Class 345 progress

Status
Not open for further replies.

kevin_roche

Member
Joined
26 Feb 2019
Messages
930
A new letter from Mark Wild to the London Assembly Transport committee has been published on the TfL web site today. It has some news on the software testing in the COS and vague plans for the upgrade to 9 car trains.

The PD+11 signalling software configuration is now being used in the Central Operating Section, paving the way for the next waves of signalling testing. PD+11 is now safety approved for testing all areas of the railway including using single train, multi-train and close-headway, as well as with multiple trains running across the transition boundaries.

There are also four ‘point releases’ of software updates planned for PD+11, providing the opportunity to bring forward any necessary bug fixes to enter Trial Running on the best footing.

and...

TfL Rail stopping services between Reading and Paddington commenced in December last year using the new Elizabeth line class 345 trains. The service is currently operating with 7-car trains and will be extended to 9-car trains later this year.

Despite a request from the Acting chair of the London Assembly Transport Committee and an assurance from Tony Meggs there is still no sign of the publication of the recent reports from Jacobs, the Crossrail Project Representative. The Jacobs reports tend to be more informative and the most recent covers up to mid October. A lot has happened since then.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

kevin_roche

Member
Joined
26 Feb 2019
Messages
930
More testing is planned this weekend. From the TfL Weekend Travel Information email.
On Sunday 1 March:
  • There will be no service between Paddington and Ealing Broadway between 09:00 and 23:00. This is due to Crossrail and Network Rail testing. Use alternative Tube routes to Ealing Broadway or Heathrow. Tickets can be used on Great Western Railway
  • A reduced service will run between Ealing Broadway and Hayes & Harlington between 09:00 and 23:00. This is due to Crossrail and Network Rail testing
 

TFN

Member
Joined
17 Aug 2017
Messages
352
Location
London
More testing is planned this weekend. From the TfL Weekend Travel Information email.

The TfL Rail train I took from Ealing today actually made automatic announcements regarding the closure on 1st and 16th March. It even said use the Central and District Lines from Ealing Broadway.

I thought it was weird that they would close Paddington to Ealing but now that it's for Crossrail testing it makes sense.

Will they just be closing the relief lines and keep the main lines open to Paddington?
 

JonathanH

Veteran Member
Joined
29 May 2011
Messages
18,530
The Hayes and Harlington terminator is dependent on the reliefs being open

Whilst that is true, this Sunday no trains from Paddington between 0933 and 2029 call at any station east of Slough and TfL Rail doesn't get to Paddington until 2300.

TfL Rail terminate at Ealing Broadway from Reading / Heathrow between these times. The Didcot to Paddington stopper is fast from Slough to Paddington.

Possession appears to close the relief line east of Ealing Broadway with access to Paddington for GWR restricted to lines 1 to 3.

This allows access for Crossrail trains to the Royal Oak Portal from Old Oak Depot and Acton Main Line to run to Bond Street as seen here.

https://www.realtimetrains.co.uk/search/detailed/PDX/2020-03-01/0930-2345?stp=WVS&show=all&order=wtt
 
Last edited:

kevin_roche

Member
Joined
26 Feb 2019
Messages
930
Whilst that is true, this Sunday no trains from Paddington between 0933 and 2029 call at any station east of Slough and TfL Rail doesn't get to Paddington until 2300.

TfL Rail terminate at Ealing Broadway from Reading / Heathrow between these times. The Didcot to Paddington stopper is fast from Slough to Paddington.

Possession appears to close the relief line east of Ealing Broadway with access to Paddington for GWR restricted to lines 1 to 3.

This allows access for Crossrail trains to the Royal Oak Portal from Old Oak Depot and Acton Main Line to run to Bond Street as seen here.

https://www.realtimetrains.co.uk/search/detailed/PDX/2020-03-01/0930-2345?stp=WVS&show=all&order=wtt

That is an interesting timetable. Looks like they are running two trains following each other over the transition between CBTC and TPWS. This is good news.
 

hwl

Established Member
Joined
5 Feb 2012
Messages
7,354
That is an interesting timetable. Looks like they are running two trains following each other over the transition between CBTC and TPWS. This is good news.
And even better news if it goes to plan during testing!
 

FlippyFF

Member
Joined
5 Jan 2014
Messages
240
Location
Ashford, Kent
That is an interesting timetable. Looks like they are running two trains following each other over the transition between CBTC and TPWS. This is good news.

