• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

National Audit Office update on scrapping of HS2 phase 2 will cost £100m and take up to three years

Status
Not open for further replies.

Nicholas Lewis

On Moderation
Joined
9 Aug 2019
Messages
7,266
Location
Surrey
NAO has done one of its frequent updates into HS2

https://www.nao.org.uk/wp-content/u...following-cancellation-of-phase-2-summary.pdf

A couple of takeaways

HS2 Ltd expects to complete remediation works for Phase 2 by summer 2027 at an estimated cost of up to £100 million
then we have
As at the end of March 2024, the HS2 programme had spent £592 million buying land and around 1,000 properties on the Phase 2 route that DfT will no longer need for HS2.
not forgetting Euston
DfT has progressed with developing minimum requirements for the station and options for a new delivery model ahead of ministerial approval. However, it is at an earlier stage in considering how cost and risk will be transferred and what the long-term governance arrangements at Euston will be. DfT expects it may be several years before it could put all these arrangements in place
oh and acknowledges
DfT will not be able to address capacity issues on the West Coast Main Line north of Birmingham through its revised programme scope
what a fiasco but at least it report one positive in the appointment of Mark Wild
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

snowball

Established Member
Joined
4 Mar 2013
Messages
8,111
Location
Leeds
This report has also been linked in another thread (post #280 here):

 
Status
Not open for further replies.

Top