YourMum666
Member
Would the GW electrification scheme have made more sense if it was planned to head down to exeter through the bristol line and the B&H line
Didcot - Oxford should really have been electrified before Reading - Newbury.It would be good if it was to be electrified, but in terms of trains per hour the west of England are lower frequency than elsewhere. West of Newbury on the B&H is rarely more than 4 trains an hour, and is down to one or two between Castle Cary and Taunton
Indeed. If you could get to at least Westbury, the 80x units would be able to use the wires for further, Mendip stone could gain improved performance over the hills and local service to Bedwyn could switch to EMU. Ideally the wires would extend further to Frome and the quarry branches so the same electric locos could be used throughout, otherwise a bi-mode haulage solution would be required or a loco change at Westbury. Any extension of wiring along their routes is beneficial to bi-mode or battery-equipped passenger stock as it decreases diesel usage and increases fuel or battery range.I think the B&H line should be the priority, to move the Acton stone trains to electric. That would be transformational (as consultants and powerpoint bandits love to say)
Junction remodelling and resignalling at both ends of Temple Meads are finished though, and equipment and new structures have been provided fully compatible with hopefully soon-to-be commenced wiring.They haven't even got to Temple Meads either.
How much use would Filton electrification get? Until the locals, regionals, and XC have bi-modes it wouldn't see that many trains an hour using it and I doubt it would lead to GWR changing any IETs to pure electric.Junction remodelling and resignalling at both ends of Temple Meads are finished though, and equipment and new structures have been provided fully compatible with hopefully soon-to-be commenced wiring.
Oxford is awaiting a station rebuild, then it will be electrified.Didcot - Oxford should really have been electrified before Reading - Newbury.
The GWR Bristol Temple Meads trains head through Bath, which still isn't electrified.and I doubt it would lead to GWR changing any IETs to pure electric.
Indeed. If you could get to at least Westbury, the 80x units would be able to use the wires for further, Mendip stone could gain improved performance over the hills and local service to Bedwyn could switch to EMU. Ideally the wires would extend further to Frome and the quarry branches so the same electric locos could be used throughout, otherwise a bi-mode haulage solution would be required or a loco change at Westbury. Any extension of wiring along their routes is beneficial to bi-mode or battery-equipped passenger stock as it decreases diesel usage and increases fuel or battery range.
Bimode locos pulling 5,000 tons of stone sounds challenging! Probably need 4 of them or something... You would think changing locos at Newbury would be a possibility thoughHow many stone trains a day are there? and if you're looking at bimode haulage for them, can't it go to Newbury on diesel? that seems like something that shouldn't wait for wires.
NE-SW expresses, Bristol-southwards locals, Wales-Birmingham freights for wiring the Brum-Taunton bit ( presuming going either way went to Plymouth ). Wonder if the Bromsgrove wiring could support doing all the lines.
I'd support that of course, but the bigger performance benefits of electric operation are available west of Newbury where the long gradients are encountered.How many stone trains a day are there? and if you're looking at bimode haulage for them, can't it go to Newbury on diesel? that seems like something that shouldn't wait for wires.
I assume you mean Westbury as the wires already extend to just beyond Newbury? The whole Bath - Trowbridge, Chippenham - Trowbridge network could do with wires to provide better diversionary routes for both freight and passenger, but it might not be among the most compelling early schemes. That bimode locos can run off wire would allow freights to get to Chippenham from Westbury anyway and the quieter and slower route might mean easier pathing until the wires are met again around Chippenham.Would the operators accept electrification to Newbury only or would they demand electrification to Chippenham as well for diversions?
I agree that completing those original goals really should be the immediate priority, but B&H could be an interesting add-on after that as many bi-mode trains run there already on fast and semi-fast expresses to Devon and Cornwall and the potential for regular London-Bedwyn services using EMUs.The priority should be completing electrification as originally envisaged, ie to Oxford, Swansea, and Bristol via both routes. Beyond Bristol, possibly to Weston-Super-Mare, but I don't see the traffic justifying it beyond there, or Newbury.
