Morning All,
I'm hoping this post catches the attention of some sort of signaling guru!
I am in the process of putting together some high level cost estimates for some major rail projects across the UK. Part of the one schemes I'm looking at requires that the existing signalling system is decommissioned and replaced with new and/ or a standard Line of Sight (LOS) system for LRT operation.
Typically, I understand that SEU rates are used to estimate signalling projects, but what is included in a standard SEU rate and how many SEUs are to be included per section of track? Is there any guidance or literature that exists on the topic? Google doesn't seem to be throwing any pointers.
I'm hoping this post catches the attention of some sort of signaling guru!
I am in the process of putting together some high level cost estimates for some major rail projects across the UK. Part of the one schemes I'm looking at requires that the existing signalling system is decommissioned and replaced with new and/ or a standard Line of Sight (LOS) system for LRT operation.
Typically, I understand that SEU rates are used to estimate signalling projects, but what is included in a standard SEU rate and how many SEUs are to be included per section of track? Is there any guidance or literature that exists on the topic? Google doesn't seem to be throwing any pointers.