yes that's rightIs it just the single platform in open air that the diesels use at Stansted?
yes that's rightIs it just the single platform in open air that the diesels use at Stansted?
We seem to be not be receiving anymore new trains at the moment... is April going to be a big month
To be honest XC have had ambitions to run 2tph from Birmingham to East Anglia for a while now, but that should be possible when Ely North is sorted. If the Liverpool service gets split at Nottingham I reckon diverting them from Peterborough to serve Leicester and Birmingham would be a reasonable way of increasing capacity there and still offering useful direct journeys from Norwich, serving Grantham and Nottingham only doesn't really achieve very much IMO.
I don't think anyone is suggesting mixing the two up.
units 755409 + 755410 have been reported to be arriving tomorrow morning.
What do we think, entire fleet of 755/4s here before an Aventra turns up? Whole Stadler fleet in service by then maybe?
Many, but probably not all. I'd certainly say more than half, including at least some of both subclasses of 745.What do we think, entire fleet of 755/4s here before an Aventra turns up? Whole Stadler fleet in service by then maybe?
Are diesels banned from the longer platforms? In any case the long platforms are in almost constant use by Stansted express. When they go 12 car it won't even be possible to share like they do now with the Cambridge shuttle.Is it just the single platform in open air that the diesels use at Stansted?
The pollution levels within the station would be horrendous if they were allowed to use the usual platform under the airport!Are diesels banned from the longer platforms? In any case the long platforms are in almost constant use by Stansted express. When they go 12 car it won't even be possible to share like they do now with the Cambridge shuttle.
Are diesels banned from the longer platforms? In any case the long platforms are in almost constant use by Stansted express. When they go 12 car it won't even be possible to share like they do now with the Cambridge shuttle.
I can’t say I’ve been following the progress in any detail despite being a WAML commuter. But I did notice just now workmen at Sawbridgeworth installing a “Class 755 3-4 cars” stopping mark on the down platform, and I saw orange jackets poking around at Harlow Mill too.
I've got neckache now.
It does seem this is an underused line but i would say its prime for electrification as an infill to cambridge to improve speeds and make it more competitive in journey times
It does seem underutilised. A Norwich - Peterborough - Birmingham service via Ely West Curve would actually be very useful. If you want to get to Birmingham from anywhere east of Cambridge it's quicker to go via London at present. And quicker still to drive which is what I tend to do.
I think one of the long platforms at Stansted Airport can accommodate 16 x 20m stock - pretty sure I saw 2x8car trains in one platform when there was disruption once
755408, 755407 and 755405 tripled up today on the 5Q61 from Norwich to Diss
Problem is that whilst Ely to Norwich may be under utilised try pathing trains through the single lead junctions at Ely North Jn and Trowse Jn plus Trowse Swing Bridge. Heading onto Stansted is even more difficult with Ely, Cambridge and Stansted North Jn to Stansted Airport constraints to consider.
Ely North is somewhere in a plan to be upgraded isn't it?
Trowse must have capacity, there's only 8 trains an hour over the bridge. The bridge could be doubled quite easily as the original bridge was just downstream of the present one and there are sidings almost up to the abutments on both sides of the river.
Would it not require the Overhead Wires to be moved to accommodate the Doubling?But try to get all the constraints I have outlined above to marry up. Its almost impossible. I'll believe it when I see it concerning The swingbridge for doubling and also Ely North Jn.
(my own veiws) - wouldn't think any Stadler fleets will be complete when the first Adventra units appear but will certainly be a good amount of the Stadler units about.
not to sure what the current situation with the Aventras is??.
Would it not require the Overhead Wires to be moved to accommodate the Doubling?
An Aventra was in Litchurch Lane yard last Friday (22nd March) which seemed to be complete and in GA livery; sorry can't be more explicit, but was passing on a bus (on London Road), and vision was blocked by a class 66
Very unlikely they'll be running this year then. Any sign of 317506 coming back from Kilmarnock?First one currently scheduled to move to Ilford in June for testing. Take that with as much salt as you wish.
Very unlikely they'll be running this year then.
There's no reason why not, but then there's no reason why either. Being AC-only the systems on the 720s should be a bit simpler but the level of issues experienced by the 710s is astounding. While I'm sure the experience from the 710 project will have helped, the fact that their introduction went so wrong means I think it would be a bit optimistic to assume everything will go to plan with the 720s. There are a lot of routes to cover where the over-sensitive software in the 720s will be put to the test. They will also be covering areas where there are already precedents for having issues with new EMUs (e.g. north of Stowmarket and the Southend branch). I think it's highly unlikely that the delay between delivery of a unit for testing and entry into service will be as long as it's been for the 710s, but I'm almost certain there will still be some delay. They have to pass sufficient tests to gain approval for passenger use and then commence staff training. Doable in 6 months but probably only just - if any issues are thrown up during testing, I imagine they won't see passenger use until 2020. At present I'd hazard a guess at 12 months after their original planned introduction, so February ish.Can you explain why, please?
I believe that the 710s have different software to the 345s and that this has contributed to the delay in their introduction into service, but won't subsequent builds of Aventras have the same as has been "proved" in the 710s? Consequently, won't testing/ commissioning/acceptance of Aventras for GA and others be quite "quick" by comparison?
1. With Modern EMUs there is physically hardly any difference between AC only and AC+DC. The 3phase drives are fed from a DC bus. Physically Shoe + Mounting, cable and MCB.There's no reason why not, but then there's no reason why either. Being AC-only the systems on the 720s should be a bit simpler but the level of issues experienced by the 710s is astounding. While I'm sure the experience from the 710 project will have helped, the fact that their introduction went so wrong means I think it would be a bit optimistic to assume everything will go to plan with the 720s. There are a lot of routes to cover where the over-sensitive software in the 720s will be put to the test. They will also be covering areas where there are already precedents for having issues with new EMUs (e.g. north of Stowmarket and the Southend branch). I think it's highly unlikely that the delay between delivery of a unit for testing and entry into service will be as long as it's been for the 710s, but I'm almost certain there will still be some delay. They have to pass sufficient tests to gain approval for passenger use and then commence staff training. Doable in 6 months but probably only just - if any issues are thrown up during testing, I imagine they won't see passenger use until 2020. At present I'd hazard a guess at 12 months after their original planned introduction, so February ish.
Agreed, like the later batches of electrostar....Consequently, won't testing/ commissioning/acceptance of Aventras for GA and others be quite "quick" by comparison?