Great Western Electrification Progress

Discussion in 'Infrastructure & Stations' started by 76020, 6 May 2013.

  1. adrock1976

    adrock1976 Established Member

    Messages:
    2,690
    Joined:
    10 Dec 2013
    Location:
    Glasgow
    Many thanks for the clarification.

    I have also fixed the previous post from Brickworks to Brickyard.
     
  2. Mintona

    Mintona Established Member

    Messages:
    3,174
    Joined:
    8 Jan 2006
    Location:
    South West
    Am I correct in saying that the ‘ladder’ junction from platforms 3 and 4 to the Brickyard sidings won’t be electrified, so terminating trains will need to switch to diesel to go down to the Brickyard sidings and then raise the pantograph again to come back into platform 1 or 2?
     
  3. edwin_m

    edwin_m Veteran Member

    Messages:
    16,483
    Joined:
    21 Apr 2013
    Location:
    Nottingham
    I can't answer this, but will point out that the platforms are now bi-directional with crossovers east of the station so the longstanding practice of arriving into 3 or 4 and shunting across is no longer essential. An electric train could terminate in 0, 1 or 2 then run into Brickyard Sidings and back into one of the same platforms.
     
  4. Tom Quinne

    Tom Quinne Established Member

    Messages:
    1,102
    Joined:
    8 Jul 2017
    All West facing points from P4 across to Line A and the Brickyard will be juiced, along with Line E only.
     
  5. Mintona

    Mintona Established Member

    Messages:
    3,174
    Joined:
    8 Jan 2006
    Location:
    South West
    I know and I was wondering if this would happen more often in the December timetable. Indeed, on 2 of the last 3 occasions I’ve terminated at Cardiff it has been into platform 1.

    Thanks for letting me know, I’d heard mention of it being otherwise. That’s re-assuring.
     
  6. Tom Quinne

    Tom Quinne Established Member

    Messages:
    1,102
    Joined:
    8 Jul 2017
    Unless the the train is late, or has a short turnaround there isn’t the capacity to hold trains in the station without going West first.
     
  7. DaveHarries

    DaveHarries Established Member

    Messages:
    1,730
    Joined:
    12 Dec 2011
    Location:
    England
    Earlier this evening I was looking at the "Trackwatch" section in the June 2019 edition of "Modern Railways" magazine. At the end, under "Next Month" it says that "Electrification on the Great Western sees a further section energised" in April. I queried this on a FB group and now understand, from replies received to my post, that Swindon to Chippenham went live during April. In addition Stoke Gifford to Patchway went live yesterday (16th June) and I am given to understand that Ebbw Junction to Marshfield goes electric on Saturday 06th July.

    Dave
     
  8. FGW_DID

    FGW_DID Established Member

    Messages:
    1,772
    Joined:
    23 Jun 2011
    Location:
    Oxfordshire
    Not quite, it’s only the National Grid 25KV compound and buried HV cables adjacent to the Up Main that is being energised.
     
  9. Richard Scott

    Richard Scott Member

    Messages:
    107
    Joined:
    13 Dec 2018
    Contact wire now up on up main through Magor, just the ATF wire on up line left to go.
     
  10. DaveHarries

    DaveHarries Established Member

    Messages:
    1,730
    Joined:
    12 Dec 2011
    Location:
    England
    What is ATF?

    Dave
     
  11. 59CosG95

    59CosG95 Established Member

    Messages:
    4,214
    Joined:
    18 Aug 2013
    Location:
    WIM/PBO
    Auto-Transformer Feeder. Essentially a beefed-up Return Conductor which is also electrified at 25kV, but out of phase with the supply to the C&C wires.
     
  12. oglord

    oglord Member

    Messages:
    197
    Joined:
    13 Oct 2010
    Location:
    Newport, Monmouthshire
    Both up and down Hereford lines from Maindee West to Maindee North junctions are now wired.
     
  13. oglord

    oglord Member

    Messages:
    197
    Joined:
    13 Oct 2010
    Location:
    Newport, Monmouthshire
    The down main seems to be missing the contact wire at Magor too.
     
