Gravesend station rebuild approved. new 12 car central platform

Discussion in 'Infrastructure & Stations' started by Rational Plan, 23 Sep 2012.

Thread Status:
Not open for further replies.
  1. Rational Plan

    Rational Plan Member

    Messages:
    220
    Joined:
    3 Aug 2011
  2. yorksrob

    yorksrob Veteran Member

    Messages:
    14,567
    Joined:
    6 Aug 2009
    Location:
    Yorks
    That's certainly an interesting reuse of existing space. I'm guessing the new island platform will be fairly narrow.
     
  3. Rational Plan

    Rational Plan Member

    Messages:
    220
    Joined:
    3 Aug 2011
    Yes, it has railings on one side.
     
  4. John55

    John55 Member

    Messages:
    800
    Joined:
    24 Jun 2011
    Location:
    South East
    There are some more detailed drawings on Gravesham Council's website. Platform is about 5m wide with the fence about 0.5m from one edge.
     
  5. MidnightFlyer

    MidnightFlyer Veteran Member

    Messages:
    12,487
    Joined:
    16 May 2010
    Are there any links? I've had a quick flick through the website but can't find anything.
     
  6. John55

    John55 Member

    Messages:
    800
    Joined:
    24 Jun 2011
    Location:
    South East
  7. jopsuk

    jopsuk Veteran Member

    Messages:
    11,070
    Joined:
    13 May 2008
    the illustrative "photo montages" (they're neither!) show the fenced off side of the platform as having a platform edge that, were the fence removed, would be usable. This seems a bit odd?
     
  8. cyclebytrain

    cyclebytrain Member

    Messages:
    299
    Joined:
    11 Jul 2009
    Whilst I've come to accept that this plan is making the best of a bad job; I still really don't like it.
     
  9. jopsuk

    jopsuk Veteran Member

    Messages:
    11,070
    Joined:
    13 May 2008
    Care to expand on your objections? I don't really know the area.
     
  10. cyclebytrain

    cyclebytrain Member

    Messages:
    299
    Joined:
    11 Jul 2009
    The Metro services that currently terminate on the down platform will (presumably) go into the new bay -making them the wrong side of the station for the bus stop and the multi storey car park (although the right side for the station car park).

    Whelchairs/bikes/pushchairs etc. for up trains are going to have to either go round the end of the bay, or use a lift. And the island is going to be narrow, so difficult to get a wheelchair up to the other end in the rush hour, especially when half the platform are waiting for the next HS/metro rather than the one currently in the platform.

    The shops will now be on only the bay platform, ditto toilets, etc. (not room to put them on the island.

    In summary, I don't think it's going to work very well; but I also see no other way of getting the extra platform length in there
     
  11. cle

    cle Established Member

    Messages:
    1,307
    Joined:
    17 Nov 2010
    No C word in the release/summary. But obviously useful.
     
  12. Lexicon10uk

    Lexicon10uk New Member

    Messages:
    3
    Joined:
    25 Sep 2012


    The new central platform is 'single faced' and is (as mentioned earlier) fenced off. This platform is actually wider than both current platforms, although you are correct in noting the lack of any facilities on it - save, seating and an 80 metre modern canopy. There is scope, however, for a coffee/tea kiosk near the new footbridge on this platform and the current shop on platform 1, will be able to extend into the space vacated by the soon to be demolished old footbridge. - although I understand that the owners of the very small Pumpkin shop, are unwilling to invest as such, (after all, they possess a complete monopoly at this station. The space to be soon available on platform 3 (currently platform 2), where the other end of the old footbridge remains in situ for the time being, will also be available for retail - should anyone wish to enquire.

    The majority of the station buildings are indeed Grade 11 listed, however, to many, it is now seen as it's achilles heel. The ideal solution would have been to replace the London end road bridge and extend there, or even a replacement 4 platform station altogether. But there we go.
     
Thread Status: