn’t covid, the latter couldn’t of been helped - industrial action can be.
Didnt the Scottish agreement recognise this explicitly? It doesnt help you directly but the prededent it there. Part of the rise to recognise flexibility and part to regcognise cost of living increases?
 

alxndr

Established Member
Joined
3 Apr 2015
Messages
1,475
We bent over backwards to help out during Covid allowing a lot of local agreements to be amended etc.

Industrial action isn’t covid, the latter couldn’t of been helped - industrial action can be.
I know, and I agree that the circumstances are vastly different, however, it doesn't change the fact that the risk assessments have been done. It's not that different than certain changes to maintenance regimes coming in now that covid has proved that they can be lengthened. I don't agree with that either for the record.
 

Signal_Box

Member
Joined
25 Dec 2021
Messages
654
Location
UK
Didnt the Scottish agreement recognise this explicitly? It doesnt help you directly but the prededent it there. Part of the rise to recognise flexibility and part to regcognise cost of living increases?

No idea I’m afraid, id assume the union made it crystal clear the measures where during a time of national emergency and only then.

I know, and I agree that the circumstances are vastly different, however, it doesn't change the fact that the risk assessments have been done. It's not that different than certain changes to maintenance regimes coming in now that covid has proved that they can be lengthened. I don't agree with that either for the record.

I would put forward the “argument“ that during covid traffic was a fraction of what is it now, and those measures might of sped up the need for maintenance on certain sections and structures. Maintenance can take a holiday, but deterioration doesn’t.
 
Status
Not open for further replies.

Top