GRALISTAIR
Established Member
Fantastic detail thanks so much 59CosG95
Thanks very much! More photos inbound...Fantastic detail thanks so much 59CosG95
Totally atmospheric photos with the silver-grey portal booms etc. against the dull grey, even threatening, sky! Thanks 59Cos95 for these and the explanations. I see what you mean by the new, as yet uncorroded, copper wire.Finally, a quick drive to Kettering to find the northernmost structure on the Fast lines:
View attachment 79476
SPC3/116/654. North of here, only the Down Slow & Up Slow have wires. This is adjacent to Northfield Avenue, Kettering - the street and railway sandwich the local allotments.
Photo update pt. 1: Missing Contact wire on Down Slow between Finedon Rd & Harrowden Jn complete.
View attachment IMG_2871.jpg
It is notably more orange when installed as the metal hasn't oxidised - but I did increase the saturation to highlight the difference!Is it that orange in real life?
We are writing to update you with the latest information on plans to improve East Midlands Railway services and the final stages of the transformative £1.5 billion Midland Main Line Upgrade. While we have been making good progress with the infrastructure and other preparations, coronavirus has, inevitably, caused a delay.
As you will be aware following discussions since the start of the East Midlands Railway franchise and the public consultation which followed, December 2020 was due to see a significant timetable change.
The December 2020 timetable delivers a fundamental uplift in capacity and frequency for services on the Midland Main Line. It provides the capacity for EMR to operate six (currently five) trains per hour between London St Pancras, the East Midlands and South Yorkshire as well as improving reliability and performance. This timetable change will also see the introduction of electric trains to the EMR franchise, making use of the newly installed overhead electric lines between Bedford and Corby.
EMR Regional services will have benefited too, with new journey opportunities and improved connectivity ahead of a more significant improvement in December 2021.
The impact of coronavirus
The coronavirus pandemic has had a profound impact on businesses and industries across the UK– including the railway. As a result, the benefits to EMR passengers we were due to deliver in December 2020 are now planned for May 2021. Although this may not come as a surprise, we share your disappointment that this is unavoidable. It is due to three principal reasons:
- The final stages of electrifying the line between Bedford and Corby has been delayed by the impact of social distancing measures. A new method of working had to be developed to enable working on the overhead lines at height and in confined spaces.
- The requirements of social distancing has also affected the ability to deliver critical training, including driver training.
- Supply chain issues, complicated by coronavirus, which have affected the whole industry. This has included delays to the cascade of electric units.
We are all immensely disappointed by this delay, but given the unprecedented impact of coronavirus and our commitment to ensure major changes in train services are delivered safely and effectively, we have no choice.
Next steps
The change to May 2021 does pose some challenging questions concerning EMR’s train fleet, particularly the use of High Speed Trains (HSTs). Discussions are already underway and we will update you as soon as possible.
In addition, this also creates challenges for the successful introduction of an improved EMR Regional timetable in December 2021. Work is ongoing to understand the knock-on implications for these long anticipated changes.
In terms of the May 2021 timetable delivery, EMR and Network Rail are working together to develop a formal timetable submission for May 2021 and this will be submitted in late summer. At this point, EMR will also publish results of the public consultation which was completed earlier this year and details of the timetable submission to show the steps and decisions taken in response to feedback from customers and stakeholders.
Completion of the Midland Main Line Upgrade
Network Rail is continuing to progress the Midland Main Line Upgrade and expect to have completed the wire runs between Bedford and Corby in the coming months. This will enable the stretch between Bedford and Corby to be fully tested and commissioned this winter.
Further work was always scheduled to continue into early 2021, this includes at stations, some bridge work and maintenance depots. These items are an important part of the upgrade but not essential to the delivery of the timetable.
Conclusion
We are sure you will share our frustration at this news but hope you can appreciate the unprecedented impact the coronavirus pandemic has had on all of us in recent months. We will continue to work together to improve the rail service and will update you further in the near future.