They were doing this the previous weekend too but what puzzled me was that the timetable (on RTT) showed them terminating at the eastbound platform at Bond Street and the return starting from the westbound platform. Isn't the nearest crossover to the east of Tottenham Court Road? If so, why weren't they shown as running to/from there?

TIA

Simon
 

kevin_roche

Member
Joined
26 Feb 2019
Messages
930
They were doing this the previous weekend too but what puzzled me was that the timetable (on RTT) showed them terminating at the eastbound platform at Bond Street and the return starting from the westbound platform. Isn't the nearest crossover to the east of Tottenham Court Road? If so, why weren't they shown as running to/from there?

TIA

Simon
No idea. I wonder if anyone else knows.
 

hwl

Established Member
Joined
5 Feb 2012
Messages
7,354
They were doing this the previous weekend too but what puzzled me was that the timetable (on RTT) showed them terminating at the eastbound platform at Bond Street and the return starting from the westbound platform. Isn't the nearest crossover to the east of Tottenham Court Road? If so, why weren't they shown as running to/from there?

TIA

Simon
Possibly they are being manually signalled east of Bond Street to do the turnback?
 

mic505

Member
Joined
26 Nov 2016
Messages
185
Any further updates regarding the 345's operating to Heathrow? Will they operate 2tph initially (replacing the Hayes & Harlington and T2/T3 to T4 shuttles) or 4tph Paddington to T4, entirely?
 

matt_world2004

Established Member
Joined
5 Nov 2014
Messages
4,504
Any further updates regarding the 345's operating to Heathrow? Will they operate 2tph initially (replacing the Hayes & Harlington and T2/T3 to T4 shuttles) or 4tph Paddington to T4, entirely?
Depends if they come in before the may timetable change or not the plan is 4tph after the may timetable change however you may see 2tph before then to terminal 4
 

mic505

Member
Joined
26 Nov 2016
Messages
185
According to Crossrail via Wikipedia 'early 2020' is the next phase for 345's running to Heathrow. All I wanted to know in detail is whether its 4tph Paddington-Heathrow T4 (replacing the 360's) or just 2tph, alongside the 360's. Hence current information is vague lol.
 

matt_world2004

Established Member
Joined
5 Nov 2014
Messages
4,504
According to Crossrail via Wikipedia 'early 2020' is the next phase for 345's running to Heathrow. All I wanted to know in detail is whether its 4tph Paddington-Heathrow T4 (replacing the 360's) or just 2tph, alongside the 360's. Hence current information is vague lol.
May on real time trains has 4 tph going to Heathrow. If they introduce the 345s before then to Heathrow it's likely to be 2tph until may.
 

Trailfinder

Member
Joined
15 Jan 2015
Messages
84
For my sins I monitored Sunday’s testing on Open Train Times. At the same time it was a good opportunity to check for faults in the OTT Paddington map regarding the Crossrail part of the map; in which case I would report to OTT.

In previous Sunday testing, 2/3 units had shuttled between the Crossrail Depot Lines and the Crossrail Tunnel Lines (Eastbound, Westbound and the Loop Siding 1). I assume this testing was to test the transitions between the Crossrail lines and the Relief Lines, via Lines 4,5 and 6.

The first unit exited the depot at approx. 12:45 (4 hours late). It then took the Crossrail Depot line and took the eastbound tunnel. This was quickly followed by the second unit, which took the same route. This was no different from previous Sunday testing.

I then waited for a return trip. At 15:25, a unit appeared westbound on the Loop Siding 1 line, then went via Line 5 and the Down Relief to Acton Main Line. This was followed by the other unit travelling westbound on the Crossrail Westbound Line. This also went via Line 5 to AML (although it did not go all the way).

After a while, both units crossed to the Up Relief; one via Acton East and the other by Friar’s Junction. They both then remained there for a period. One unit then set off eastbound and took the eastbound tunnel via Line 6. The other unit returned to the depot.

At approx. 19:15, the unit reappeared on the Eastbound Line, then later returned to the depot via the Crossrail Depot Line.

So a very long possession, which most probably has inconvenienced thousands of passengers, for very little testing, which obviously still needs to be done. Why can’t it be done overnight?

It was interesting to note that some time after 20:00, the Main Lines east of Ealing Broadway were not being used and services were using the Relief Lines; Paddington platforms 1 to 6 were also not in use; this resulted in some HEX services using platform 12; this would cause those passengers who were travelling ‘contactless’ on the HEX being charged the TFL fare!
 

Trailfinder

Member
Joined
15 Jan 2015
Messages
84
The evening shuttles between Hayes and Harlington Loop and Terminal 5 continue. Is this testing or training for the TFL drivers?

