I paid a visit to the area again today - but was alas frustrated by road closures to reconstruct bridges for EWR and HS2 shutting three of the roads I needed to pedal along..

Nonetheless here's state of play for the two spots I was able to photograph:

The first three are from the bridge that is one bridge west of the bridge at Claydon Jct. (due north of Charndon)

20211017_123836.jpg
(Above) - facing East to the bridge at Claydon Jct - with work compound (stacked portakabins) for HS2 to top right. Still some work to do here - TBH, I don't think this site has changed much in a year, I posted photos from the bridge in the picture last November and the ground was being cleared at that time.

20211017_123755.jpg
From same location but facing West. The ground is looking good - and is being used as a road to the rest of the site.

20211017_123855.jpg
Thought it worth observing that the bridge has been tidied up - extra bricks and topping.

20211017_131632.jpg
Steeple Claydon crossing - bridge still not complete - facing West. The road to this bridge is marked out in adjacent fields with some surface removal but not really much else.
The former level crossing's length of track remaining in-situ has shrunk since last year.
20211017_131612.jpg
Steeple Claydon again, facing East. The ground is less of the mud bath that it was last year - perhaps more gravel been added for easier site access.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
29,070
Thought it worth observing that the bridge has been tidied up - extra bricks and topping.

That bridge (and the road) was closed for a while over the summer, presumably for the partial rebuild / tidying up you note.
 

HGS

Member
Joined
20 Jun 2013
Messages
9
Here are a couple of pictures I took in 2014 of the level crossing in Steeple Claydon. First looking west, second looking east. The rails are about the only thing recognizable. The third one is the warning sign on the approach to the level crossing. There were no warning lights that I could see!
 

Attachments

  • IMG_3996.JPG
    IMG_3996.JPG
    612.4 KB · Views: 161
  • IMG_3997.JPG
    IMG_3997.JPG
    543.2 KB · Views: 160
  • IMG_4000.JPG
    IMG_4000.JPG
    537.9 KB · Views: 156
Last edited:

Trog

Established Member
Joined
30 Oct 2009
Messages
1,546
Location
In Retirement.
I think one of the piers took a knock during a derailment in the 1980's freight train on one of the slows. Glancing blow on the side but enough to expose some of the reinforcement.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,267
Picture 2 is taken from OXD/29 Charndon Main St bridge, which on the TWA drawings was down for “general repairs and parapet raising”. Seen in the distance is OXD/29A Twyford No 2 footbridge which replaces a footpath crossing.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
7,674
Location
Leeds
According to the November Modern Railways, p. 25, the first 440m of the line, from Gavray Junction to Charbridge Lane, Bicester, have been commissioned for engineering trains.

I thought I'd seen a discussion upthread about why this section was so well advanced compared with other sections, but can't find it now, but you can see the stretch in the pics in #239.
 
Last edited:

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,267
According to the November Modern Railways, p. 25, the first 440m of the line, from Gavray Junction to Charbridge Lane, Bicester, have been commissioned for engineering trains.

I thought I'd seen a discussion upthread about why this section was so well advanced compared with other sections, but can't find it now, but you can see the stretch in the pics in #239.
That was a discussion very shortly before the main EWR thread was split and repurposed. It is about mid April in the now fairly dormant “consultation” thread. So you weren’t imagining things… :D
 
Last edited:

snowball

Established Member
Joined
4 Mar 2013
Messages
7,674
Location
Leeds
According to the November Modern Railways, p. 25, the first 440m of the line, from Gavray Junction to Charbridge Lane, Bicester, have been commissioned for engineering trains.
Elsewhere in the same issue of the magazine (p. 90, Trackwatch) the length commissioned is given as 1 mile 20 ch, about half of which is within the work site.
 
Last edited:

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,267
Elsewhere in the same issue of the magazine (p. 90, Trackwatch) the length commissioned is given as 1 mile 20 ch, about half of which is within the work site.
Would Trackwatch reports normally add up each direction for a two track railway? I’m struggling to fit 1 mile 20 ch into the space available, even if halved…
 

snowball

Established Member
Joined
4 Mar 2013
Messages
7,674
Location
Leeds
Would trackwatch normally add up each direction for a two track railway? I’m struggling to fit 1 mile 20 ch into the space available, even if halved…
It's saying the length commissioned extends further east than the other report. It says from Gavray Junction (19M 00ch) to 17M 60ch. It says the worksite is entered at 18M 28ch on one track and 18:34 on the other. It says LCs have been abolished at Jarvis Lane, Bicester Eastern Perimeter Road and Manor Farm, and a temporary facing crossover has been put in.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,267
It's saying the length commissioned extends further east than the other report. It says from Gavray Junction (19M 00ch) to 17M 60ch. It says the worksite is entered at 18M 28ch on one track and 18:34 on the other. It says LCs have been abolished at Jarvis Lane, Bicester Eastern Perimeter Road and Manor Farm, and a temporary facing crossover has been put in.
Oh so the length commissioned includes the junction, so that makes more sense. I think you meant “further west” though?
 

snowball

Established Member
Joined
4 Mar 2013
Messages
7,674
Location
Leeds
Surely further east? Going east from Oxford through Bicester towards Bletchley, the link to the Chiltern line turns off at what I assume is Gavray Junction (near Gavray Drive), then continuing east you go under the Chiltern line and into the work site? Both versions of the story have the west end of the commissioned length at Gavray Junction.
 