Yours Sincerely,
Gary Walsh
Route Director, East Midlands
Network Rail Infrastructure Limited
Will Rogers
Managing Director
East Midlands Railway
At a guess, based on information provided in the article, these substations would be the new upgraded TSCs (with ATS potential) at Ampthill and by the fast lines just south of Bedford - it does say between Bedford and Ampthill.Are the substations being commissioned in those closures the ones that were called off due to the stormy weather in Feb/March?
Napsbury ATS (Auto Transformer Site); no idea where it's planned to be sited. Perhaps near the North Orbital Commercial Park? (https://goo.gl/maps/SY8ufqBSJ5CAJHSn9; 51°44'02.5"N 0°19'07.3"W)
Can confirm there is a broad stretch of railway embankment at this location between the up slow and the boundary of the industrial estate - used for track access etc. Bit surprised - there's the Napsbury Lane bridge* and then the A414 bridge in close proximity which I would have thought would have been inconvenient. Don't know if the land is still railway-owned but south of the A414 bridge and on the west side of the line opposite 'North Cottages' there was a larger area where once there had been sidings and further back the construction link from the LNWR line used during the 1860s build of the 'London Extension'. Or do they want to keep that clear for a certain possible 'railfreight' terminal?!There or thereabouts.
- Work to transform the former Kettering Yard into an EMU stabling facility (KES; Kettering Electric Stabling) is nearly complete: wires are all now up. Final snags to be undertaken.
Network Rail urges passengers to check before travelling over next two weekends as vital improvement work takes place on Midland Main Line
Region & Route: London North Eastern & East Midlands
Network Rail is urging passengers who have to travel over the next two weekends to check their journeys, as vital work continues on the £1.5billion Midland Main Line Upgrade.
On 18/19 and 25/26 July, Network Rail engineers will carry out work to install the final section of the overhead line equipment on the route, in preparation for bi-mode trains, which are quieter and better for the environment, to run on the line in future between Bedford and Corby, via Kettering.
The overhead power lines carry 25,000 volts of electricity, enough to seriously injure or kill anyone that comes into contact with them. Network Rail is warning people of the dangers of trespassing on the tracks, and you can find out more about our hard-hitting safety campaign, Always On, here: https://www.networkrail.co.uk/commu...community/railway-safety-campaigns/always-on/
Work has already taken place to commission and test two new substations on the route to provide the power which is needed to allow more trains to run in future. Over the next two weekends, vital work will also be carried out to test the electrical system, upgrade sections of the track on the Midland Main Line and improve the surfacing of the platforms at Wellingborough and Kettering stations.
There are various changes to services between Sheffield/Nottingham/Derby and London St Pancras International over the two weekends to enable to work to be completed safely. Network Rail, East Midlands Railway and Govia Thameslink Railway are urging passengers to check before travelling and allow plenty of time for their journeys.
Gavin Crook, Principal Programme Sponsor for Network Rail, said: “We would like to thank passengers for their continued patience whilst this essential part of the Midland Main Line Upgrade is carried out.
“This work to install the final section of the overhead line equipment and carry out vital testing is a major step towards the completion of the Midland Main Line Upgrade, which will bring improved, faster journeys for passengers, with more seats and a more reliable railway.
“We strongly advise passengers who must travel to check their journeys in advance with National Rail Enquires or their train operator and allow plenty of time to travel.”
Lisa Angus, Transition and Projects Director for East Midlands Railway, said “We are advising any passengers who may need to travel to / from London over the weekends of 18/19 July and 25/26 July, to check our website as there is disruption to our services and rail replacements in place for part of your journey.
“The work taking place over these weekends is a significant milestone of the Midland Main Line upgrade. The final installation of the overhead line equipment will mean more reliable, faster journeys for our passengers in the future.
“As always, we thank our passengers for their patience whilst this crucial work is taking place.”
Jenny Saunders, Passenger Services Director for Thameslink and Great Northern, said: “Our services between Bedford and London are likely to be busier over the next two weekends than is usual currently, because of this important work further north. Also, trains will be replaced by buses for significant periods, so it will be especially important for people to consider whether they really need to travel, and to plan their journey in advance if they have to use public transport.