Another vote for Oxford and Bristol first. After all,if Exeter were fully wired up, we'd probably end up getting 387s on some Padd trains!!!Coming from a current Exeter resident, Oxford and Bristol Via Box must take priority. Was in the original project scope and work had already started before being put 'on hold'. Think back to all the work done at Bath and Keynsham what feels like many years ago to make the line 25Kv ready
Bimode locos pulling 5,000 tons of stone sounds challenging! Probably need 4 of them or something... You would think changing locos at Newbury would be a possibility though
How much use would Filton electrification get? Until the locals, regionals, and XC have bi-modes it wouldn't see that many trains an hour using it and I doubt it would lead to GWR changing any IETs to pure electric.
It needs doing, just questioning its place in the queue.
Yes lots of work was done, there are even some masts erected east of Chippenham.Coming from a current Exeter resident, Oxford and Bristol Via Box must take priority. Was in the original project scope and work had already started before being put 'on hold'. Think back to all the work done at Bath and Keynsham what feels like many years ago to make the line 25Kv ready
Coming from a current Exeter resident, Oxford and Bristol Via Box must take priority. Was in the original project scope and work had already started before being put 'on hold'. Think back to all the work done at Bath and Keynsham what feels like many years ago to make the line 25Kv ready
That would involve splitting most of the regional trains - would Cardiff accept getting a Bristol shuttle and no more trains through beyond that?Allowing Bristol - Cardiff trains to go electric would be pretty useful, as well as a lot of ECS moves to and from Stoke Gifford depot. Remember some of the locals are bi mode now.
Electrifying to Oxford allows for an end to the split of the locals in didcot, so improves the railway product in the areaThat would involve splitting most of the regional trains - would Cardiff accept getting a Bristol shuttle and no more trains through beyond that?
Accepting the significant difference in miles I don't really see that Oxford and Bristol routes add all that much compared to electrifying the huge aggregate trains using diesel all the way from the quarries into outer London, presumably speeding them up and keeping them out of the way better too.
That is why we need a large fleet of BEMU/'tri-mode' Stadler FLIRTs (or similar*) for local/regional services in the south-west (all operators - TfW, GWR SWR), including the Cardiff - Portsmouth axis (for which 3rd rail pick up would be useful too). Then a longer-term strategy of piecemeal gap-filling electrification can steadily reduce any remaining unwired diesel mileage, leading to eventual removal of the diesel generator sets from those trains' power pods.That would involve splitting most of the regional trains - would Cardiff accept getting a Bristol shuttle and no more trains through beyond that?
Level boarding should be specified as a required feature for ALL new rolling stock, whether for northern, gwr or elsewhereThat is why we need a large fleet of BEMU/'tri-mode' Stadler FLIRTs (or similar*) for local/regional services in the south-west (all operators - TfW, GWR SWR), including the Cardiff - Portsmouth axis (for which 3rd rail pick up would be useful too). Then a longer-term strategy of piecemeal gap-filling electrification can steadily reduce any remaining unwired diesel mileage, leading to eventual removal of the diesel generator sets from those trains' power pods.
* other train manufacturers are available but I hope the FLIRTs' level boarding feature is not sacrificed in specifications.
A good one for partial electrification once the mainline wiring reaches St Davids, given suitable new trains. Say Crediton to Topsham and somewhere en route to Axminster, so BEMUs should be able to cope. On the main line, the estuary and sea wall sections beyond Exminster pose their own unique challenges.6. Possibly branches around Exeter?
Agree strongly!Level boarding should be specified as a required feature for ALL new rolling stock, whether for northern, gwr or elsewhere
The upcoming (with GBRf) class 99 six-axle high-power bi-modes would be absolutely fine - slower than a 59 on diesel due to a less powerful engine, but under OHLE with 6000 kW (8000 hp) available, higher tractive effort and modern AC-traction drives they should romp away.Bimode locos pulling 5,000 tons of stone sounds challenging! Probably need 4 of them or something... You would think changing locos at Newbury would be a possibility though
Why would you think that?Surely electrification to Exeter/Plymouth and Briston will not be continuous, but will be in sections to allow BEMU's to be used in the non-electrified bits.