Evening all,
I hope that this post finds you and yours coping as well as possible given the times we are in.
I am currently working on a SimSig timetable for the Three Bridges ASC area: it is built around the real-life scenario of a large engineering block which closes the fast lines throughout about 50% of the area covered by the simulation. This, of course, means various service alterations, not least on the branch routes from Purley through to Caterham / Tattenham Corner and I need some advice on the traction settings here.
The Caterham / Tattenham services are, on the day in question, all operating between Caterham / Tattenham Corner and Purley only due to the reduction in line capacity caused by the engineering works. After looking up the traction settings on a SimSig timetable compiled by somebody else I have done all the Tattenham Corner - Purley trains and set their traction as SN (Southern) 5-car Class 377. However the same timetable has all the Caterham services - headcode 2Jxx - as 8-car Class 455. The Caterham trains in this TT - all 2Cxx - are, of course, only going Caterham - Purley. Would Southern use 8-car Class 455 regardless or would they run them half-length (ie. 4-car)? I believe the scenario I am working around has happened a couple of times recently so I am wondering if anyone has ideas: TBH I would be surprised if 8/455 formations were used on such short workings, especially on a Sunday. As an aside the first service inbound to Caterham starts from East Croydon, prior to which it works ECS from Selhurst Depot.
The date I am working around, for anyone wondering, is that of Sunday 22nd November: Purley on that date looks like this:
www.realtimetrains.co.uk
Cheers,
Dave
I hope that this post finds you and yours coping as well as possible given the times we are in.
I am currently working on a SimSig timetable for the Three Bridges ASC area: it is built around the real-life scenario of a large engineering block which closes the fast lines throughout about 50% of the area covered by the simulation. This, of course, means various service alterations, not least on the branch routes from Purley through to Caterham / Tattenham Corner and I need some advice on the traction settings here.
The Caterham / Tattenham services are, on the day in question, all operating between Caterham / Tattenham Corner and Purley only due to the reduction in line capacity caused by the engineering works. After looking up the traction settings on a SimSig timetable compiled by somebody else I have done all the Tattenham Corner - Purley trains and set their traction as SN (Southern) 5-car Class 377. However the same timetable has all the Caterham services - headcode 2Jxx - as 8-car Class 455. The Caterham trains in this TT - all 2Cxx - are, of course, only going Caterham - Purley. Would Southern use 8-car Class 455 regardless or would they run them half-length (ie. 4-car)? I believe the scenario I am working around has happened a couple of times recently so I am wondering if anyone has ideas: TBH I would be surprised if 8/455 formations were used on such short workings, especially on a Sunday. As an aside the first service inbound to Caterham starts from East Croydon, prior to which it works ECS from Selhurst Depot.
The date I am working around, for anyone wondering, is that of Sunday 22nd November: Purley on that date looks like this:
Realtime Trains | Departures from Purley all day on 22/11/2020
Train information at Purley all day on 22/11/2020. From Realtime Trains, an independent source of train running info for Great Britain.

Cheers,
Dave