Progress of New Depot at Brantham, Suffolk

Status
Not open for further replies.

Alfie1014

Member
Joined
27 Jun 2012
Messages
1,126
Location
Essex
The level crossing is a convenient get out clause imho....all the issues are ones that would have been identified if they'd asked local people and staff first. Everyone local knows that it's massively open to flooding, the ground in places is rather toxic from industrial waste and that you'd need at least access to both up and down mains to make it a viable project. Why they even started with it I don't know. What I also don't know is why they announced it as the site for the new depot before agreeing a price with the land owner who is now supposedly being "difficult" over the pricing, surprise.

As for the Harwich Parkstone option I think that's dead in the water due to opposition from the FOCs and the port. I think the preferred option at the minute is the old sidings next to Harwich Town, Norwich Victoria sidings and Yarmouth for storage with Crown Point/Ilford/Clacton doing the maintenance as now.

With the first of the new fleet arriving later this year, things are really looking a bit tight.

Indeed part of the problem as I understand it is simply the increased length of the fleet to be berthed overnight, (my estimates put it around 15% greater than the current, a combination of more longer vehicles), plus the fact that Clacton, Ilford, Bishops Stortford and Cambridge wont be able to accomodate as many of these longer vehicles as today means some innovative solutions will be required, especially as the crunch points are more towards the London end of the franchise area. How all of this translates into traincrew strategy when so much is so fluid is anyone guess.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

LAX54

Established Member
Joined
15 Jan 2008
Messages
3,759
Indeed part of the problem as I understand it is simply the increased length of the fleet to be berthed overnight, (my estimates put it around 15% greater than the current, a combination of more longer vehicles), plus the fact that Clacton, Ilford, Bishops Stortford and Cambridge wont be able to accomodate as many of these longer vehicles as today means some innovative solutions will be required, especially as the crunch points are more towards the London end of the franchise area. How all of this translates into traincrew strategy when so much is so fluid is anyone guess.


Has anyone thought that maybe when they announced all these new trains, they did not actually think it right through ?
 

eastdyke

Established Member
Joined
25 Jan 2010
Messages
1,923
Location
East Midlands
Has anyone thought that maybe when they announced all these new trains, they did not actually think it right through ?
By 'they' do you mean GA, DfT or both?
FWIW 'the landowner' is St. Francis Group, they acquired the site in 2007. Must have thought when GA pitched up that 2017 was going to be a good year. By virtue of the site history and location (access roads) it is far from straightforward to re-develop!
 

306024

Established Member
Joined
23 Jan 2013
Messages
3,946
Location
East Anglia
Has anyone thought that maybe when they announced all these new trains, they did not actually think it right through ?

Yes quite a few very knowledgeable people have indeed thought that. Trains the equivalent of 6 cars or 12 cars in today’s money will struggle to fit in the many sidings that are 4 or 8 cars long. Keeping the normal service running with such a huge crew training programme is another logistical challenge to be faced too.
 

eastdyke

Established Member
Joined
25 Jan 2010
Messages
1,923
Location
East Midlands
GA has put out a press realease concerning (the expected) depot upgrade works at Crown Point:
https://www.greateranglia.co.uk/abo...forming-norwich-depot-in-readiness-new-trains
The relevance to this thread is the final paragraph:
Options for other additional maintenance facilities – originally planned to be at Brantham - are still being considered.
Full release:
Work has begun to prepare Greater Anglia’s Norwich-based Crown Point Depot for the new fleet of trains that will serve the region from 2019, including sending engineers to Switzerland to learn how to look after them.

crown_point_depot_-_road_16_upper_level_artists_impression_apr2018.jpg

Greater Anglia is investing over £40 million in the project which will see the depot, which opened in 1982, transformed to accommodate the longer trains.

The large scale expansion ushers in a new era for East Anglia’s railways, with better facilities to house and maintain the 58 new trains being built by Stadler, as well as a new train washing facility, improved servicing equipment and the ability to store and dispense more fuel.

Special high walkways will be installed to give engineers access for maintenance and repairs - as most of the new trains’ components are on the roof – due to their lowered floors which make them more accessible to passengers.

New jacks will be installed to enable engineers to lift a complete train without having to split the carriages for bogie and underframe equipment removal, and new equipment transfer turntables and support offices will also be added.

In addition, the depot will gain upgraded toilet maintenance facilities, as all the new trains will have large tanks to collect waste, rather than emptying it onto the tracks.

Stadler will be responsible for maintaining their brand new regional bi-mode, Airport Express and InterCity trains at the depot, working closely with Greater Anglia to ensure that the new trains are in top condition to provide rail passengers in East Anglia with punctual and reliable services.

The landmark project means that train maintenance expertise and the jobs involved in looking after the state-of-the-art new trains stay in Norwich and continue the city’s long-standing crucial role in the delivery of the region’s train service.

That presence is valuable to the local and regional economy, with benefits for Norwich and Norfolk both from having employees based at the depot and from the linked supply chain.

Around 70 Greater Anglia staff will transfer to Stadler, 12 of whom will be seconded as Systems Technicians and will each spend six months with Stadler in The Netherlands, Switzerland, Poland and/ or Spain learning how to look after the new train systems.

Mike Kean, Greater Anglia’s Franchise & Programmes Director, said: “The investment in Crown Point depot is great news for Norwich and Norfolk. We’re committed to the region we serve and playing our part in supporting its development, so we’re very pleased to be able to create a new centre of excellence for train maintenance in East Anglia, in partnership with Stadler.

“The coming months will be an exciting and busy period as we implement the major project to prepare the depot for the new trains. At the same time, the team continue to work hard maintaining and repairing our existing trains to ensure that customers still receive a reliable and punctual service while Stadler are building our brand-new train fleet.”

crown_point_depot_artists_impression_apr2018_1.jpg

To provide additional space and reduce pressure on Crown Point depot while the work is being carried out, Greater Anglia has leased an additional depot at Colchester from Balfour Beatty.

Hein van der Schoot, Managing Director of Stadler Rail Service UK, commented: "The major upgrade of the current facility, ahead of the introduction of the new fleet, will mean that the Stadler trains are serviced and maintained at the highest level to ensure optimum performance. The construction work represents a critical milestone within the project, and we look forward to continued close working with Greater Anglia throughout this vital stage in the process and beyond."

The work will be carried out by Taylor Woodrow, the civil engineering division of VINCI Construction UK.

Options for other additional maintenance facilities – originally planned to be at Brantham - are still being considered.
 

LAX54

Established Member
Joined
15 Jan 2008
Messages
3,759
The BB depot at Colchester is 'cut-off' for quite a few hours of the day with freight traffic recessed on the DGL for some hours :)
 

LAX54

Established Member
Joined
15 Jan 2008
Messages
3,759
At least the water there is, in the main, from the sky :D
May also go someway to explain why they moved their offices "The Hub" to that particular location, right next door to the Balfour's depot :)
 

scott118

Member
Joined
24 Feb 2015
Messages
927
Location
East Anglia
BB has now closed that depot. GA have had their surveyors in taking a look round.

Cambridge are busy installing additional roads, between the wash road and platform 8.
 

LAX54

Established Member
Joined
15 Jan 2008
Messages
3,759
Think GB also looked at it for some of their locos, and for fueling
 