  14. Richard Scott

    Richard Scott Member

    Messages:
    107
    Joined:
    13 Dec 2018
    It's definitely there in my area but unsure how far that may go as can only see either way for 100m or so!
     
  15. Linda smith

    Linda smith Member

    Messages:
    45
    Joined:
    31 Oct 2018
    Had a quick look yesterday evening. Only the up relief was missing its contact wire. And this morning I noticed that a run of earth cable has now been run to just short of somerton bridge.
     
  16. 59CosG95

    59CosG95 Established Member

    Messages:
    4,214
    Joined:
    18 Aug 2013
    Location:
    WIM/PBO
  17. chorx18

    chorx18 New Member

    Messages:
    4
    Joined:
    13 Mar 2017
    Do we know when passenger trains will be using the wires west of Bristol Parkway?

    I'm going on a journey next week which includes Bristol Parkway to Cardiff so would be good to know what to watch out for!
     
  18. JN114

    JN114 Established Member

    Messages:
    2,121
    Joined:
    28 Jun 2005
    December
     
  19. uvarvu

    uvarvu Member

    Messages:
    27
    Joined:
    5 Apr 2016
    On the 14th June I travelled on 1B91 to Bristol Parkway, between Reading the Didcot the train spent some time on the relief lines but when it was time to move back onto the fast lines it stopped dead, turned on the Diesel engines and then moved to the fast lines (I'm not sure which junction but it was somewhere east of Didcot). Once it was on the fast lines it went back to electric mode. Could it not coast across the points? At first I thought the train stopped to let something pass but nothing did so I'm not sure what happened.
     
  20. JN114

    JN114 Established Member

    Messages:
    2,121
    Joined:
    28 Jun 2005
    It would have switched to Diesel to go under Steventon bridge (IETs won’t go on Electric West of Didcot, the goalkeeper balises will drop the pans at Foxhall regardless). I presume there was a signal check at Moreton Cutting and the driver opted to use that opportunity to switch to Diesel for the bridge.
     
  21. 59CosG95

    59CosG95 Established Member

    Messages:
    4,214
    Joined:
    18 Aug 2013
    Location:
    WIM/PBO
    GWML Electrification: State of Play, as of week commencing 24/6/19.
    All mileages given from Paddington, except where noted.
    Paddington to Wootton Bassett Jct - LIVE
    • All main line tracks wired as far as Wootton Bassett Jct, and are to be considered "live" as such. From Wootton Bassett Jct, the envelope of "live" wires continues along the South Wales Main Line to Filton Jct (inc. Bristol Parkway), and to the Limits of Wiring on the Berks & Hants line and Reading-Basingstoke Line; details are given below.
    • TTCs have replaced/been replacing headspans at various locations within London - locations include Westway (beneath the A40), Acton Main Line, Ealing Broadway, and between Southall & H&H. These are part of the works for the Elizabeth Line.
    • Everything wired at Reading (bar P4-6 which were never in the plan). Includes the TCD & the curves, down to Reading West (see B&H section).
    • West of Didcot Parkway, all lines are wired & live heading towards Swindon.
    • Everything wired at Swindon (bar the goods lines north of P1, where provision is provided).

    Small Points
    • ATF wires in operation from Maidenhead to Wootton Bassett; Kensal Green to Maidenhead currently only using return conductors but will be AT-ready in the near future. Some AT wires up along this stretch now; whether they are live remains to be seen.
    • Parapet Work extended upwards at Southbury Lane Bridge, Ruscombe; the wing walls remain unfinished. Original Coping stones have now been replaced.
    • Platforms all extended at Tilehurst, Pangbourne, Goring & Streatley and Cholsey; PIS systems still advertise them as being 7 coaches long.
    • Platform extension at Didcot Parkway (P2 & P3) is visually complete but barriered off.
    • Few masts and cantilevers now up on the Didcot Avoiding Line, which finish at Appleford; Appleford LC being the limit of structures for the time being.
    • Oxford Lines west of Didcot Pkwy wired as far as the loco fuelling sdg; Down Oxford as far as 53m 31ch, Up Oxford as far as 53m 42ch. Didcot avoiding lines have sprouted masts (4 portals, 2 TTCs), with a wire pair over the Down Didcot Avoider.
    • A note on Steventon: Wires up under the High St Bridge (aka the "Brunel Bridge"); however, the bridge may well be demolished in CP6. "Temporary" parapet work to protect passers-by from stray currents now complete. Wires west of Causeway Crossing are only authorised for passenger service on 80x trains in both directions, however, 387s are allowed to run empty to/from Cocklebury sidings under AC. The appeal to demolish the bridge is due to occur in the autumn (of 2019). The discussion continues.
    • Overruns through Swindon Jct (77m 36ch) onto the Golden Valley Line have also been wired.
    • Swindon Cocklebury Sidings in operation for Class 387 stabling as of 2/1/19.