As a Heathrow worker, I use the TFL service to and from Ealing Broadway so I look forward to the service becoming 4tph. The only thing I do not look forward to are the uncomfortable (concrete) longitudinal seats.
 

samuelmorris

Established Member
Joined
18 Jul 2013
Messages
5,121
Location
Brentwood, Essex
The evening shuttles between Hayes and Harlington Loop and Terminal 5 continue. Is this testing or training for the TFL drivers?

As a Heathrow worker, I use the TFL service to and from Ealing Broadway so I look forward to the service becoming 4tph. The only thing I do not look forward to are the uncomfortable (concrete) longitudinal seats.
The transverse seats aren't quite as hard, but yes the longitudinal seats are essentially wooden/plastic benches like you see on other subways around the world.

Trailfinder said:
this would cause those passengers who were travelling ‘contactless’ on the HEX being charged the TFL fare!
Better that than the other way round!
 

kevin_roche

Member
Joined
26 Feb 2019
Messages
930
There are some questions above on the timing of the introduction of 9 car trains to Heathrow and Reading.
I have now had time to read through an update on the software and systems in the latest Jacobs report for from period from 8 Dec 2019 to 4 Jan 2020.
http://content.tfl.gov.uk/project-representative-periodic-report-period-10-2019.pdf

This report was published on the TfL website last week and there are a number of interesting points despite the fact that it covers a period 3 months ago.

Page 6
The expected completion of Y1.3 software authorisation has slipped by 6 weeks in the last period. The primary cause of this particular delay has been the additional time taken by BT[Bombardier Transportation] to produce documentation required to support its application to the ORR.

This is the version of the train software that will allow Trial Running in the COS and I believe it will also be used on 9 car units running to Reading and Heathrow once it is approved as it supports TCMS and ETCS signalling.

From the earlier Jacobs Report for the period from 01 Apr 2018 to 28 Apr 2018

There are three key approvals for Authorisation to Place into Service (APIS) for Phase 2 to be issued by the ORR:
APIS GSM-R data to NR (achieved in this period);
APIS ETCS trackside to be issued to NR;
APIS ETCS on-board to be issued to BT.

There is a mention in the latest Jacobs report of the slippage to the date of Trial Running, this was also mentioned by Mark Wild in his letter to the London Assembly Transport Committee.
Page 9
Notwithstanding the slippage last period in the date for the start of Trial Running (to REDACTED) the CRL Routeway, Dynamic Testing and Plateau Teams are maintaining their plans for earliest completion. There is a particular logic to retaining the Trial Running target of REDACTED because the date is embedded in the current committed BT and Siemens plans for integrated software delivery. Ultimately, it might prove possible for CRL to drive to a later software configuration for Trial Running than P_D+11, if a software development and assurance window emerges from the Mega Plan 2 initiative; however, the approach to continue with the early target is prudent for now.

As with previous periods, the delivery of planned tests has been subject to disruption due to events, issues and asset failures. Among a number of recent unplanned events, the most serious was a SPAD which occurred during MDT 43, as part of Train Describer testing at the North Kent Line interface; initial indications are that this was due to a misunderstanding or a miscommunication, but the circumstances are being formally investigated. While there have been notable improvements in Dynamic Testing readiness (as evidenced in performance metrics presented at the Routeway/T&C Vis-Board review), we remain concerned that poor Dynamic Testing delivery continues to pose a significant risk to the achievement of Trial Running.

Train Describer test failures have raised concerns about the integrity of the current interface design. CRL will investigate further, but is committed to not be distracted from the main task of delivering the Central Section, rather than investing a disproportionate effort in resolving a lower priority issue. We support this approach.

Also on Page 9 is an indication that 9 car units (FLUs) will operate from May 2020.
There have been some positive developments in the analysis of service-affecting faults. BT and Siemens, in conjunction with CRL, now believes that the fixes incorporated into the P_D+11 and P_D+12 software releases will provide higher levels of PPM (for the 12TPH Stage 3 service) than previously modelled.

Nevertheless, all parties acknowledge that it is not until reliability mileage can begin to run in earnest (currently expected in May 2020) that modelled assessments can begin to be replaced with measured observations. Access to the COS for this work will be at a premium as other workstreams compete to complete their works. Other points to note are:
  • The introduction of FLUs on the GWML will provide some reliability performance by proxy, as they incorporate some of the same software as the trains operating in the COS.
  • The ORR has been reported by RfL as willing to consider a proposal to increase the number of trains in the COS up to 8, during the enhanced Dynamic Testing period. If this is the case then the additional trains would be operating from May 2020.
  • The NR/COS transitions are causing concern because reliability growth is in its infancy and access is limited. Evidence of transitions operating reliably at line speed would be of particular interest to NR when it is considering the Stage 4 timetable submission.
  • The speed of analysis and rectification of faults needs to be increased.

