Sorry if this has been asked before, but wasn't there supposed to be 9-car workings by now on the western side to H&H, or have I missed it being introduced?
Looks like they are starting next Thursday if this is correct?
http://www.realtimetrains.co.uk/search/advanced/NBY/2018/12/06/0000-2359?stp=S&show=all&order=wtt
There's a brief update on the Bedwyn turnback siding in the latest Rail magazine (page 24). Looks like it's planned to be done in the August blockade at the end of the month.
Hi All,
Looks like the final metalwork has now gone in at Newbury Station.
https://twitter.com/networkrailwest/status/1017510808979419142
Also, SPS now fixed to underside of A339 bridge at the eastern end. Will grab some photos tomorrow.
Finally taken from Rockingham road looking back towards Newbury & out towards Emborne, quite a distance I think.
Also, I believe the next blockade is Mon 14th-17th May