Crossrail opening delayed until Autumn 2019

Discussion in 'UK Railway Discussion' started by gavin, 31 Aug 2018.

  1. gavin

    gavin Member

    Messages:
    958
    Joined:
    25 Dec 2006
    Crossrail delayed until Autumn 2019

    https://www.bbc.com/news/uk-england-london-45367990
     
    Last edited: 1 Sep 2018
  2. Registered users do not see these banners - join or log in today!

    Rail Forums

     
  3. plcd1

    plcd1 Member

    Messages:
    699
    Joined:
    23 May 2015
    The opening of the Crossrail core has been delayed to Autumn 2019. No word yet what that means for subsequent phased openings but this is a serious but not unexpected delay.
     
  4. quantinghome

    quantinghome Member

    Messages:
    521
    Joined:
    1 Jun 2013
    Breaking News: Crossrail opening delayed until autumn next year

    https://www.theguardian.com/uk-news...rail-opening-postponed-until-autumn-next-year
     
    Last edited by a moderator: 31 Aug 2018
  5. CeeJ

    CeeJ Member

    Messages:
    60
    Joined:
    25 Jun 2017
    Announcement today that Crossrail’s opening will be pushed back until autumn next year!

    https://twitter.com/skynewsbreak/status/1035453997329645568?s=21
     
    Last edited by a moderator: 31 Aug 2018
  6. theironroad

    theironroad Established Member

    Messages:
    1,910
    Joined:
    21 Nov 2014
    Location:
    London
    That's not just a couple of weeks late then, but a hefty overrun of almost a year.
    Certainly a massive project, but also quite a hyped one, so there's going to be some embarrassment.
     
  7. hwl

    hwl Established Member

    Messages:
    2,220
    Joined:
    5 Feb 2012
    Paddington - Abbey Wood delayed till autumn '19 with LST -Shenfield to operate as currently (was meant to change in May '19) and they hope to have 345s to Heathrow (was planned for last May) by then.

    This screws up the LST high level platform works planned for next June-July so they can take 9 car.
     
  8. theking

    theking Member

    Messages:
    264
    Joined:
    30 Sep 2011
    No surprise I hear they have trainee drivers sitting at home doing nothing due to lack of di's like gtr did.
     
  9. hwl

    hwl Established Member

    Messages:
    2,220
    Joined:
    5 Feb 2012
    Crossrail Press Release:
     
    Last edited: 31 Aug 2018
  10. bramling

    bramling Established Member

    Messages:
    5,043
    Joined:
    5 Mar 2012
    Location:
    South-east / Barnard Castle
    Not really surprising. Apart from persistent rumours, the stations look nowhere near ready, the trains are nowhere near as bedded in as they should be this close to December, and testing has barely started.

    Shades of the JLE all over again...

    However, to be fair, it’s a massive project and a few months delay in the grand scheme of things isn’t the end of the world.
     
  11. jon0844

    jon0844 Veteran Member

    Messages:
    23,080
    Joined:
    1 Feb 2009
    Location:
    UK
    Guess it's now the turn of TfL to get the media attention. Must be good news for GTR, especially on a week where GTR is announcing more trains from the original May timetable being restored in the coming weeks.
     
  12. ijmad

    ijmad Member

    Messages:
    780
    Joined:
    7 Jan 2016
    Location:
    UK
    I think everyone was expected a few months of delay but 9+ months is pretty surprising, especially given it's also pushing back the Shenfield and Reading branch services even further. Is there any chance they're underpromising deliberately and might actually beat their revised goal and open in June or something?
     
  13. SteveOfTheStow

    SteveOfTheStow Member

    Messages:
    71
    Joined:
    16 Dec 2017
    I wonder if they're saying autumn but really are planning for the May 2019 timetable change
     
  14. samuelmorris

    samuelmorris Established Member

    Messages:
    2,406
    Joined:
    18 Jul 2013
    Location:
    Brentwood, Essex
    Not remotely surprising, just disappointing they didn't give any public impression things were behind, though we could visibly see that was the case...
     
  15. ijmad

    ijmad Member

    Messages:
    780
    Joined:
    7 Jan 2016
    Location:
    UK
    First rule of Project Management, if you miss your original delivery date, it's better to vastly pad the remaining time and surprise people, rather than set an aggressive revised date and miss it a second time.
     
  16. SteveOfTheStow

    SteveOfTheStow Member

    Messages:
    71
    Joined:
    16 Dec 2017
    None of the core stations look remotely ready on the surface - that's not work you can do in 3 months!
     
  17. hwl

    hwl Established Member

    Messages:
    2,220
    Joined:
    5 Feb 2012
    Just Abbey Wood - Paddington is new for Autumn 2019 it doesn't rely on any NR TT changes.