I hope that helps.
 

goldenarrow

Member
Joined
28 Sep 2019
Messages
49
Location
London
The evening shuttles between Hayes and Harlington Loop and Terminal 5 continue. Is this testing or training for the TFL drivers?

It's now driver training runs. Bulk of the Heathrow ETCS testing wrapped around two months ago IRRC.
 
Last edited:

matt_world2004

Established Member
Joined
5 Nov 2014
Messages
4,504
Speculatively , I reckon you will see 9 car 345s on the terminal 4 central shuttle first before running to Heathrow paddington
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
6,021
Location
West Wiltshire
The Finance Committee papers for next weeks TfL meeting have a target

Page 92) The target for 2020/21 is to begin trial running on the Elizabeth line by Autumn 2020. This is a key milestone which would keep the project on track for delivery of the central section „as soon as practically possible in 2021‟.
Full weighting will be given if target is met. If the target is met by December 2020 a 50% award will be given. Beyond December, no award.

http://content.tfl.gov.uk/fincom-20200311-agenda-papers.pdf

if the target is to begin trial running (start, not successfully complete it) and can still get 50% if it starts as late as December 2020.
Perhaps its just me but it suggests there is no great urgency to this, (and I'm guessing this means throughout whole line, not just a short central section)
 

kevin_roche

Member
Joined
26 Feb 2019
Messages
930
The Finance Committee papers for next weeks TfL meeting have a target

Page 92) The target for 2020/21 is to begin trial running on the Elizabeth line by Autumn 2020. This is a key milestone which would keep the project on track for delivery of the central section „as soon as practically possible in 2021‟.
Full weighting will be given if target is met. If the target is met by December 2020 a 50% award will be given. Beyond December, no award.

http://content.tfl.gov.uk/fincom-20200311-agenda-papers.pdf

if the target is to begin trial running (start, not successfully complete it) and can still get 50% if it starts as late as December 2020.
Perhaps its just me but it suggests there is no great urgency to this, (and I'm guessing this means throughout whole line, not just a short central section)
I did read somewhere that some part of the trial would be done with 24tph. I don't think they can turn that number round at Westbourne Park or Abbey Wood.
 
Joined
14 Dec 2018
Messages
1,144
I did read somewhere that some part of the trial would be done with 24tph. I don't think they can turn that number round at Westbourne Park or Abbey Wood.
What's the shortest time you can take from coming to a stop to being able to take the key out (including releasing the passenger doors)? Likewise what's the shortest time from putting the key in to being able to depart (including closing the doors)? (Also do the announcements have to be set up from scratch each time, or is there a button for "same route, reverse direction" sort of thing?)
Just asking because if the two times were short enough they could use "stepping back" (realistically there would need to be 3 to 4 "step backs" per train) to achieve the very short turnaround times. It all depends on what the minimum realistic times to key out and back in are though.
 

hwl

Established Member
Joined
5 Feb 2012
Messages
7,354
What's the shortest time you can take from coming to a stop to being able to take the key out (including releasing the passenger doors)? Likewise what's the shortest time from putting the key in to being able to depart (including closing the doors)? (Also do the announcements have to be set up from scratch each time, or is there a button for "same route, reverse direction" sort of thing?)
Just asking because if the two times were short enough they could use "stepping back" (realistically there would need to be 3 to 4 "step backs" per train) to achieve the very short turnaround times. It all depends on what the minimum realistic times to key out and back in are though.
Paddington - Westbourne - Paddington turnback is designed to be done driverless so no stepping back required, the drivers walks through the train while the train leaves the platform goes to the siding and then returns to the other platform. It can support 24tph if the GWML is out etc.

Westbourne need to be able to turn back 24tph till the GW services start running through.
 

matt_world2004

Established Member
Joined
5 Nov 2014
Messages
4,504
Paddington - Westbourne - Paddington turnback is designed to be done driverless so no stepping back required, the drivers walks through the train while the train leaves the platform goes to the siding and then returns to the other platform. It can support 24tph if the GWML is out etc.

Westbourne need to be able to turn back 24tph till the GW services start running through.
Detraining a 200m long train in 2.5 minutes is a pretty good feat.
 