    The "Main Line"; Wootton Bassett Jct - Chippenham (Cocklebury Lane Bridge) - LIVE
    Until further notice, the 25kV transmission wires will run in a trough from Cocklebury Lane Bridge (just east of Chippenham) to Thingley Jct. Large steelwork is expected to remain in situ until wiring is authorised west of Thingley, but some specific items may be poached if required elsewhere (and duplicates aren't stored at RAF Wroughton). Details given in the "Postponements" section.
    • Both lines are LIVE, signed off for passenger use, and in service from Wootton Bassett Jct to Christian Malford (93m 31ch) as of 0700 on 21/04/2019 (Easter Sunday).
    • Catenary, contact & Earth wires are up over/adj. to both lines from Cocklebury Lane to Wootton Bassett Jct.
    • Limit of AT Feeding: the Auto-Transformer at Christian Malford.

    Chippenham (Cocklebury Lane Bridge) - Thingley Jct
    • No piles in Chippenham station, nor any masts affixed to the viaduct.
    • All piles in and majority of masts (and cantilevers) up from the western end of the viaduct to Thingley Junction (where the feeder station will be). Most TTCs have booms from beyond the viaduct to Thingley East Junction. About 14 masts are up in the vicinity of Thingley Feeder Stn, 2 of which have TTC booms affixed. Another has an STC boom.
    • Piles continue westwards to the next bridge.

    Thingley Jct - Keynsham
    • No wiring for the foreseeable future, but overbridges between Thingley Jct & Box Tunnel have all been rebuilt. Corsham Main Road Bridge needs its parapets raising. New aqueduct & footbridge at Corsham complete.
    • Both Box & Middle Hill Tunnels have had track lowered.
    • A new footbridge has been built at Ashley Box.
    • Piles also in (and have been for over a year) at Ashley (beyond Box Tunnel) - these might well be trial piles.
    • Bathampton Jct to beyond Sydney Gardens has had track lowered. A new signal gantry at Bathampton Jct was installed over Xmas 2017 and is now in use after the removal of the old gantry in May 2019.
    • Bath Spa platforms realigned & raised, with track also slewed.
    • Track through Oldfield Park & Keynsham now lowered.
    • A lot of piles are in along the embankment around Saltford and Keynsham in readiness for future wiring.

    South Wales Main Line (Wootton Bassett Jct-Bristol Parkway-Severn Tunnel-Newport-Cardiff)

    Wootton Bassett Jct to Filton Jct (inc. Bristol Parkway) - LIVE
    • Wires from Wootton Bassett Jct to Bristol Parkway in passenger service since 30/12/18.
    • All 6 through Lines at Bristol Parkway have been wired and are live.
    • Live wires continue to Filton Jct & Stoke Gifford IEP Depot; Chipping Sodbury Goods Loop and the Cheltenham Curve overrun (as far as the limit of wiring) are also fully wired and live.
      • Limit of Live Wires on the Filton Lines (+ Down Bristol Parkway Relief): 112m 23ch.
      • Limit of Live Wires on the Charfield Lines (from Westerleigh Jct): 120m 59ch.
    • Filton Bank bridge works (mileages all from Temple Meads):
      • Easton Rd Overbridge (1m 18ch) completely rebuilt.
      • Narroways FB (2m 12ch) & Ashley Hill FB (3m 11ch) replaced.
      • Bonnington Walk Overbridge (3m 62ch) - parapets raised.
      • FB south of Filton Abbey Wood (4m 18ch) will need work if wiring is to occur.
    Filton Jct - Severn Tunnel
    • Stoke Gifford IET Depot all wired and energised.
    • Patchway Tunnels conductor rail installed.
    • Wires extend westwards from Filton Jct through Patchway and Pilning (across all lines) to the Severn Tunnel (on BOTH lines).
    • Limit of Live Wires on the Tunnel Lines extended from Stoke Gifford Jct to Patchway Jct (112m 68ch) as of 0220 on 12/5/19.
    • Cattybrook Brickworks Bridge closed since 18/3/18.