    The May '19 Shenfield- Paddington has got delayed and this does have NR timetable impacts and means the defeerrment of the LST high level platform works from June -July '19 to after whenever the Shenfield trains go through the core (so December 2019 at the earliest). Just as well the 315 lease was extended. Delaying the GWR to CR transfers from Dec '19 till May '19 at the earliest also leaves plenty of room to sort out the issues more sensibly there (769s, 387 for HEx, Heathrow tunnel signalling and all the station works)
     
  18. LeeLivery

    LeeLivery Member

    Messages:
    883
    Joined:
    13 Jul 2014
    Location:
    London
    Journalists are claiming TfL and the DfT only found out yesterday that it would be late.

    I find that hard to believe. Well, not that Grayling found out yesterday but TfL. If they hadn't planned for this they're more stupid than they look. It's been expected by everyone.

    Indeed, I was at Whitechapel the other week. It's at least a year off.
     
  19. ijmad

    ijmad Member

    Messages:
    780
    Joined:
    7 Jan 2016
    Location:
    UK
    Twitter rumours say TfL and the DfT were only told yesterday:
    https://twitter.com/catneilan/status/1035459461392031744
     
    Last edited by a moderator: 31 Aug 2018
  20. Mikey C

    Mikey C Established Member

    Messages:
    2,154
    Joined:
    11 Feb 2013
    It was the same with the new Spurs stadium, everyone could see it was well behind schedule, but the club only admitted it at a pretty late date
     
  21. Joe Paxton

    Joe Paxton Established Member

    Messages:
    1,489
    Joined:
    12 Jan 2017
    I imagine that is a gross simplification. Rather, perhaps it was only yesterday that Crossrail Ltd officially informed TfL and the DfT that the central core wouldn't be ready for December - but TfL and the DfT would have been increasingly well aware that things were not on course. Apart from anything else, various TfL people are deeply integrated into the Crossrail project. And Crossrail Ltd is a wholly owned subsidiary of TfL.

    I smell the scent of DfT / Grayling blame avoidance!
     
  22. matthewmacleod

    matthewmacleod Member

    Messages:
    113
    Joined:
    19 May 2011
    Ultimately it's probably for the best. Somewhat miffed I have to wait a few extra months, but given the scope and scale of the project it's hardly a devastating delay.

    Is there any indication of the factors that ended up pushing this decision? I get the impression from the PR that it's mostly down to station fit-out running behind schedule, as well as issues with signalling.
     
  23. pdeaves

    pdeaves Established Member

    Messages:
    1,553
    Joined:
    14 Sep 2014
    Location:
    Gateway to the South West
    Actually, I would put that as a second rule, the first being that you don't wait until just three months before a major launch to assess the facts and decide it's not sensible!
     
  24. LeeLivery

    LeeLivery Member

    Messages:
    883
    Joined:
    13 Jul 2014
    Location:
    London
    Indeed "I'm not an expert in rail matters." :lol:
     
  25. Searle

    Searle Established Member

    Messages:
    1,556
    Joined:
    4 May 2012
    Location:
    Ladbroke Grove
    [​IMG]

    me, finding out about this news
     
  26. ijmad

    ijmad Member

    Messages:
    780
    Joined:
    7 Jan 2016
    Location:
    UK
    Geoff Marshall has put up a rather speedy vlog which has some Q&A in it around his previous vid (and some more discussion of the service pattern), but also mentions the delay. Speedy recording... unless he had confirmed rumours from insider sources. He says 'Summer 2019' several times in the video whereas the actual press release says Autumn.

     
    Last edited: 1 Sep 2018
  27. Cletus

    Cletus Established Member

    Messages:
    1,617
    Joined:
    11 Dec 2010
    Location:
    Dover
    I love this (underlined) part of this Londonist post
    https://londonist.com/london/transp...l-delay?utm_source=dlvr.it&utm_medium=twitter

     
  28. Requeststop

    Requeststop Member

    Messages:
    753
    Joined:
    21 Jan 2012
    Location:
    Port Moresby, Papua New Guinea
    900 Million over budget I hear and delayed a year. More money being thrown at and wasted in London and the South East. Are there no penalty clauses in the contracts for being over budget and delays to finishing the projects? I bet there are no resignations over this further debacle. Dreadful.
     
  29. matthewmacleod

    matthewmacleod Member

    Messages:
    113
    Joined:
    19 May 2011
    Neither of those are true.

    There is a good business case for the project, and it would be difficult to realistically call that money 'wasted' in any sense.

    There are obviously a huge number of contracts in place and many of those will have conditions tied to on-time completion.

    Good. There should be no resignations over this.

    You are wildly overstating this.
     
  30. DarloRich

    DarloRich Veteran Member

    Messages:
    19,389
    Joined:
    12 Oct 2010
    Location:
    Work - Fenny Stratford(MK) Home - Darlington
    Told (Officially) and known ( unofficially) are two different things - especially where government types are concerned! ;)
     
  31. thejuggler

    thejuggler Member

    Messages:
    326
    Joined:
    8 Jan 2016
    I suspect 'only told yesterday' was the detail on the length of the delay, not the fact there was a delay as these will be reported monthly.

    In the end the system will be there for decades, so apart from cost and inconvenience the opening date isn't time critical.
     