• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

HS2 delayed again?

absolutelymilk

Established Member
Joined
18 Jul 2015
Messages
1,406
If fellow posters had made there own enquiries they would have discovered that the issue is not about the new drainage structure which the local Wendover community have accepted but it is all about the vast number of lorries passing through the town to complete the works which frankly HS2 do not care about.Bucks C C have refused planning permission until this issue can be resolved and the local Wendover HS2 group have submitted alternative and sensible proposals which I understand are now being considered.
How many lorries will pass through the town per day?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

bobjarred05

Member
Joined
21 Apr 2025
Messages
6
Location
cambridge
For those who cant see the article, some key parts

The cost of finishing HS2 between Birmingham Curzon Street and Old Oak Common has soared to £81 billion (at 2019 prices). And the work will not be completed until 2036 at the earliest, with 2039 more likely.

That’s the information presented to ministers in a report from HS2 Ltd Chief Executive Mark Wild, as part of his preliminary assessment of the scheme.
 

HSTEd

Veteran Member
Joined
14 Jul 2011
Messages
18,725
I guess HS1 had one council for the most part (Kent CC? Though I don't know if lower tier councils had a say?) which was also getting a lot of benefit from the scheme (new HS stations and the classic compatible service).

Buckinghamshire on the other hand gets not much apart from a lot of disruption.

There should be no need to get LA approval for anything that parliament has approved directly. Minor modifications included in that.
The design approach for HS1 was very different from HS2 though, from the beginning. Even leaving aside the benefits that the people being disrupted received from the scheme.

I don't think trying to give schemes the ability to sign themselves off for "minor modifications" without resort to further authority would be a good idea.

Such a power would be ripe for abuse.
 

stuu

Established Member
Joined
2 Sep 2011
Messages
3,480
If fellow posters had made there own enquiries they would have discovered that the issue is not about the new drainage structure which the local Wendover community have accepted but it is all about the vast number of lorries passing through the town to complete the works which frankly HS2 do not care about.Bucks C C have refused planning permission until this issue can be resolved and the local Wendover HS2 group have submitted alternative and sensible proposals which I understand are now being considered.
Vast = 1 per day
 

mike57

Established Member
Joined
13 Mar 2015
Messages
2,010
Location
East coast of Yorkshire
The design approach for HS1 was very different from HS2 though, from the beginning. Even leaving aside the benefits that the people being disrupted received from the scheme.
If the answer is to compensate those negatively affected during the works how much would this cost v delay and continual to and fro with the local authority
I don't think trying to give schemes the ability to sign themselves off for "minor modifications" without resort to further authority would be a good idea.
I think a balance need to be struck, looking in from outside I see a local authority opposed to the whole scheme, who are making it as difficult as possible. I dont know if this is individual people, or a more organised opposition, but if a scheme such as this is deemed to be in the national interest then there has to be a way of avoiding these sort of issues, otherwise costs just spiral have spiralled

The cost of finishing HS2 between Birmingham Curzon Street and Old Oak Common has soared to £81 billion (at 2019 prices).
To be honest this seems eyewatering and barely sustainable. I know it been gone over before but at 2025 prices thats well over £100bn. There will not be any more High Speed rail built in the UK with costs approaching 1bn per mile. I know there are things other than the actual route to consider when talking about cost, but this doesn't even get you into Euston. I bet Mr Starmer wishes Mr Sunak had cancelled the whole thing when he entered No10 in October 2022. I know it was under way then and would have been a hard decision, but how much has been spent since then, and how much more will have to be spent before trains run from Euston to Birmingham?
 

HSTEd

Veteran Member
Joined
14 Jul 2011
Messages
18,725
If the answer is to compensate those negatively affected during the works how much would this cost v delay and continual to and fro with the local authority
Probably not that much money (either that or infinite money!), but I don't think that is necessarily the most effective option.
The most effective option would probably be to design schemes that benefit the people being disrupted as an integral part of their design, as HS1 did and many road schemes do.

If you promise compensation to people, you run the risk that the cynical streak prevalent in the population today will assume the government will wriggle out of the compensation once they have what they want.