    Severn Tunnel - Newport
    Due to have IETs in AC service by next year - hopefully sooner!
    • Severn Tunnel Conductor rail in place.
    • Wires are now up over all lines (both Tunnel Lines, both Main Lines & the Down Relief) at STJ Station; this also includes the overruns on the mains towards Chepstow. Wires continue westwards to Magor Bridge (Redwick Rd?)
    • The Up Tunnel Loop between STJ & the Tunnel is fully wired.
    • Ground trunking currently being installed at STJ in preparation for the electrical feed.
    • Feeder cables now hang from both the eastern set and western set of Switchgear Masts.
    • Masts going up between the M4 Bridge & Bishton Flyover. These include:
      • Two opposing pairs of TTC masts have gone up between Church Rd Bridge & the Playing Fields Footbridge. These may now be bearing wires.
      • Two large uprights have gone up between Undy Playing Fields footbridge & "the ramp" bridge at Magor on opposite sides of the line; these may well take a portal boom.
      • Another 3 masts (two for a portal boom, one a TTC with boom up) have appeared east of "the ramp" bridge at Magor; these join the sole TTC on the Up side by the bridge.
      • 4 TTCs are up west of "the ramp" bridge; at least 3 bear SPS. West of these, a Portal (due to take mid-point anchor terminations) has gone up.
      • The signal gantry at Magor (west of the West End Footbridge) has been replaced by 4 signals on posts; this should mean its removal prior to electrification is imminent. A TTC with SPS is up over the Mains there too.
      • Around the aforementioned doomed signal gantry, another MPA Portal and a 3-track portal have gone up, as well as more 4-track Portals & TTCs - the gap is closing!
      • 1 mast is up to the west of Redwick Rd Bridge (by the Down Relief), and a mast due to bear a portal is up to the east of Whitewall Footbridge (by the Up Main). A "Slim" TTC is up over the centre pair of lines just east of Redwick Rd bridge. OTP is in place for a masting operation by Redwick Rd compound.
      • This area of Magor (the site of the old station) still has a few gaps.
      • NR are currently working on wiring all 4 lines between Magor & Bishton (as of week beginning 6/5/19). Up Relief Wired through Magor old station. Mains also wired but contact wire varies across all lines; the Up Relief is missing some elsewhere in Magor. ATF wires going in around Magor too, but only on the Down side.
      • Plenty of TTCs (all of them, perhaps?) and a 4-track portal are up between the A4810 and the bridge over the eastern end of Bishton Flyover. Steelwork (mainly TTCs) continues to a large Tensorex Anchor Portal at the eastern end of Bishton Flyover.
      • Over Bishton LC, ALL wires (2 Earths, 2 ATFs, and 4 C&C pairs) are now up. This continues to Somerton Rd Bridge on all lines.
    • A run of Earth Wires & ATF wires have been strung up on the Relief side (adjacent to the DR) between Llanwern Works East Connection & Llanwern West Jct. The AEW on the Up side now continues to past Lliswerry Pond, where Bird Flight Deflectors have been installed.
    • Just east of Somerton Rd Bridge, a Tensorex Anchor Portal has gone up.
    • 6-track portals, probably 'Vierendeels', going up around East Usk Yard (approx. MP157 1/2).
    • Between the Maindee Jcts (157m 74ch to 158m 16ch), a cluster of piles is in beside the Down Relief; these are complemented by masted piles on the Main side (adjacent to the Up Main).
    • Both Up & Down Hereford Lines are wired between Maindee West Jct & Maindee North Jct (41m 03ch from the former Rotherwas Jct, just south of Hereford); the Limit of wires is just north of signal "NT 1559".
    • The gap between the Maindee Triangle (Caerleon Rd Bridge) & East Usk Yard (Somerton Rd Bridge) is closing, with the erection of a number of back-to-back non-Series 1 TTCs in East Usk Yard.
    • Caerleon Rd Bridge is now renewed.
    • At the AT Feeder Station at the Maindee Triangle, the tall masts have now gained their spanwires in readiness for the C&C below.
    • The first wire run has now gone up over the Usk Bridge; C&C is now up over the Down Relief from the Tensorex portal immediately east of the bridge, through P1 at Newport and up to Hillfield Tunnel.

