Dunbar station upgrade progress (new platform on 'Down' side)

Status
Not open for further replies.

Aictos

Established Member
Joined
28 Apr 2009
Messages
10,403
I see the work at Dunbar on the new platform is going well with the skeleton of both lift shafts in place, I’m aware some repositioning of the OHL will need to be done but what exactly needs to be done?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

ScottDarg

Member
Joined
27 Apr 2017
Messages
707
Location
South Lanarkshire
The new platform is now in use following the timetable change. Video from Network Rail of an Azuma arriving:
Hello @LNER! Great to see an #Azuma calling at #Dunbar's brand new Platform 2 yesterday morning. We've constructed this to increase capacity and improve operational flexibility on the busy East Coast Main Line. #ECML https://t.co/0NhJwgz8PP
https://twitter.com/NetworkRailSCOT/status/1206549608853385216?s=19

Couldn't find another thread and didn't think this post warranted a thread of its own.
 

PhilipW

Member
Joined
6 Feb 2008
Messages
756
Location
Fareham, Hants
So are there 3 lines through Dunbar ? The video seems to show three.
What is the middle line used for ? Non-stop London bound trains, or is it bi-directional ?
 

ScottDarg

Member
Joined
27 Apr 2017
Messages
707
Location
South Lanarkshire
So are there 3 lines through Dunbar ? The video seems to show three.
What is the middle line used for ? Non-stop London bound trains, or is it bi-directional ?

The line the Azuma is on is the Northbound/Down main line and the middle line is the Southbound/Up main line.

The third line is a loop that serves the older platform that terminating trains use and Southbound trains call at. Southbound services running non-stop will usually use the middle line.

This image shows all 3 lines. The train is heading South through the loop: https://flic.kr/p/jpL7AS
 
Last edited:

yorkie

Forum Staff
Staff Member
Administrator
Joined
6 Jun 2005
Messages
67,749
Location
Yorkshire
Just to add to the description provided above by @ScottDarg, here is a diagram showing the track layout.

dunbar.jpg

Source: Traksy (@takno ), with my addition of the new platform ;)
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,382
I remember going through Dunbar when it still had the original down loop platform, I’m thinking late 60s maybe?

By the time of ECML electrification, the track had been long gone, but I think the platform itself was still there in a fairly derelict condition.
 

Aictos

Established Member
Joined
28 Apr 2009
Messages
10,403
Excellent news, good to see this project completed.
 