I think a balance need to be struck, looking in from outside I see a local authority opposed to the whole scheme, who are making it as difficult as possible. I dont know if this is individual people, or a more organised opposition, but if a scheme such as this is deemed to be in the national interest then there has to be a way of avoiding these sort of issues, otherwise costs just spiral have spiralled
I know it is a popular trope that it is the fault of the opposition that the costs on this scheme have spiralled out of control, but I'm not sure how accurate that is.

There has been plenty of cost growth that can't be directly traced to the demands of 'NIMBYs' after all.
 

styles

Member
Joined
7 Dec 2014
Messages
690
Location
Midlothian
Probably not that much money (either that or infinite money!), but I don't think that is necessarily the most effective option.
The most effective option would probably be to design schemes that benefit the people being disrupted as an integral part of their design, as HS1 did and many road schemes do.

If you promise compensation to people, you run the risk that the cynical streak prevalent in the population today will assume the government will wriggle out of the compensation once they have what they want.


I know it is a popular trope that it is the fault of the opposition that the costs on this scheme have spiralled out of control, but I'm not sure how accurate that is.

There has been plenty of cost growth that can't be directly traced to the demands of 'NIMBYs' after all.
The inquiries and reports seem to suggest the bulk of the increases are due to overoptimistic cost estimates, low contingency, inflation - particularly the increase in cost of steel and concrete, scope creep (e.g. the extension on the tunnel through the Chilterns), and worse ground conditions than anticipated.

Some of this should've been managed better, some of it is more difficult to manage.

The scale of the cost changes while simultaneously scaling the project back so significantly, is pretty grim though. At one point the boss of HS2 Ltd suggested it could cost £110bn - triple what Gordon Brown originally estimated and nowhere near the same scale of delivery. At that point it wouldn't even deliver a return on investment.
 

absolutelymilk

Established Member
Joined
18 Jul 2015
Messages
1,406
For those who cant see the article, some key parts

The cost of finishing HS2 between Birmingham Curzon Street and Old Oak Common has soared to £81 billion (at 2019 prices). And the work will not be completed until 2036 at the earliest, with 2039 more likely.

That’s the information presented to ministers in a report from HS2 Ltd Chief Executive Mark Wild, as part of his preliminary assessment of the scheme.
Is the 2036 date for Birmingham to OOC or Birmingham to Euston?
 

FMerrymon

Member
Joined
11 Dec 2024
Messages
122
Location
Reading
The inquiries and reports seem to suggest the bulk of the increases are due to overoptimistic cost estimates, low contingency, inflation - particularly the increase in cost of steel and concrete, scope creep (e.g. the extension on the tunnel through the Chilterns), and worse ground conditions than anticipated.

Some of this should've been managed better, some of it is more difficult to manage.

The scale of the cost changes while simultaneously scaling the project back so significantly, is pretty grim though. At one point the boss of HS2 Ltd suggested it could cost £110bn - triple what Gordon Brown originally estimated and nowhere near the same scale of delivery. At that point it wouldn't even deliver a return on investment.

Not triple. The original estimates were in 2009 prices. Adjusting to current prices would be a 65-70% increase.
 

Grimsby town

Member
Joined
4 Apr 2011
Messages
664
Is the 2036 date for Birmingham to OOC or Birmingham to Euston?
The article says that this OOC to Birmingham. I wonder if wires are being crossed somewhere. Given the progress on construction, it does seem somewhat unbelievable that it's still 11 years from opening.
 

styles

Member
Joined
7 Dec 2014
Messages
690
Location
Midlothian
Not triple. The original estimates were in 2009 prices. Adjusting to current prices would be a 65-70% increase.
Fair point on inflation.

£37.5bn Brown estimated in 2009 would be £59bn today.

So an 86% increase, nearly double still, despite massively scaling back.
 

mrmartin

Member
Joined
17 Dec 2012
Messages
1,194
The inquiries and reports seem to suggest the bulk of the increases are due to overoptimistic cost estimates, low contingency, inflation - particularly the increase in cost of steel and concrete, scope creep (e.g. the extension on the tunnel through the Chilterns), and worse ground conditions than anticipated.

Some of this should've been managed better, some of it is more difficult to manage.