“Buses will replace Thameslink services between Bedford and Luton on both Sundays, between Bedford and St Albans during the night of Saturday 25 July, and between Hendon and St Pancras in the early morning of Sunday 19 July. If you do have to travel during any of these periods, please allow plenty of extra time for your journey.”
Network Rail is asking passengers to continue following Government guidance around the use of public transport. Passengers who do travel should wear a face covering on train services and any replacement bus services. However, some passengers are exempt, including young children and people with hidden disabilities or breathing difficulties.
Detail of the service changes:
Saturday, 18 July - Trains to/from Sheffield and Nottingham will start/terminate at Market Harborough. Road replacement services will be in place between Market Harborough and Bedford, and between Corby and Kettering. Thameslink services will run between Bedford and St Pancras.
Sunday, 19 July - Trains to/from Sheffield and Nottingham will start/terminate at Market Harborough. Road replacement services will be in place between Market Harborough and Luton and between Corby and Kettering. Thameslink trains will run between Luton and St Pancras.
Thameslink services will not run between Bedford and Luton and road replacement services will be in place. Road transport will also replace trains between Hendon and St Pancras until 08:55. Thameslink services between Bedford and Gatwick Airport via Redhill will not run. A road replacement service between Gatwick Airport and Purley will call at Redhill.
Saturday, 25 July - Trains to/from Sheffield and Nottingham will start/terminate at Leicester. Replacement road services will be in place between Leicester and Bedford, and between Corby and Kettering. Thameslink services will run between Bedford and St Pancras.
Thameslink services will not run between Bedford and St Albans from 23:00 on Saturday, 25 until 09:30 on Sunday, 26 July. Road replacement services will be in place.
Sunday, 26 July - Trains to/from Sheffield and Nottingham will start/terminate at Leicester. Replacement road services will be in place between Leicester and Luton, and between Corby and Kettering. Thameslink services will run between Luton and St Pancras. Road replacement services will be in place between Bedford and Luton.
Excellent news!It's sufficiently "finished" that there were some dignitaries being shown around on Friday.
Further details with Stage B2 - the isolator switches that have gone live are SPC1/79/864, SPC1/79/860 and SPC1/79/853 (the first three from the left in the image below, courtesy of NR via Rail Technology Magazine); the 4th one (presumably SPC1/79/849) has yet to go live.News from Bedford today.
Boiling down the notices, they read as follows:
Stage 2 (Bedford Station - Down Slow and Up & Down Platform Loop) - current BWA terminations of wire runs in Platform 2 (Down Slow) and 3 (Up & Down Platform Loop) to be extended to the Tensorex portal at SPC2/80/599. (Note the 'SPC1' reference should be SPC2)
Stage B2 (Bedford TSC) - the Across Track Feeds, SIs, Switches and HV Cabling for Bedford TSC are to be treated as live IMMEDIATELY. There are some unfinished works there, but they will probably be dealt with this weekend.
Stage 3B (Bedford Station - Up Fast) - wires on Up Fast through Bedford to be installed, bridging the gap between the anchor at SPC1/79/816 (where the old equipment is presumably terminated, on a new structure) to the fixed-anchor portal at SPC1/80/467 (where live wires on the Up Fast resume).
Road Sign - Bromham Rd bridge closed overnight from 8pm Fri 10th July to 8am Sat 11th July. Presumably this is to remove the redundant temporary pedestrian bridge.
Indeed it is! While SMOS (Structure Mounted Outdoor Switchgear) is nothing new in OLE (Indeed, some exist on masts with OLE elsewhere in the country) but the use of dedicated masts is a fairly recent decision - presumably to make maintenance easier and possible with only an isolation (rather than a line-block or possession as well). All the new MML TSCs etc. have them, and so do all those on the GWML (and other new lines); they've also been added in as part of power supply upgrades on the WCML, ECML and GEML (for Crossrail).That looks like some serious kit.