Bletchleyite
Veteran Member
It is ironic that the main toilets are on 3/4 when most waiting passengers will be on 5/6 (Avanti northbound) and 1/2 (LNR southbound).
Accessible toilets should be provided on all platforms at MKC regardless, tbh. It's a busy enough place for interchange that it justifies at least one loo on each platform. Able-bodied toilets would be less pressing, although still worth it on P5/6.
Doesn't Reading have toilets on every island, as they on the London end of 8/9 and 10/11 and the country end of 1/2/3/7, 12/13 and 14/15. Plus there are two lifts to each platform for redundancy.Newly developed and bigger stations (such as Reading) don’t even have that so that’s highly unlikely.
They would know which platform they are due to use, but that can always change whilst en routewould on train staff be aware of which platform the train was headed for, and, as previously mentioned, that the lift was not working
Newly developed and bigger stations (such as Reading) don’t even have that so that’s highly unlikely.
The issue is that the lifts are out for a long period of time.
Surely, even if assistance hadn't been booked, the on-train staff for the first part of the journey, towards Milton Keynes, should have contacted ahead as soon as they were aware of him being on the train, in order to give a reasonable chance of a solution being found.
Not 100% sure if it was, Avanti we're unloading all trains there at the time so it's not really relevant. As soon as the TM knew it was terminating there they should have thought about it, and the platform staff would 100% have know about the lift situationWas this service even supposed to stop at MKC? The passengers ultimate destination was Euston and my understanding is that the only reason for the de-train at MKC was because of the full line block south of MKC
It's entirely possible the TM did not know they would be terminating until some time after arriving into MKC. If they did not know the root issue causing them to be held, they would not immediately start making arrangements for wheelchair users to exit the platform.Not 100% sure if it was, Avanti we're unloading all trains there at the time so it's not really relevant. As soon as the TM knew it was terminating there they should have thought about it, and the platform staff would 100% have know about the lift situation
A lift will be fine for most of the time, but inevitably it will break-down or simply be out-of-service for periods for maintenance, so there needs to be another exit route from the platform other than the stairs which can be used within a reasonable, say 30 minutes, time period to allow the passenger to exit.
I am surprised it isn't an existing requirement for managing emergency situations because there will be situations where the use of the lift is not permitted or advisable and another route must be used.
Such as?
If you can come up with a workable, practical solution to what you’re asking for, I’m sure Network Rail will be all ears.
Barrow crossings are being phased out. Oversized items such as glazing don't need replacing very often, and can either be craned in, carried.across the tracks in a regular possession or handled up and down the footbridge steps.Another poster made a good suggestion, they referred to a barrow crossing along the ends of the platforms, something I have seen at other stations. I would have assumed something like this would be necessary for maintenance purposes as well, when moving over-sized items like glazing, panelling, vending machines or other large items which won't fit in the lift, or safely down the stairs, to get them to/from the platform.
It's entirely possible the TM did not know they would be terminating until some time after arriving into MKC. If they did not know the root issue causing them to be held, they would not immediately start making arrangements for wheelchair users to exit the platform.
Again, it is a bit of the 'open windows' or 'swiss cheese' theory here, but it is a failure of the station planning, not the onboard train crew, to have no plan for wheelchair users.
I wonder what the plan is when wheelchair assistance is pre-booked from MKC when services are running normally for trains booked to use this platform.
Barrow crossings are being phased out. Oversized items such as glazing don't need replacing very often, and can either be craned in, carried.across the tracks in a regular possession or handled up and down the footbridge steps.
Another poster made a good suggestion, they referred to a barrow crossing along the ends of the platforms, something I have seen at other stations. I would have assumed something like this would be necessary for maintenance purposes as well, when moving over-sized items like glazing, panelling, vending machines or other large items which won't fit in the lift, or safely down the stairs, to get them to/from the platform.
Barrow crossings are being phased out. Oversized items such as glazing don't need replacing very often, and can either be craned in, carried.across the tracks in a regular possession or handled up and down the footbridge steps.
Many stations don’t even have level access between platform and street level, let alone lifts to all platforms. What good is a barrow crossing between platforms if you can’t even get in or out of the station if you’re in a wheelchair?
It solves this very particular problem, IF staff can arrange to take a line block safely, which is not as easy as it sounds when the signaller is busy dealing with an incident involving stranded trains further up the line. It also increases the risk of trespass, by providing a very obvious route onto the tracks.We are discussing a station which has lifts and wheelchair access, so in this situation a set of barrow crossings would have allowed a member of railway staff to simply arrange to push passenger across to the next platform, either to board a train or to use the working lift. It solves the problem.