The scale of the cost changes while simultaneously scaling the project back so significantly, is pretty grim though. At one point the boss of HS2 Ltd suggested it could cost £110bn - triple what Gordon Brown originally estimated and nowhere near the same scale of delivery. At that point it wouldn't even deliver a return on investment.
But I would say they are interlinked. If you're having to build a lot more viaducts and/or tunnels because of NIMBY pressure then you may 10x your concrete and steel needs. Much like gold plating it for 400km/h operation did. Similar with ground conditions - slab track is required over 300km/h from what I know, and slab track has absolutely no tolerance for poor(er) ground conditions.
 

mike57

Established Member
Joined
13 Mar 2015
Messages
2,010
Location
East coast of Yorkshire
So an 86% increase, nearly double still, despite massively scaling back.
And even the rump thats left of the original project (what did the 2009 £59bn scope cover?, reaching Manchester?, Leeds? Euston?) isn't finished yet and will probably go further over budget.
 

FrontSideBus

Member
Joined
11 Feb 2025
Messages
95
Location
Merseyside
£100bn to get to Birmingham... How much would it have cost to upgrade the infrastructure on the ECML and WCML to facilitate 150+ Mph?
 

FMerrymon

Member
Joined
11 Dec 2024
Messages
122
Location
Reading
Fair point on inflation.

£37.5bn Brown estimated in 2009 would be £59bn today.

So an 86% increase, nearly double still, despite massively scaling back.

To be pedantic, that estimate is from 2011 and under the coalition govt. Original budget for phase 1 was set at £30bn if calculated in 2019 prices, in 2013.

Similar with ground conditions - slab track is required over 300km/h from what I know, and slab track has absolutely no tolerance for poor(er) ground conditions

Slab track required for 18 trains an hour at high speed. 11 trains per hour would not require it even at 225mph, as per Prof Andrew McNaughton.

== Doublepost prevention - post automatically merged: ==

The article says that this OOC to Birmingham. I wonder if wires are being crossed somewhere. Given the progress on construction, it does seem somewhat unbelievable that it's still 11 years from opening.

Yeah, does seem a little bizarre that. The original expectation was entire phase 1 to complete in 9 years, so given how much has been done, another 11 years seems a bit much.

== Doublepost prevention - post automatically merged: ==

£100bn to get to Birmingham... How much would it have cost to upgrade the infrastructure on the ECML and WCML to facilitate 150+ Mph?

The question should be how much to add another pair of tracks to facilitate extra capacity
 

jfowkes

Member
Joined
20 Jul 2017
Messages
1,134
£100bn to get to Birmingham... How much would it have cost to upgrade the infrastructure on the ECML and WCML to facilitate 150+ Mph?
No point upgrading for higher speeds if you just end up stuck behind a stopper that's only doing 100mph.

The southern end of the WCML doesn't need speed it needs capacity.
 

styles

Member
Joined
7 Dec 2014
Messages
690
Location
Midlothian
To be pedantic, that estimate is from 2011 and under the coalition govt. Original budget for phase 1 was set at £30bn if calculated in 2019 prices, in 2013.
It's not - it's the Brown government's estimate, in 2009 prices: https://commonslibrary.parliament.uk/research-briefings/cdp-2021-0168/

Official estimates of the costs of HS2 have increased from an initial estimate of £37.5bn (in 2009 prices) to a range of £72bn to £98bn.
Note that I am giving the original HS2 estimate, not the phase 1 estimate.
 

FMerrymon

Member
Joined
11 Dec 2024
Messages
122
Location
Reading
Just seen this latest report is from Wolmar, so I'll wait for official confirmation.
 
Last edited:

FMerrymon

Member
Joined
11 Dec 2024
Messages
122
Location
Reading
It's not - it's the Brown government's estimate, in 2009 prices: https://commonslibrary.parliament.uk/research-briefings/cdp-2021-0168/


Note that I am giving the original HS2 estimate, not the phase 1 estimate.


