Minstral25
Established Member
It is being built, I don't see how you're going to stop it..
Now who'd being negative!
Now that would be short sighted, deliberately making one platform unable to take a 12 car..
Why a 12-car train will never use it? Unless there is a new Three Bridges to Redhill 12-car service being gestated?
I agree acceessing it conflicts with a northbound departure from #0. Ideally you need a parallel connection from the down Redhill so those moves can take place simultaneously, and better overlap arrangements at the south end to reduce conflict. That said greater use of #2 for down services is probably not required currently whilst the south junction still retains the long crossover to the Reigate line from #3. All southbounds can normally continue to use that. In the longer term I think NR wish to remove that long crossover with its multiple diamonds. Then improvements to southbound access to #2 would be essential as all Reigate trains would have to use that plattform.
I'm guessing you don't use Redhill but the long queue of trains in the evening peak waiting to access Platform 3 is not something you have experience. If you are in the last train you can often be 20 or 30 minutes late into Redhill just for waiting to access Platform 3
I know nothing of the proposed platform facilities, but if as you suggest this will become the busiest platform accomodating the most lucrative customers waiting in the morning peak it would be very shortsighted to skimp on the facilities. If there are so many customers, I'm sure a refreshment facility will be able to survive there. .
Yes it would be short sighted but that was the plan
That would save money indeed, but I think NRs eyes are on the further developments possible when the south junction track and the signalling in the area next come up for renewal. These would incorporate removal of the long crossover from #3 to the Reigate line and additional parallel connections from #0 and #1 towards Brighton. That final aspiration favours Up trains running around the outside of the layout through #0 with reversers and Reigate down trains accomodated 'in the middle' on #1 and #2. There is a sketch of these ideas published in the NR Sussex Area Route Study (page 164) - https://www.networkrail.co.uk/Sussex-Area-Route-Study-FINAL.pdf
I have also attached a screenshot of the page.
Note also that this shows #1 as a through platform. It is possible that the bay status is only a temporary feature forced by the limitations of the existing signalling; the cost, difficulty, risk and resource wastage of making very significant modiifications to the existing control systems that have only a fairly limited remaining life. In my opinion making #1 a bay (at least temporarily) has probably avoided some very significant engineering challenges.
This plan shows what was planned after the platform 0 rebuild. The crossover from the Southbound main line to platform 2 does not exist currently but was part of the original Platform 0 plan (currently that crossover is about a mile North of Redhill) that included rebuilding the Northern station throat.
If they don't do it then flexibility is lost and the capacity problems at Redhill will not be improved.
Redhill is so congested it needs solving now, platform 0 in its original form was a compromise but would have helped. This plan just creates more serious problems and loses some of the flexibility of the current situation.