Have noticed fairly major construction work going on at Sandhills, including what looks like a new (foot?) bridge waiting to be put in position. Just curious as to what's going on.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

ukrob

Established Member
Joined
15 Jan 2009
Messages
1,810
Have noticed fairly major construction work going on at Sandhills, including what looks like a new (foot?) bridge waiting to be put in position. Just curious as to what's going on.

Bridge replacement. No trains 25th to 28th inclusive.
 

Poss Planner

Member
Joined
25 Aug 2011
Messages
19
The existing Sandhills Lane Bridge is to be replaced, with a new deck - the temporary bridge is for S&T cables etc....
 

ChrisTheRef

Established Member
Joined
15 Apr 2009
Messages
1,432
Location
South Liverpool
Rail Replacement Buses on 27th and 28th between:
Liverpool Central and Bootle Oriel Road
Liverpool Central and Walton
Liverpool Central and Rice Lane

(no trains 25th/26th!)
 

robertclark125

Established Member
Joined
12 Mar 2008
Messages
1,617
Location
Cardenden, Fife
The station itself was done up in 2007, and is much better. So the bridge will be the final bit of work, hopefully for many years
 