I assume you mean Atherstone!Not only did this give stations like Tamworth, Lichfield and Atherton a regular 1 TPH service to Euston for the first time ever
I assume you mean Atherstone!Not only did this give stations like Tamworth, Lichfield and Atherton a regular 1 TPH service to Euston for the first time ever
Given that freight pays an access charge per km of train run how was that ever expected or given?Then there were some huge arguments with ORR and the freight guys. The former, quite reasonably, wanted to ensure that existing access rights (ie existing train paths) were not disadvantaged. (Of course in BR days this would not have been done). The freight guys wanted more extra capacity for free.
Given that freight pays an access charge per km of train run how was that ever expected or given?
Yes, it's very beneficial for the Liverpool-Wigan local service.
Warrington-Wigan-Balshaw Lane is still a messy railway though, with the slow lines switching sides repeatedly.
Maybe it's a good job the promised freight volumes have not happened.
Meanwhile the signalling north of Weaver Jn is now 45 years old and will have to be replaced soon, hopefully with some of these layout issues resolved.
Ansaldo has also become Hitachi of course, and is a key player in NR's ERTMS roll-out.
I had the misfortune to suffer from the complete closure of Crewe - Wilmsow - Cheadle Hulme from Dec 2005 to Jun 2006 - the blockade was originally intended to be for 12 weeks but difficulties with the Ansaldo signalling meant re-opening was repeatedly postponed. The 'express' bus to Crewe from Wilmslow took over a hour (17 minutes by fast train) because of the indirect nature of the roads and traffic congestion in Wilmslow/ Alderley Edge. The 'stopping' bus was even worse with long detours to serve the intermediate stations. Wilmslow itself retained a hourly train service to Manchester via the Styal line, operating on the 'one -engine-in-steam' principle from the Airport - Wilmslow SB having been demolished with indecent haste right at the start! Passenger numbers took several years to recover from that fiasco as punters became used to other modes. As has been mentioned, resignalling of Stockport itself was also abandoned, so even today Pendolinos are 'belled' through Edgeley in the traditional manner.
However I know the 140mph running wasn't possible due to infrastructure limits ie it needed in cab signalling however wasn't it later stated that Virgin could run up to 135mph without needing in cab signalling?
Going over 125MPH requires in-cab signaling. That was where the speed upgrade was going to come from.
Questionably yes ...but no major time savings in doing so , for many reasons.
I don't know the reasons but whatever they were, it's unlikely I think that we will ever see above 125mph on the WCML in my lifetime.
140mph would have banned what is now LNR from the fast lines. I'm not unconvinced that the present 110/125mph split hasn't actually turned out better overall.
Really not worth it -as HS2 will deliver more.I mean that sincerely.
No AT is part of a general power supply upgrade , the ole works on WCRM was final removal of what remained of compound catenary and of worn ole wire renewal
Have you counted the negatives in that?140mph would have banned what is now LNR from the fast lines. I'm not unconvinced that the present 110/125mph split hasn't actually turned out better overall.
What I recall is them subsequently being told that cab signalling was required for anything greater than 125 mph. Which is completely different to not being required below 140 mph...However I know the 140mph running wasn't possible due to infrastructure limits ie it needed in cab signalling however wasn't it later stated that Virgin could run up to 135mph without needing in cab signalling?
What I recall is them subsequently being told that cab signalling was required for anything greater than 125 mph. Which is completely different to not being required below 140 mph...
a completely rebuilt Watford with extra fast line platforms (horrendously expensive and lots of land take)
However I know the 140mph running wasn't possible due to infrastructure limits ie it needed in cab signalling however wasn't it later stated that Virgin could run up to 135mph without needing in cab signalling?
Which was the original thought however it was discovered that they could operate the 390s at speeds of up to 135mph using the existing signalling ie not cab signalling however for various reasons they didn't go though with it.
Indeed in 2013 Virgin Trains own Chris Gibb announced that they were looking at upgrading part of the WCML near Lockerbie see here for a article from Rail Technology Magazine.
It's also stated here that Virgin Trains were calling for 135mph running in 2013 in order to make the best use of the capacity of the WCML and to better compete with the airlines.
Which I believe is more then enough to state my case...
Thank you for such an informative post! Watford has a special place in my heart, so I'm naturally fascinated by the tidbit quoted above.
As it never made it into the project proper I doubt there will be much if any detail on it, but I've considered additional platforms several times over and the sticking point has always been the length of loop required off the fast lines to make them viable/worthwhile. When you mention land take as an obstacle, is that just the platforms themselves, or is that also because you would probably have to widen the entire embankment southwards, not to mention potentially widening the Bushey Arches viaduct (and possibly taking a chunk out of Bushey station), depending on the speed profile desired. Let alone heading north where the Watford tunnels come into play...
* a few other bits and pieces.
It did - that was my idea ! , handily placed for future electrification , which also was "influenced" by myself.
And me, when that was our work package ... swapped Ditton (so you got the glory).
I remember Virgin touting 135mph and other improvements to cut down Glasgow times; do we think any of those are still going ahead?
I assume you mean Atherstone!
The Trent Valley semi-fasts were (and are) a great success - it was born from the ashes of a very resource led single unit which did random movements as the bare minimum that was contractualized in 1996 for Central Trains. The long period of withdrawal was painful , but in the medium - long term very worthwhile.
The cross Nuneaton serices in the Leicester direction were another "overlooked" service in PUG2 (unsurprising perhaps when Silverlink could have been forced off the fast lines entirely !) * - so the options of grade seperation at NN for the hourly 2 car DMU were painfully looked at by the RT /NR ream and deemed "not value for money" as the cross passenger flows ranged from a handful of people to about 30 per train. ...