    Newport
    • All canopies now cut back.
    • All steelwork in Newport is complete. Remaining SPS and Registration Arms are also being installed.
    • P1 and the Down Relief (Through) Line wired.

    Newport - Cardiff
    • Plenty masts up around Gaer Jct (159m 32ch) north of Cardiff Rd Bridge (the B4237):
      • one by the Down Relief;
      • two by the Up Main (one of which is a boomed TTC with SPS);
      • three by the Gaer Jct - Park Jct Chord.
    • Around 6 piles are in adjacent to the Up Main between Gaer Jct and Ebbw Jct (160m 07ch); these will probably take masts for portal booms. One such boom appears to have gone in! Currently unknown if Alexandra Dock Jct Yard will be electrified.
    • Lots of steelwork up immediately behind the signal gantry adjacent to the Up Main at Ebbw Jct; this includes a full portal boom and a TTC acting as an overrun mast on the Ebbw Vale branch.
    • Almost all steelwork up from Ebbw Jct to Long Dyke Jct (169m 35ch) east of Cardiff Central; most SPS is now up too.
    • ATF wire installed on the Up Main between Lighthouse Rd & New Dairy Farm bridges. In the Up direction, the Earth Wire is in place until just before the bridge over the Ebbw River.
    • Wires up through Duffryn on both Main lines between the Ebbw River Bridge & New Dairy Farm Bridge, after which it switches to both Relief Lines.
    • Wires up across all 4 tracks between Pengam Jct (168m 40ch) & Marshfield.
    • About 4 or 5 portals have been erected just west of Pengam Jct; 5 masts are up on the Up side east of Rover Lane bridge, complemented by 2 on the Down side.
    • 1 run of C&C has gone up between Moorland Road Jct (168m 65ch) and Long Dyke Jct (169m 35ch) over the Reliefs; this is assumed to be a crossover as it crosses from one Relief line to the other.
    • At Long Dyke Jct, all masts are up, and the ATF wire is now up over the Relief Lines.
    • In the Pellet St area, a Mid Point Anchor Portal Boom has now gone up.
    • Just east of St. Mary's St Bridge, 2 hexagonal Tensorex Portals have been erected over all tracks.
    • Over the bridge over St. Mary's Street in Cardiff (just east of Central), and immediately to the west of the bridge, 5 portal booms spanning all tracks have gone up.
    • Similar bespoke mast foundations are going in just east of Bute St Bridge, near the junction with the line from Queen Street.
    • Splott Rd Bridge upgrade work now complete.
    Cardiff Central - Platforms 0-4 to be wired
    • Re-signalling completed. Platform 0 now open. 3 masts now up over P0/1 with TTC booms.
    • An Anchor Portal (of the hexagonal "TGBU" variety) has gone up over P2/3, just east of the canopies.
    • All large steelwork for P4 is now in position.
    • Most (if not all) TTC masts for P2 & the Up Through Line, along with P3 & the Down Through Line have gone up at the station. Some already have SPS.
    • Brackets appear to be in place on the coping stones on the Taff Viaduct (at the western end of the station).
    • Plenty piles up adjacent to Cardiff Canton. A number of these now appear to have masts on them, as seen from a westward-facing shot from Central. Portals next?
    • Brickwork Sidings to be increased in length (and electrified) to accommodate GWR Class 387s; the first masts and cantilevers have now gone up, with around 2 boomed TTCs and 2 STCs in position.
    • Proposed Limit of Wiring: Leckwith Loop North Jct (171m 55ch) at a guess.
    Swansea IEP Depot
    • New IEP Depot at Maliphant Sidings, Swansea now complete; all steelwork up. SPS, such as Insulators, Switchgear and Cantilevers have all been taken down, leaving only bare masts/booms in situ.

