• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

(AUS) Removing a level crossing

Status
Not open for further replies.

Pakenhamtrain

Member
Joined
26 Jan 2014
Messages
1,059
Location
Melbourne, Australia
Over the last 8 years the Victorian government have been removing level crossings as part of an election promise made back by the Andrews Labor government. Initially 50 level crossings were promised to be removed the number has increased to 110.

Narre Warren and level crossing at Webb Street was added to the list of level crossings to be removed in July 2021. The current station is where I spent some of teenage years starting out my rail photography.


As part of the removal the railway line was to be elevated with a new station to be built next to the current station. Narre Warren is no stanger to level crossing removals. In 2004 Narre Warren - Cranbourne Road to the east of the station was duplicated and as part of the duplication the level crossing was removed the duplicated road going under the rail line.

bINomDM.jpg

The final artists impression of the station looking north.
From the LXRA/Bigbuild website.
Indigenous elements were added to the design of the station reflecting the local area as a place of movement and meeting.

Narre Warren is an island 2 track station. The current station has been in it's location on the west side of Webb Street since 1995. The current station buildings date back to 2003 when it was upgraded to a premium station featuring station building with a customer service desk.
The main entrance of the station in 2006.
Hitachi 23M stops at Narre Warren to pick up passengers. Next to the track is the former station masters house which was demolished 2006-2007.
Siemens 739M trails a down Pakenham train in 2006.
The first signs of work appeared in November with parts of the eastern carpark closed off and holes dug into the platform to allow the placement of temporary overhead stanchions.
Looking towards the city.
And delineation fencing was added next to both tracks.
In December the both carparks were closed and the temporary overhead stanchions were placed.

A week later the lights were removed from the carpark.

In Febuary of 2023 the carpark was leveled and the machines moved in.

One week later in March first up was the pile drill. Each support for the new viaduct required multiple piles to be put into the ground. Work started around the eastern carpark before moving to the west side carpark. Each pile was drilled out and filled with concrete before reinforcing bars were put into the concrete. All up 110 holes were dug.

In April the steel mesh that makes up the headstocks of the station arrived on side. These were cast on site.

Early May saw the digging out of the piles to start construction of the piers.

Mid to late May the first piers for the elevated track were ready to be cast. In this case they were cast on site.
And we saw the arrival of a crawler crane to lift the headstocks onto the piers.
In June multiple headstocks were placed.
And piling began on the far east side of the carpark next to Narre Warren - Cranbourne Road.
Late June saw the first Super T Beam placed. These beams form the platform of the new station. In this case this beam is for the new citybound platform 1.
July saw multiple Super T beams placed for both plaforms, L beams forming U troughs and more piers.


August saw more placement of L beams and the final placement of the Super T Beams.
Looking towards the city.
Looking towards Pakenham.
Early September saw the first L beams over the level crossing at Webb Street. At the same time the ramps that lead to the viaduct started construction.
Late September the lift shafts started to take form. The nature of this removal meant the citybound lift shafts were constructed in the temperory carpark to the south of the station. The Pakenham bound shafts were able to be constructed in place.
Also arriving on site was the first steel bridge peices that would span over Narre Warren - Cranbourne Road.

In October the steelwork for the station and surrounding infrastructe started to be placed.

Late October the steel bridges over Narre Warren - Cranbourne road were placed. The LXRA has fantastic photos of the process
Photos from the LXRA Facebook/Twitter page.

And now we arrive at November. Signals are in place, the ramps are in place, the new station buildings are under construction. The end of the current station was near.
And it was announced mid November that the station that served the Narre Warren area since 1995, and level crossing that has been in there for over 100 years would be no more.

On November 24 in all but a few hours the level crossing at Webb Street would become consigned to the history books.

At 2145 hours on the 24th of November HCMT unit 25 on run 4096 departed Narre Warren and crossed Webb Street as the final train to do so.
 
Status
Not open for further replies.

Top