No, 2009 is the base year, the estimate is from 2011. Its from this paper https://web.archive.org/web/2011081...eedrail.dft.gov.uk/files/hsr-consultation.pdf

Its not the original estimate either, which was 30bn in q3 2009 prices in the march 2010 white paper, though that excluded rolling stock

The 72-98bn quoted in that article is in q3 2019 prices (and a big mistake not including the base year there).
 

mike57

Established Member
Joined
13 Mar 2015
Messages
2,010
Location
East coast of Yorkshire
Slab track required for 18 trains an hour at high speed. 11 trains per hour would not require it even at 225mph, as per Prof Andrew McNaughton.
A question, I understand what slab track is, but how does the trains per hour affect the need for it, is it a 'wear rate' or is something else going on?
 

stuu

Established Member
Joined
2 Sep 2011
Messages
3,480
But I would say they are interlinked. If you're having to build a lot more viaducts and/or tunnels because of NIMBY pressure then you may 10x your concrete and steel needs. Much like gold plating it for 400km/h operation did. Similar with ground conditions - slab track is required over 300km/h from what I know, and slab track has absolutely no tolerance for poor(er) ground conditions.
The 400 km/h design speed means embankments need to be stronger as well, that would definitely have had an impact on costs. The slab track contract is worth £250m or something, it's basically a rounding error on the cost, especially now
 

HSTEd

Veteran Member
Joined
14 Jul 2011
Messages
18,725
The question should be how much to add another pair of tracks to facilitate extra capacity
Extra capacity to where though?

The original scheme had to take over virtually all north south traffic to justify one pair of tracks!
The railway doesn't even go near any intermediate population centres, so I can't see much point to adding more capacity to a route that is unlikely to be full for a very long time.
 

mrmartin

Member
Joined
17 Dec 2012
Messages
1,194
The 400 km/h design speed means embankments need to be stronger as well, that would definitely have had an impact on costs. The slab track contract is worth £250m or something, it's basically a rounding error on the cost, especially now
From what I read the tolerances of ground conditions for slab track are much tighter than traditional ballast. But I am not a civil engineer. What I was trying to mean was if the tolerances are tighter on slab concrete - you have to do a lot more reinforcement BEFORE the concrete contractor comes in that otherwise needed?
 

FMerrymon

Member
Joined
11 Dec 2024
Messages
122
Location
Reading
Extra capacity to where though?

The original scheme had to take over virtually all north south traffic to justify one pair of tracks!
The railway doesn't even go near any intermediate population centres, so I can't see much point to adding more capacity to a route that is unlikely to be full for a very long time.

Are you suggesting the wcml is not full and doesn't have potential for further growth? Speeding up the existing lines doesn't address the situation hs2 was designed to address and would in fact make it worse.

Hs2 doesn't need to go near intermediate population centres to substantially benefit them. Its the primary reason hs2 is being built.
 

HSTEd

Veteran Member
Joined
14 Jul 2011
Messages
18,725
Are you suggesting the wcml is not full and doesn't have potential for further growth? Speeding up the existing lines doesn't address the situation hs2 was designed to address and would in fact make it worse.
The two tracks of HS2 will easily empty WCML of any traffic that does not involve the intermediate stations.
This transferred traffic has no chance of filling 18 400m GC gauge trains per hour, at least not for a very very long time

Building extra HS2 tracks won't remove any more trains from the WCML, because all the trains that can be removed will have been.
Hs2 doesn't need to go near intermediate population centres to substantially benefit them. Its the primary reason hs2 is being built.
Having a three quarters empty four track HS2 provides no additional benefits over a half empty two track HS2.

If you wanted HS2 to be full or to try to justify more tracks HS2 would have to directly assume more of the WCML traffic, which it can't do because it doesn't go near any of the intermediate traffic generators.
 
Last edited:

irish_rail

On Moderation
Joined
30 Oct 2013
Messages
4,300
Location
Plymouth
Are you suggesting the wcml is not full and doesn't have potential for further growth? Speeding up the existing lines doesn't address the situation hs2 was designed to address and would in fact make it worse.

Hs2 doesn't need to go near intermediate population centres to substantially benefit them. Its the primary reason hs2 is being built.
When the majority of WCML trains are not full length (ie 11 car pendolino or 12 car 350s) then I'd say there is a good argument that the WCML is not as full as was previously suggested.
 

stuu

Established Member
Joined
2 Sep 2011
Messages
3,480
From what I read the tolerances of ground conditions for slab track are much tighter than traditional ballast. But I am not a civil engineer. What I was trying to mean was if the tolerances are tighter on slab concrete - you have to do a lot more reinforcement BEFORE the concrete contractor comes in that otherwise needed?
The tolerances of high speed rail are already much tighter so there can't be a lot in it. It's also not traditional slab track laid by a paving machine, it's modular segments not unlike a Hornby train set, so presumably a bit more scope for fine-tuning
 

Top