    GWML/SWML Blockade Works (2018):
    • 6/7 to 3/12: Reduced capacity (2 lines only) for wiring work between Newport & Cardiff Ctl.
    • 15/9 to 6/10, and 13/10 to 14/10: Bristol Parkway electrified.
    • 27/10 to 18/11, 24-25/11, 1-2/12: Filton Bank 4-tracked.
    • 11/11: Bristol TM to Bath Spa resignalled.
    • December blockades at Bristol Parkway & Didcot Parkway done.
    • Christmas-New Year Blockade at Severn Tunnel Jct done.

    GWML/SWML Blockade Works (2019):
    • 20/1/19, and 10/2/19: Newport to Bridgend blockaded (inc. Cardiff Central) for electrification work AT Cardiff Central; both done.
    • 17/2/19: Bristol Parkway to Newport blockaded for electrification work over the Usk Bridge at Newport; done.
    • 31/3/19: Newport to Bridgend blockaded (inc. Cardiff Central) for electrification work AT Cardiff Central; done.
    • 19/4/19 to 22/4/19: Bristol Parkway to Newport blockaded for electrification work in the Severn Tunnel Junction area; done.
    • 27/4/19 to 28/4/19: Bristol Parkway to Newport blockaded for electrification work in the Severn Tunnel Junction area; done.
    • 9/6/19: Newport to Bridgend blockaded (inc. Cardiff Central) for electrification work; done.
    • 16/6/19: Newport to Bridgend blockaded (inc. Cardiff Central) for electrification work; done.
    • 27/7/19 to 28/7/19: Bristol Parkway to Cardiff Central blockaded for electrification work.
    • 25/8/19 until 14:00: Bristol Parkway to Cardiff Central blockaded for electrification work.
    • 8/9/19 until 14:00: Bristol Parkway to Cardiff Central blockaded for electrification work.
    • 14/9/19 to 15/9/19: Newport to Bridgend blockaded (inc. Cardiff Central) for electrification work.
    • 22/9/19 until 14:00: Newport to Bridgend blockaded (inc. Cardiff Central) for electrification work.
    • 29/9/19 until 14:00: Newport to Bridgend blockaded (inc. Cardiff Central) for electrification work.
    • 13/10/19 until 14:00: Newport to Bridgend blockaded (inc. Cardiff Central) for electrification work.
    • 20/10/19 until 14:00: Newport to Bridgend blockaded (inc. Cardiff Central) for electrification work.
    • Details of any further OLE-related blockades will be added as they are made available.

    Berks & Hants Line (Reading-Newbury) - LIVE
    Electric trains in squadron service.
    • Wires from Oxford Rd Jct are LIVE to the limits of electrification (53m 42ch on the Newbury Lines, 38m 07ch on the Basingstoke Lines) since 0650 on 21/10/18.
    • Class 387s are now in service on Reading-Newbury services as of 31/12/18.
    • Within Reading West, piles for the new footbridge (under Murphy's remit) are in, but have been "decapitated" (i.e. shortened) and capped until a new footbridge solution is found.
    • New stairs from Reading West's Down platform to Oxford Rd are now in use. Work is ongoing for a permanent footbridge replacement.
    • Parapet work on Tilehurst Rd Overbridge has been completed on both sides, although Heras fencing was still in place at the end of April.
    • Platforms extended at Reading West, Theale, Aldermaston and Thatcham.
    • Newbury's new footbridge is now open; lifts in service as of 19/4/19.
    • Immunised signalling continues to about MP55 1/2. Bedwyn Turnback Siding now extended to accommodate 5-car IETs.

