• Our booking engine at tickets.railforums.co.uk (powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

ScotRail HST Introduction - Updates & Discussion

Status
Not open for further replies.

Steven_G

Member
Joined
5 Mar 2018
Messages
140
There is a lot of sense about 2 sets a month from January.

Remember Kilmarnock have started work. One set from each coach works per month makes sense.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Cashew

Member
Joined
22 Mar 2019
Messages
32
There is a lot of sense about 2 sets a month from January.

Remember Kilmarnock have started work. One set from each coach works per month makes sense.
Remember set number 8 hasn't left Doncaster yet and we don't know if number 9 has been started or when delivery is expected. and we do not know what progress Kilmarnock have made if any, as they will be novices when it comes to fitting the sliding doors.
 

Killingworth

Established Member
Joined
30 May 2018
Messages
4,871
Location
Sheffield
Remember set number 8 hasn't left Doncaster yet and we don't know if number 9 has been started or when delivery is expected. and we do not know what progress Kilmarnock have made if any, as they will be novices when it comes to fitting the sliding doors.

Remember XC sets are twice as long. 2 more of them to emerge yet. With them out of the way by late January (?) getting out shorter sets should speed up.
 

Northhighland

Member
Joined
19 Aug 2016
Messages
606
I think everyone involved would be better not putting dates out there only to miss them. Wabtec don't seem to have predictability yet over the time period so until they do I would suggest they avoid promising what they cannot deliver.
 

Cashew

Member
Joined
22 Mar 2019
Messages
32
Remember XC sets are twice as long. 2 more of them to emerge yet. With them out of the way by late January (?) getting out shorter sets should speed up.
There are still a number of GWR "Castle" sets to be delt with, and I think the number is 4 or 5.
 

InvHst

Member
Joined
9 Dec 2018
Messages
268
.... and it's been cancelled.

Been reported this morning from rail magazine head of media that the move was cancelled as scotrail won't be taking any until the issues are resolved with them plan to have 12 by end of year apparently
 

385001

Member
Joined
27 Nov 2017
Messages
211
Location
Edinburgh

.... and it's been cancelled.

Cancelled as ScotRail won't take it until they are right and all snags sorted according to this tweet.
https://twitter.com/Clinnick1/status/1181486533326643200

Richard Clinnick said:
Planned delivery of the 8th @ScotRail IC7 HST today has been cancelled. The operator won't take them until they are right and all snags sorted. Plan is to have around 12 in traffic by end of year.

Also interesting about plan for 12 units in traffic by the end of the year. Would mean another 4 in addition the on hold 8th set being delivered in the next couple of months which would be a much faster rate than previous.

EDIT: @InvHst best me to it.

Been reported this morning from rail magazine head of media that the move was cancelled as scotrail won't be taking any until the issues are resolved with them plan to have 12 by end of year apparently
 

JohnR

Member
Joined
23 Jul 2010
Messages
492
Has Kilmarnock started work on them yet? Feels like that was announced ages ago.

12 by December 2019 feels both ambitious (given current build rate) and pathetic (given original plans)
 

InOban

Established Member
Joined
12 Mar 2017
Messages
4,216
Cancelled as ScotRail won't take it until they are right and all snags sorted according to this tweet.
https://twitter.com/Clinnick1/status/1181486533326643200



Also interesting about plan for 12 units in traffic by the end of the year. Would mean another 4 in addition the on hold 8th set being delivered in the next couple of months which would be a much faster rate than previous.

EDIT: @InvHst best me to it.
Without any inside knowledge I suggested that a few pages ago. There's no reason why Abellio should be paying lease charges to Angel trains for sets which are not reliably fit for use.
 

Bassman

Member
Joined
14 Dec 2018
Messages
79
Without any inside knowledge I suggested that a few pages ago. There's no reason why Abellio should be paying lease charges to Angel trains for sets which are not reliably fit for use.
In my opinion ,if this true , has been a long time coming! Goods delivered should be fit for purpose.. for passengers, for train companies, and for leasing companies.
 

Bassman

Member
Joined
14 Dec 2018
Messages
79
also for railway employees who have to use equipment which is less than reliable!
 

43096

On Moderation
Joined
23 Nov 2015
Messages
15,268
Without any inside knowledge I suggested that a few pages ago. There's no reason why Abellio should be paying lease charges to Angel trains for sets which are not reliably fit for use.
Or is this at least in part ScotRail bluster and having to be seen to be being tough on the supplier even though a substantial part of the reason is ScotRail’s own engineering incompetence.
 

