Nicholas Lewis
On Moderation
NAO has done one of its frequent updates into HS2
https://www.nao.org.uk/wp-content/u...following-cancellation-of-phase-2-summary.pdf
A couple of takeaways
https://www.nao.org.uk/wp-content/u...following-cancellation-of-phase-2-summary.pdf
A couple of takeaways
then we haveHS2 Ltd expects to complete remediation works for Phase 2 by summer 2027 at an estimated cost of up to £100 million
not forgetting EustonAs at the end of March 2024, the HS2 programme had spent £592 million buying land and around 1,000 properties on the Phase 2 route that DfT will no longer need for HS2.
oh and acknowledgesDfT has progressed with developing minimum requirements for the station and options for a new delivery model ahead of ministerial approval. However, it is at an earlier stage in considering how cost and risk will be transferred and what the long-term governance arrangements at Euston will be. DfT expects it may be several years before it could put all these arrangements in place
what a fiasco but at least it report one positive in the appointment of Mark WildDfT will not be able to address capacity issues on the West Coast Main Line north of Birmingham through its revised programme scope