January 2018– Electrification or new build electrifying in Progress
1) Manchester to Preston and Blackpool North plus Man Vic – Miles Platting area
2) Bolton to Wigan North Western - GRIP 3
3) Great Western Main Line London - Cardiff
4) Midland Main Line to Kettering and Corby only
5) Gospel Oak to Barking Line (GOBLIN) - very close to completion
6) Barnt Green to Bromsgrove
7) Chase Line from Walsall to Rugeley Trent Valley
8) Edinburgh Glasgow Improvement Programme (EGIP)
a) via Falkirk High complete
b) Edinburgh – Glasgow via Shotts
9) Rolling Programme -- Cumbernauld - Falkirk Grahamston etc- Stirling- Dunblane -Alloa
EGIP – Stirling-Dunblane-Alloa deliverability review
http://orr.gov.uk/__data/assets/pdf_file/0007/26188/stirling-dunblane-alloa-electrification-project-deliverability-review-summary-report-2017-07-25.pdf
10) Crossrail (yes new build but it will be electrified from the start)
11) HS2 (yes new build but it will be electrified from the start)