DannyMich2018

Member
Joined
19 Dec 2018
Messages
734
Or is this at least in part ScotRail bluster and having to be seen to be being tough on the supplier even though a substantial part of the reason is ScotRail’s own engineering incompetence.
Possibly. We all know Wabtec is not blameless but XC and GWR's refurbs seem to be working okay and are not in bits and EMR and LNER's sets seem to still give good service for their age so why oh why is the Scotrail HST situation a mess?
 

380101

Member
Joined
18 Feb 2015
Messages
1,001
Has Kilmarnock started work on them yet? Feels like that was announced ages ago.

12 by December 2019 feels both ambitious (given current build rate) and pathetic (given original plans)

First set has been at Wabtec Kilmarnock since the end of June and the coaches are currently going through the paint shop and final fit out. There is also a complete set with power cars across the way in Brodies getting an exam carried out before going into service.
 

InOban

Established Member
Joined
12 Mar 2017
Messages
4,216
A properly refurbished unit shouldn't require anything more than fuel and water for months. After all they've been stripped back to bare metal.
 

Northhighland

Member
Joined
19 Aug 2016
Messages
606
First set has been at Wabtec Kilmarnock since the end of June and the coaches are currently going through the paint shop and final fit out. There is also a complete set with power cars across the way in Brodies getting an exam carried out before going into service.

So are you saying Kilmarnock have one set complete and one nearly complete?
 

380101

Member
Joined
18 Feb 2015
Messages
1,001
So are you saying Kilmarnock have one set complete and one nearly complete?

The complete set in Brodies has not been done in Wabtec Kilmarnock. I think it must be most recent set delivered up from Doncaster, but not 100% sure.

I've only seen the one set of coaches in Wabtec Killie whilst driving past the yard.
 

Northhighland

Member
Joined
19 Aug 2016
Messages
606
So Killmarnock are taking 12-16 weeks for a set and have only one in production? That isn’t going to help as much as hoped.
 

380101

Member
Joined
18 Feb 2015
Messages
1,001
So Killmarnock are taking 12-16 weeks for a set and have only one in production? That isn’t going to help as much as hoped.

I imagine they've taken longer with their first set due to the staff having to learn how to do the door conversion. Wabtec Killie basically went straight from the 321 to 320 conversions to the HST job, so probably couldn't spare the staff to send to Doncaster to train before hand. Hopefully once they get the first set out the way things will speed up.
 

Highland37

Established Member
Joined
29 Jun 2012
Messages
1,259
Longer? They've taken 3 months! All the evidence available shows that hoping Wabtec will speed up is not a realistic expectation.
 

FOH

Member
Joined
17 Oct 2013
Messages
712
I imagine they've taken longer with their first set due to the staff having to learn how to do the door conversion. Wabtec Killie basically went straight from the 321 to 320 conversions to the HST job, so probably couldn't spare the staff to send to Doncaster to train before hand. Hopefully once they get the first set out the way things will speed up.
I'm sure I read somewhere they aren't doing the doors, just all the normal mkIII refurb work and then they'll to Doncaster just for doors and nothing else
 

Caleb2010

Member
Joined
25 Nov 2015
Messages
355
Location
Dufftown
Currently on the 12.48 INV-EDB, set HA32, according to the coach letters its formed A,C,B,D. Still at least the booked seat exists today!
 

Bodiddly

Member
Joined
7 Feb 2013
Messages
648
I notice a lot of comments here that are very naive about how the railway works and especially trains getting refurbished. When a train enters the works, it is assessed on not just the work planned but also the basics i.e, how structurally sound it is, levels of corrosion needed dealt with, roof condition, bodywork, major exam date and whether it ties in with the work being carried out. These are 40 year old coaches with high levels of corrosion, especially around the toilet areas. Years and years of effluent, spraying up onto the undercarriage has taken its toll on the subframe. Completed sets are coming out of the works and straight into Scotrail sheds for C4 exams, due to the expired maintenance schedule.
Scotrail inherited some cantankerous beasts in these trains and it will take time to get them completed and in place but who can argue whether you would rather travel from the Central belt to the Highlands on a IC7 or a 170?
 
Status
Not open for further replies.

Top