Long established Barrow crossings are being actively closed so they're certainly not going to be newly installed. They're well and truly out of favour. I've been a trained user of one and it could be a very long wait for permission to cross at times, and it relied on perfect communication and control between the station staff and signaller as I don't believe there was interlocking with the signalling.In the absence of another way to get passengers with limited mobility safely off the platform when the lift breaks down, it sounds like barrow crossings are still very much required.
I'd also expect getting a crane in to lower something which could be brought across a simple crossing would make the maintenance activity substantially more expensive and difficult to organise, doing anything with cranes around over-head lines is normally a challenge. Manual handling things up and down stairs isn't generally recommended, which is of course why we're having this discussion in the first place!
You'd never get approval to install a permanent drawbridge over the fast lines at MKC.Metal drawbridges maybe? (Which has been done in the past at Brockenhurst IIRC)
Still needs a link to the signals, but maybe could be interlocked properly.
This would be much more expensive in both staff and parts costs/storage than contracting it out. The appropriate response here is to insert a penalty clause in the contract for any repairs that take longer than x days to fix, which is almost certainly already how it is being done.I'd be tempted to bring maintenance of the lifts in house and keep both trained persons and a large stockpile of parts available.
There was nowhere for the train to go forward from Milton Keynes, and no certainty when it would be allowed to move in either direction given the scale of the disruption. Terminating the train was pretty much the only option.One procedure I suppose would be not allow terminating or taking a train out of service if the lifts are broken.
Evacuations excepted obviously.
This would be a tough restriction I suspect though.
Plenty of other locations where lifts have been out of service for months.The focus on the staff is wrong here - if you've never been shown proper manual handling technique, aren't strong enough to appropriately handle the individual and don't know their disability, you should be extremely cautious about proceeding to try and lever them up a flight of stairs. Somebody in a wheelchair (especially an ex-rugby player) may have very sensitive positioning requirements for their back and neck. If you handled them wrong, lost your grip (because you were sweating on a hot day, for example) or lost your footing you could cause further injuries or worse.
The failure is with the railway companies for not having a proper plan in place to respond to the broken lifts. They've been out of service for ages, and changing platforms at MKC is necessary for the majority of interchanges you'd be making there. There's options including intercepting journeys at Euston (at the cost of a longer journey time), replatforming connecting trains (at the cost of some delays), or even crossing the line at the end of the platform (at the cost of a fair amount of delay while the lines are blocked).
This would be much more expensive in both staff and parts costs/storage than contracting it out. The appropriate response here is to insert a penalty clause in the contract for any repairs that take longer than x days to fix, which is almost certainly already how it is being done.
If the parts aren't available to a dedicated lift maintenance contractor then why would NR or LNR have any better luck?If the task is impossible (because there are no parts available) the size of the penalty is immaterial, the job won't get done.
If the parts aren't available to a dedicated lift maintenance contractor then why would NR or LNR have any better luck?
Such as?
If you can come up with a workable, practical solution to what you’re asking for, I’m sure Network Rail will be all ears.
Keeping in mind that (AIUI) the majority of U.K. stations aren’t wheelchair accessible at all, let alone having lifts. So, to prevent the (very rare) scenario in this thread, you’ll need to apply your solution to every single one of them.
There is (AFAIK) no solution to detraining wheelchair passengers during an emergency evacuation either.
As I previously mentioned, the TM 100% knew they were terminating there as my train was the last to be given permission to move south from Rugby at the time.It's entirely possible the TM did not know they would be terminating until some time after arriving into MKC. If they did not know the root issue causing them to be held, they would not immediately start making arrangements for wheelchair users to exit the platform.
Again, it is a bit of the 'open windows' or 'swiss cheese' theory here, but it is a failure of the station planning, not the onboard train crew, to have no plan for wheelchair users.
I wonder what the plan is when wheelchair assistance is pre-booked from MKC when services are running normally for trains booked to use this platform.
The only person whose fault it is is whoever procured the contract for the lift supply and maintenance and failed to do due diligence on the onwards maintenance contract.As I previously mentioned, the TM 100% knew they were terminating there as my train was the last to be given permission to move south from Rugby at the time.
The 1st of the 2 Avanti trains that then arrived in at MKC we're between 30-45 minutes after I for there, so the line block had been in place for nearly at hour.
I'm not absolving anyone of responsibility, clearly more than 1 member of staff has not considered the best scenario. De-train at Rugby for onward road transport would have been the obvious and quickest option. Something that happens pretty regularly for issues such as lift availability, I've known it at multiple stations across LNWR/WMR so I'm sure Avanti at Rugby would've had no issue sorting it out.
It's not the station's fault they de-trained him there with no notice, I'd say from him statement that the Avanti staff went to find LNWR staff to assist, who found him halfway up the stairs. If they had known in advance, they could have had a plan in place be that using an alternative platform or manual movement but clearly they didn't