MatthewRead
On Moderation
The North London line use to be third rail throughout when was the third rail partially replaced by overhead wires?
Actually..........it was electrified on the fourth rail system until the mid 1970's or laterThe North London line use to be third rail throughout when was the third rail partially replaced by overhead wires?
I can remember going right round from Richmond to North Woolwich, must have been early-mid 1990s, and there being four changeovers. 3rd rail at both ends but there was also some in the middle, spliced by two overhead sections. Someone better informed will be able to give the changeover stations. The Class 313 pantograph, which I had unwittingly sat underneath, made quite a hiss and a series of bangs as it was raised or lowered.
Were there ever incidents when the changeover was forgotten?
That's scary, but fascinating.I do remember reading of the stray currents getting into the signalling at the time, not only along the line but also impacting the Victoria Line 80 feet beneath at Highbury. As this had always been a DC section it must have been some aspect of the AC installation.
In the late 1960s, at Stanford University near San Francisco, some very precise instrumented ellectrical experiment with growing plants was found to have started being wrecked by unknown interference. Their chief clue was it was man-made, because it only happened on Monday to Friday in working hours, not at weekends. They did a whole series of tests to trace it, eventually identifying it was the new BART transit system, which had just begun running tests. Thing was, the nearest point on BART was 5 miles from the research labs. That's how far the currents can go.
I do remember reading of the stray currents getting into the signalling at the time, not only along the line but also impacting the Victoria Line 80 feet beneath at Highbury. As this had always been a DC section it must have been some aspect of the AC installation.
In the late 1960s, at Stanford University near San Francisco, some very precise instrumented ellectrical experiment with growing plants was found to have started being wrecked by unknown interference. Their chief clue was it was man-made, because it only happened on Monday to Friday in working hours, not at weekends. They did a whole series of tests to trace it, eventually identifying it was the new BART transit system, which had just begun running tests. Thing was, the nearest point on BART was 5 miles from the research labs. That's how far the currents can go.
I do remember reading of the stray currents getting into the signalling at the time, not only along the line but also impacting the Victoria Line 80 feet beneath at Highbury. As this had always been a DC section it must have been some aspect of the AC installation.
at farringdon they took special measures to stop southbound trains going into the tunnel with pan up.From the AC electrification of Acton to Camden in the mid 90s, the changeovers were at Acton Central (Pan Up), Camden Road (Down), Dalston Kingsland (up), and Hackney Wick (down).
Between Dalston and Hackney Wick the 313s could stay on D.C., but reduced power take due to protection the signalling from the D.C. return currents.
Changeovers were forgotten frequently, and still are. There was one only a couple of weeks ago at Mitre Bridge on the West London Line. Perhaps the most infamous was on the first weekday of London Overground (TfL) operation, when a driver forgot to drop the pan at Hackney Wick, and promptly brought all the wires down at Channelsea Junction.
they were testing current monitoring stuff and looking at the interference generated by thyristor controlled trains. Then a tap changer loco went through and the traces on the monitors went off the scale.I do remember reading of the stray currents getting into the signalling at the time, not only along the line but also impacting the Victoria Line 80 feet beneath at Highbury. As this had always been a DC section it must have been some aspect of the AC installation.
In the late 1960s, at Stanford University near San Francisco, some very precise instrumented ellectrical experiment with growing plants was found to have started being wrecked by unknown interference. Their chief clue was it was man-made, because it only happened on Monday to Friday in working hours, not at weekends. They did a whole series of tests to trace it, eventually identifying it was the new BART transit system, which had just begun running tests. Thing was, the nearest point on BART was 5 miles from the research labs. That's how far the currents can go.
at farringdon they took special measures to stop southbound trains going into the tunnel with pan up.
What were they? Because I never saw or heard of them. And there are various dents and new panels in the Blackfriars roof to prove it!
What were they? Because I never saw or heard of them. And there are various dents and new panels in the Blackfriars roof to prove it!
Actually..........it was electrified on the fourth rail system until the mid 1970's or later
I think it was 1988 with the first section from Stratford to Dalston and then of the freight line through to Camden.
Out of interest when did the West London line become AC?Yes - despite intense briefing and strategically placed operations managers all over the patch for the first few weeks (+ warning notices placed in all 313 cabs) - there were 2 in one day on the West London Line , making NLR the honourary winner of the West London Line lost pan club (taking the trophy off Eurostar and EWS) - we even had issues at Acton Central - and infamously with some empties dropping down at WS23 off the High Level at Willesden (ECS) onto the down DC bay. In the latter case - the arc drew a fire , (as the lost pan short circuited on the juice rails - which burnt out a few signal cables and singed a nearby Bakerloo line train)
To get back to commissioning , I took the first "passenger" AC train from Camden Rd to Hampstead Heath with Glenda Jackson naming 313020 at the latter - Mid June 1996 - (have framed photos) - the West London line opened early to AC , 313009 doing the honours - 10 days before schedule. (though the NL core section Camden to Willesden ran 6 months late as there were structural issues with the viaducts and underlying ballast)
Out of interest when did the West London line become AC?