On Saturday, there's a Stafford -Stoke replacement bus. Does anyone have an idea what the engineering work is for ?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Mcr Warrior

Veteran Member
Joined
8 Jan 2009
Messages
14,192
On Saturday, there's a Stafford -Stoke replacement bus. Does anyone have an idea what the engineering work is for ?
Looks primarily like ballast replacement work in the area.

More info here...


Extract(s)...
Starting on Saturday 10 August and taking place each weekend for the next four weeks engineers will be completing £2.5m of essential improvement work through Stoke-on-Trent.
Work will include:

Replacing 3720 tonnes of ballast (the stones on the railway that keep the track in place)

Upgrading 32 bearers, which help the track switches and crossings to stay in place
 