The Planner
Veteran Member
- Joined
- 15 Apr 2008
- Messages
- 17,817
What section lengths on the Coventry to Nuneaton line are above this 45mph limit and where are they?
None of it is above 45mph
What section lengths on the Coventry to Nuneaton line are above this 45mph limit and where are they?
To recap.
The 230 has been tested up to to 20 mph at Long Marston. It has proven running gear, structure and doors - all as used on London Underground. The engines are a proven automotive design. It has been confirmed it has a coupling adaptor for rescue.
The main areas of uncertainty it seems to me are the control module and how the engines behave under a rail vehicle. But it works up to 20 mph on ropey track.
So how to progress things ?. How about a faster line with real world passengers on it !. One that is off the route used by other services as far as possible. The Coventry to Nuneaton route is fairly self contained, has a line speed reaching 45 mph and is in need of an increase in capacity.
Currently the line is operated by a 153 - a single car. The 230 will be an improvement as it is longer. So if it breaks down the service will have to revert to the single car train CURRENTLY USED. I expect the 153 will be kept hanging around near Coventry/Nuneaton for an initial period until LM are more confident. If a 153 is not available for rescue (that can happen - other trains do break down) then it follows that the service will be disrupted if the 230 breaks down. BUT that is the same situation as if the 230 had never existed. However, while one or both of a 153 and the 230 are working, the service will be better.
To recap.
The 230 has been tested up to to 20 mph at Long Marston. It has proven running gear, structure and doors - all as used on London Underground. The engines are a proven automotive design. It has been confirmed it has a coupling adaptor for rescue.
Currently the line is operated by a 153 - a single car. The 230 will be an improvement as it is longer. So if it breaks down the service will have to revert to the single car train CURRENTLY USED. I expect the 153 will be kept hanging around near Coventry/Nuneaton for an initial period until LM are more confident. If a 153 is not available for rescue (that can happen - other trains do break down) then it follows that the service will be disrupted if the 230 breaks down. BUT that is the same situation as if the 230 had never existed. However, while one or both of a 153 and the 230 are working, the service will be better.
Im pretty sure that now they have been given the go ahead with the trial train that they will be ramping up producing another one or two to ensure that any breakdowns or faults will just enable a simple switch of trains. Be foolish if they didnt do that.
If a traction pack fails, then they can do a simple switch of one of those in about 10 minutes using a forklift.
There is a short LM has already stated that, in the early days at least, the 153 will be kept in the area on standby.
If a traction pack fails, then they can do a simple switch of one of those in about 10 minutes using a forklift.
Sensible to keep the Class 153 on standby as there are rail passengers who need an assured service provision.
Are there any areas on the Coventry to Nuneaton line where a Class 230 with such a problem would be difficult to access?
Sensible to keep the Class 153 on standby as there are rail passengers who need an assured service provision.
--- old post above --- --- new post below ---
Are there any areas on the Coventry to Nuneaton line where a Class 230 with such a problem would be difficult to access?
Sensible to keep the Class 153 on standby as there are rail passengers who need an assured service provision.
--- old post above --- --- new post below ---
Are there any areas on the Coventry to Nuneaton line where a Class 230 with such a problem would be difficult to access?
In the nature of these things it is inevitable that on the very first day one of these will break down on a bridge but.......surely the whole point of this design is that a failed "traction pack" won't usually matter as the train will be able to get back to depot on the remaining power.
Im well aware of that however this isnt much good if it goes up ****creek with no access to bring another in let alone have a forklift do its job either.
"The engines are a proven automotive design"
And so were all the engines in the modernisation-era DMUs, and none of them were any good.
The Rolls-Royce, Albion, AEC and Leyland engines were all bus/truck derived and all were useless in a rail environment, the Leyland ones maybe surviving longer simply because there were more of them and so became "standard".
Engines optimised for road use may be totally unsuitable for rail use
As logical an explanation as it is, I still fear it will fall flat on those wishing doom and gloom upon this enterprise.
In the nature of these things it is inevitable that on the very first day one of these will break down on a bridge but.......surely the whole point of this design is that a failed "traction pack" won't usually matter as the train will be able to get back to depot on the remaining power.
Hence the upcoming year-long trial!
Where exactly will "the depot" be?
--- old post above --- --- new post below ---
Noting that today is the last day of September 2016, can I ask how near are we now to the commencement of this "one year period"?
Where exactly will "the depot" be?
--- old post above --- --- new post below ---
Noting that today is the last day of September 2016, can I ask how near are we now to the commencement of this "one year period"?
"The engines are a proven automotive design"
And so were all the engines in the modernisation-era DMUs, and none of them were any good.
The Rolls-Royce, Albion, AEC and Leyland engines were all bus/truck derived and all were useless in a rail environment, the Leyland ones maybe surviving longer simply because there were more of them and so became "standard".
Engines optimised for road use may be totally unsuitable for rail use
It will get based at Coventry North Yard, nowhere else to put it.
Documentation I have seen says its going in there. Bay platform is the last of the worries as there is no money for it...
Signalling diagram for the bay platform has been doing the rounds for a couple of years and considering the documentation saying its going in the North yard is from LM then I would assume there is some truth in it.
Signalling diagram for the bay platform has been doing the rounds for a couple of years and considering the documentation saying its going in the North yard is from LM then I would assume there is some truth in it.
Eh?
As others have noted, if the 230 fails, it will get dragged back to somewhere it can be worked on - same as happens when trains of other types fail... and unless it suffers some absolutely catastrophic failure, it is highly likely to be able to limp home by itself, given the nature of the traction set-up, using multiple power packs.
Like I said, LM will have a 153 on standby locally in the early stages. And even if that does get withdrawn eventually, all it will mean is things reverting to how they are now if a unit working Coventry-Nuneaton fails - LM has to rustle up another unit from Tyseley.
Or is Vivarail supposed to abide by some special gold standard dictated by you, with a standby train and a squad of engineers on hand just in case, whenever 230001 turns a wheel?
You think that no progress has been made in engine design and manufacture in the last 70 years?
I suspect little progress has been made in modifying engines optimised for road use to rail use. The applications are fundamentally different, with completely separate use regimes.
You may have missed it but I am one of the people who has been for this project right from the start and it makes sense for them to get started on a second one not only to use as a rescue train but also for when people see it working in real time other TOCs may change their mind and want to test one themselves.