    Project Postponements
    • Thames Valley Branches:
      • Windsor & Henley deferred to at least CP6. The first few yards of the Windsor branch (Not the Henley Branch) have been wired as an overrun.
      • Marlow removed from scope of current programme. The first few yards of the branch have been wired as an overrun.
      • Southcote Jct to Basingstoke deferred to at least CP6. The first few yards of the Basingstoke Lines have been wired as an overrun.
    • Appleford LC to Oxford paused; if CP6 accounts allow for wiring to be extended to Oxford, it would be very likely to happen now that Oxford has been remodelled.
    • Catenary & Contact wires between Chippenham (Cocklebury Lane Overbridge) & Thingley Jct have been deferred until at least some point in CP6. All Large steelwork to remain, unless required elsewhere.
    • Bristol Temple Meads to Bath & Bristol Parkway paused, dependent on Bristol resignalling:
      • Taunton-Bristol Parkway completed over Easter 2018;
      • Bristol Temple Meads to Bath Spa completed in November 2018;
      • The WSM stretch from Flax Bourton Tunnel to Cogload Jct remains outstanding;
      • Track remodelling of Bristol East Jct remains outstanding;
      • Filton Bank 4-tracking completed Autumn 2018.
      • Further Signalling works due in 2019: Bath Spa due to be resignalled over the 11th/12th of May (done), and the 23rd of June. N.B. The Severn Beach Line will be closed for resignalling works on Sunday 7th of July.
    • Bristol Temple Meads' "Midland Shed" to be reopened in CP6 at the earliest, after Bristol resignalling is complete and the PSB is demolished.
    As always, do let me know if I've missed anything!
    (apologies to anyone who saw it in a state of source code chaos too).
     
    Last edited: 24 Jun 2019
  22. Phil G

    Phil G Member

    Messages:
    150
    Joined:
    16 Oct 2017
    Waiting for train to Bristol this morning and delayed due to damage to overhead wires! Delay started just after Steventon.
     
  23. 59CosG95

    59CosG95 Established Member

    Messages:
    4,214
    Joined:
    18 Aug 2013
    Location:
    WIM/PBO
    Oh dear. Still, at least it's happened far fewer times on Series 1 equipment than the Mk3-era headspans on the ECML and the "London section" of the GWML!

    Did GWR state where the fault was?
     
  24. Phil G

    Phil G Member

    Messages:
    150
    Joined:
    16 Oct 2017
    No but train on time at Steventon then 13 late at Wantage Road so presumably between the two. It didn't manage to make any time up so I was thinking it may have been on diesel after that. Of course the reason given may have been rubbish.
     
  25. JN114

    JN114 Established Member

    Messages:
    2,121
    Joined:
    28 Jun 2005
    Which train? I may be able to do some digging...
     
  26. Chonner

    Chonner Member

    Messages:
    13
    Joined:
    6 Apr 2018
  27. Phil G

    Phil G Member

    Messages:
    150
    Joined:
    16 Oct 2017
  28. JN114

    JN114 Established Member

    Messages:
    2,121
    Joined:
    28 Jun 2005
    ADD (Automatic Drop Device) Activation on traction changeover from Diesel to Electric was the issue with 1C03. Subsequent trains have to be cautioned until OHL staff examine the line. The unit will be restricted to Diesel only until it can be examined on maintenance depot.

    It’s normally a little tricky to tie down whether it was an infrastructure fault that caused the ADD, or a spurious ADD that causes (ultimately) unnecessary cautioning.
     
  29. Phil G

    Phil G Member

    Messages:
    150
    Joined:
    16 Oct 2017
    Thanks for the info, hopefully it's not an infrastructure issue.
     
  30. JN114

    JN114 Established Member

    Messages:
    2,121
    Joined:
    28 Jun 2005
    While I’ve been in the office this afternoon it’s only been for briefings, not been let loose on the desk today. As far as I can tell though it’s all back to normal working so even if it were an infrastructure issue it’s very minor.
     

Share This Page