• Our booking engine at tickets.railforums.co.uk (powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Lowering track under bridges because of tall trains

Status
Not open for further replies.
Joined
8 Apr 2009
Messages
249
Location
Sheffield
A friend of mine who is a resident of renishaw received a letter today stating track works may cause noise pollution because of the lowering of the track near the golf course due to taller trains passing through!
The line is the freight line between Sheffield and Chesterfield does anyone have a clue what this is?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Lrd

Established Member
Joined
26 Jul 2010
Messages
3,018
The same happened at Southampton, they had to lower the entire trackbed through the tunnel to allow the 'new' taller (9ft6in) containers to pass through.
 

DaveNewcastle

Established Member
Joined
21 Dec 2007
Messages
7,387
Location
Newcastle (unless I'm out)
and is what was being done to one side of the Panmanshiel Tunnel (while the other side had already been lowered with trains in service) when it collapsed trapping those inside.
 

43106

Member
Joined
6 Jul 2008
Messages
376
Location
South-ish Edinburgh
The only occasion I know when track was being lowered was when the Carstairs - Edinburgh line was electrified - it was simply to allow the OHLE to fit. I actually saw them doing it in the late 1980's under the Slateford Road bridge. IF they have decided to electrify the MML, then this could be preparatory work for it.
 

tirphil

Member
Joined
27 Jan 2011
Messages
275
Location
Wales
Hibel Road and Prestbury tunnels on the Macc & Colwich both had their trackbeds lowered during the WCML upgrade.
 

Ploughman

Established Member
Joined
15 Jan 2010
Messages
2,882
Location
Near where the 3 ridings meet
A combination of Track Lowering and Bridge lifts was used for all the lines affected by the electrification for Leeds North West.
I seem to remember a figure of 30 track lowerings to get the clearance for the wires.
For a basic lowering approx 150m of track either side of the bridge would be taken out, ballast dug out to grade then relaid to new levels.

On one stretch Shipley to Bradford we had to track lower under 4 consecutive bridges. We wanted to uplift the lot and dig out from start to finish so it would look better and give a better ride. But no the high ups stipulated we dig each bridge to its own lowering scheme. In the end over the 1 mile length 1 panel of track was not removed and the result is a Roller Coaster ride.
 
Last edited:

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,265
It will be interesting to see if the same needs to be done to the Severn Tunnel during electrification of the SWML. I gather that the guage is a bit tight there alerady.

Railway myth repeated as fact? There's actually no evidence that there's a problem whatsoever.

NR quoted here: http://www.rail.co/2011/04/28/electrification-delivering-the-transformation/
...said there is ample room for electrification in the tunnel:

As for the tunnels – the big one I guess you’re interested in on GW is the Severn which in fact is really quite an electrification-friendly tunnel with quite good clearances. From the initial survey work we’ve done already, we’ve found that the room in the roof of the tunnel is capable of accommodating normal low encumbrance equipment like we put in tunnels elsewhere in the UK. And it would also be perfectly appropriate to use solid beam technology through the tunnel. We will consider both options when we move into the detail design phase.
 

W230

Established Member
Joined
6 Jan 2012
Messages
1,214
IF they have decided to electrify the MML, then this could be preparatory work for it.
I think that this section of track at Renishaw is part of the Tapton "Old Road" and not the MML. In which case it's nearly all freight so is likely to be for the larger 9'6" containers as already suggested.

wikipedia said:
All passenger services north from Chesterfield now serve Sheffield, and the section north from Tapton Junction to Rotherham Masborough (the "Old Road") has been freight only since July 1954, although it is occasionally used as a diversionary route. It serves as a bypass line which keeps freight trains away from the congested lines through central Sheffield.
 

LE Greys

Established Member
Joined
6 Mar 2010
Messages
5,389
Location
Hitchin
Just out of curiosity, will all the old GWR overbridges go when the wires are put up west of Airport Junction or will they be raised/the track be lowered? I can understand if there are preservation orders on them, and they are nice bridges, but it seems a bit expensive just for the sake of that.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
31,265
Just out of curiosity, will all the old GWR overbridges go when the wires are put up west of Airport Junction or will they be raised/the track be lowered? I can understand if there are preservation orders on them, and they are nice bridges, but it seems a bit expensive just for the sake of that.

They will do whatever is most cost effective at each location. They have already altered a number of overbridges quite significantly west of Reading for gauge clearance anyway.
 
Status
Not open for further replies.

Top