Regarding the proposed bi-mode replacement, a massive elephant in the room emerged at the DfT consultation in Leicester the other week.
In addition to their other flaws, such as a Leeds-London train, even at the maximum extent of electrification and assuming they would be allowed to use the HS2 wires from Sheffield to Chesterfield, having to run a greater distance under diesel than electric power (111 miles diesel, 106 miles electric - without dispensation over that HS2 section, the split is 124 diesel, 93 electric), the speed of operation under electric power is likely to be severely stunted on the MML racetrack on the southern end of the route.
The question was raised regarding concerns over the specification of current wires, and the answer was surprisingly candid.
The DfT spokesman confirmed that:
- Yes, indeed, this is true - electric traction is limited to 100mph Bedford to London under current route specifications.
- There are NO plans to improve this section in Network Rail's CP6 programme (2019-2024). It may possibly be included in CP7 (2025-2029).
- Replacing the wires will require both transformers and catenary to be completely replaced and this will mean Thameslink services would have to be suspended during any works, unless they themselves can draft in enough diesel traction for "drags" or stop-gap operation (spoiler - they won't be able to with current frequencies).
- An additional stop at Kettering will be added to all timetabled services to accommodate a power change. That's coming from the DfT spokesman, not me - power changes "on the fly" were dismissed at the meeting.
(Regarding the fourth point, why they didn't have the foresight to at least finish electrification at Leicester, where all intercity trains stop anyway, is beyond me. If you live in Kettering, congratulations! By a quirk of ridiculously poor planning, your relatively small town is mooted to become a key interchange for all MML services, even if that means your mate down the road in Wellingborough is going to lose their direct London service to accommodate you in the timetable!)
Diesel traction runs at up to 125mph on most sections south of Bedford. This means losing 25mph from the schedule over 80 miles of track, which adjusting for the superior acceleration of electric traction would still cost the electric haulage 5-8 minutes of time non-stop. Factor in the power change stop (up to an extra 5 minutes), and there is zero chance that the proposed new stock could match current timetables, never mind the proposed 6 trains per hour due from 2019.
So in a nutshell, even if the line were electrified throughout, they need to sort those wires out ASAP or there are going to be major timetable issues. People have questioned the bi-mode stock's ability to run to timetable on the diesel section, but they won't be able to even match it on the main chunk of the electrified section either, and that's the fault of poor planning from Network Rail more than anything!
I like the Mk. 5 idea, if only because the traction is already there and it requires minimum faffing around - they just have to make the coaches compatible. Alternatively, they could just cascade Mk. 4s and compatible locomotives like many have said, though they may have to plump for 67s rather than 68s as the former can do 125mph. There are enough sitting around in store that could do the job with a bit of fixing up, certainly - is their wiring compatible with the Mk 4s?
Final point - in my subjective view, the current EMT set-up isn't "broke" in the sense that they're punctual and relatively comfortable (Meridian pong aside), so I do worry about attempts to "fix" it, however old the HSTs are becoming!