Nicholas Lewis
Established Member
Dept of Transport has published it first 6 monthly report into the project covering progress as well as future phases
https://www.gov.uk/government/speeches/hs2-6-monthly-report-to-parliament
Already reporting cost pressures
and earliest opening date starting to sound shaky despite its 9 years away
Still I guess they are learning from Crossrail debacle
https://www.gov.uk/government/speeches/hs2-6-monthly-report-to-parliament
Already reporting cost pressures
HS2 Ltd is currently reporting cost pressures of £0.8bn. If not successfully remediated, these pressures will be drawn against the Company’s delegated contingency. These pressures are driven by:
enabling works to prepare the line of route for construction. These have been underway since 2017 and in some areas have encountered more significant challenges than anticipated, such as the need to safely remove more asbestos than expected, resulting in increased scope and duration. These additional costs are likely to be in the order of £0.4bn according to HS2 Ltd
Euston Station, where further development of the baseline scheme has identified a significant cost pressure, which HS2 Ltd is currently reporting as in the order of £0.4bn. Further work is ongoing to validate these initial estimates and this could identify further pressure. As this remains at the design stage, work is underway to consider opportunities, efficiencies and scope reductions in order to redress these pressures and we will report further on this in the next report
and earliest opening date starting to sound shaky despite its 9 years away
On Phase One, the Delivery into Service (DIS) range for initial services from Old Oak Common to Birmingham Curzon Street remains 2029 to 2033. HS2 Ltd continues to predict that it will provide services within this range but notes some pressures on the earliest date from COVID impacts and delayed handovers from Enabling Works, which it is seeking to mitigate.
Still I guess they are learning from Crossrail debacle