Last edited:

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,267
Surely further east? Going east from Oxford through Bicester towards Bletchley, the link to the Chiltern line turns off at what I assume is Gavray Junction (near Gavray Drive), then continuing east you go under the Chiltern line and into the work site?
I’m thinking the 400m (or 800m if counted both ways) of brand new track is up to the temporary alignment of Charbridge Lane, which is somewhat short of the old LC and the new bridge. The extra length commissioned must be the existing track and junction just west of the new section. The initial section of 2 track EWR well under the Chiltern line bridge already existed before the works started.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
7,674
Location
Leeds
I'm not familiar with the area and didn't have a clear mental picture of which roads are open or diverted, but it looks as though 1M20ch, or about 2km, would take you to a point due north of Launton, about easting 61 on the OS map. If that's incompatible with open roads, well Trackwatch has done retractions before now.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,267
I'm not familiar with the area and didn't have a clear mental picture of which roads are open or diverted, but it looks as though 1M20ch, or about 2km, would take you to a point due north of Launton, about easting 61 on the OS map. If that's incompatible with open roads, well Trackwatch has done retractions before now.
The tracks still stop at the temporarily diverted Charbridge Lane. First pic in #239 a few days ago. I think it will be some time yet before they extend towards Launton.

I just checked Google satellite view, I think you can see the temporary buffer stops where the existing lines were cut, between the Chiltern mainline bridge and the new Jarvis Lane footbridge, alongside the industrial estate. The overhead view also shows the road diversion route around the new bridge site..
 

alexx

Member
Joined
17 Sep 2015
Messages
95
The tracks still stop at the temporarily diverted Charbridge Lane. First pic in #239 a few days ago. I think it will be some time yet before they extend towards Launton.
Charbridge Lane is now closed for the next couple of months to commission the new bridge, so it might be quicker than you think.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,267
Charbridge Lane is now closed for the next couple of months to commission the new bridge, so it might be quicker than you think.
Yes but it was still closed at the time of the Modern Railways article we were discussing.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,267
Well quite. It was still open on Sunday afternoon when it was supposed to be closed too :)
So does that look as though they’re closing the temporary road well before, (maybe 3 months or so), the road over the new bridge is finished?
 

alexx

Member
Joined
17 Sep 2015
Messages
95
So does that look as though they’re closing the temporary road well before, (maybe 3 months or so), the road over the new bridge is finished?
It's closed now until December 17th, and if I recall correctly from the letter that arrived the other week when it reopens there'll only be one lane open for a few months so temporary traffic lights to add to the fun.
 

kevin_roche

Member
Joined
26 Feb 2019
Messages
930
That’s the magnet of the AWS (automatic warning system).
When I saw it I was wondering what the plans for signalling on the new line will be. I think all new lines are supposed to be fitted with ETCS, but I guess for the delivery trains they need AWS/TPWS for the time being.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,267
When I saw it I was wondering what the plans for signalling on the new line will be. I think all new lines are supposed to be fitted with ETCS, but I guess for the delivery trains they need AWS/TPWS for the time being.
AFAICT that section is just a reinstatement of the existing system.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
15,838
When I saw it I was wondering what the plans for signalling on the new line will be. I think all new lines are supposed to be fitted with ETCS, but I guess for the delivery trains they need AWS/TPWS for the time being.
E-W will be lights on sticks.
 

Trainee9

Member
Joined
29 Jul 2020
Messages
82
Location
Milton Keynes
Bletchley Viaduct: The Box over the mainline is looking nearer to completion, with shuttering removed on the Duncombe Street side, revealing the connection between viaduct and Box, (p1061) and on the Eaton Road site side (p1058). More steelwork has been erected for the highlevel station buildings, and an external concrete staircase on the Saxon Street side of the station is also visible (p1056).
 

Attachments

  • 101_1056.JPG
    101_1056.JPG
    1.3 MB · Views: 196
  • 101_1058.JPG
    101_1058.JPG
    610 KB · Views: 195
  • 101_1061.JPG
    101_1061.JPG
    1.4 MB · Views: 195
Last edited:

eMeS

Member
Joined
12 Jun 2011
Messages
954
Location
Milton Keynes, UK
Bletchley Viaduct: The Box over the mainline is looking nearer to completion, with shuttering removed on the Duncombe Street side, revealing the connection between viaduct and Box, (p1061) and on the Eaton Road side side (p1058). More steelwork has been erected for the highlevel station buildings, and an external concrete staircase on the Saxon Street side of the station is also visible (p1056).
Thanks for your pictures - did you see any signs of a lift installation going in?
 

Trainee9

Member
Joined
29 Jul 2020
Messages
82
Location
Milton Keynes
Thanks for your pictures - did you see any signs of a lift installation going in?
I could not see any signs of a lift installation. Also if there is going to be foot access from Saxon St I wonder how passengers will negotiate the cement works access road and that 20ft high concrete wall. Maybe somebody knows more from prior announcements and drawings?
 