• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Class 701 'Aventra' trains for South Western Railway: progress updates

Snow1964

Established Member
Joined
7 Oct 2019
Messages
8,237
Location
West Wiltshire
Useless statistic
tommorow (6th Oct 2023) is 2300th day from when order was announced back in June 2017

First one entering service according to original schedule is nearly 4 years late (was Autumn 2019). Is this some sort of record.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

gabrielhj07

Established Member
Joined
5 May 2022
Messages
1,214
Location
Herts
Meanwhile the Windsor Lines Passengers Association covers Windsor and Reading lines, Hounslow loop, Kingston loop, Chertsey and Camberley branches, but not Shepperton.
Bit odd that the Kingston Loop is included but not the Shepperton Branch.
 

gabrielhj07

Established Member
Joined
5 May 2022
Messages
1,214
Location
Herts
Trains via Kingston loop use the Windsor lines. Most Shepperton services go via Wimbledon.
I know that the majority of Shepperton services stick to the mainline side, but as an extension of the New Malden - Twickenham loop, which is 'Windsor side', I'd have thought it'd be included. Not the end of the world.
 

Nicholas Lewis

On Moderation
Joined
9 Aug 2019
Messages
7,289
Location
Surrey
Useless statistic
tommorow (6th Oct 2023) is 2300th day from when order was announced back in June 2017

First one entering service according to original schedule is nearly 4 years late (was Autumn 2019). Is this some sort of record.
I would imagine Alstom must be questioning their purchase of Bombardier now after their shares crashed nearly 30% yesterday and which they partly attributed the cause as

Second, representing around one third of the variation, is the delay in completing the Aventra program in the UK, which has impacted first half cash-flow, and this will be only partly recovered in the second half, as completion is now expected beginning of fiscal year 2024/25
alstom-discloses-preliminary-financial-information-its-first-half-fiscal-year-202324-ending-september-30-2023
 

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
11,842

Invincible

Member
Joined
23 Apr 2022
Messages
635
Location
Surrey
I would imagine Alstom must be questioning their purchase of Bombardier now after their shares crashed nearly 30% yesterday and which they partly attributed the cause as


alstom-discloses-preliminary-financial-information-its-first-half-fiscal-year-202324-ending-september-30-2023
"However, the Aventra program in the UK, one of the legacy non-performing contracts, has not been completed as per original plans during this first half and is now expected to be completed beginning of fiscal year 2024/25. The negative impact has been recognized on first half adjusted EBIT."

Am a bit confused by this, many Aventra units have been delivered to SWR and the leasing company should have paid Alstom. But guess SWR are saying the trains build and software are not up to being in service, so payment has been withheld.
Alstom do not see it as thier fault.
A spokesman said: "Since then Alstom has delivered the same model of train to other customers including the Elizabeth Line which are operating very successfully."
Guess lawyers are now involved?

So there must be pressure to get the trains in service before the end of the year, but the only tests are the 5Q50/51/52 by GBRF staff (been running OK this week).
 
Last edited:

43096

On Moderation
Joined
23 Nov 2015
Messages
16,860
"However, the Aventra program in the UK, one of the legacy non-performing contracts, has not been completed as per original plans during this first half and is now expected to be completed beginning of fiscal year 2024/25. The negative impact has been recognized on first half adjusted EBIT."

Am a bit confused by this, many Aventra units have been delivered to SWR and the leasing company should have paid Alstom. But guess SWR are saying the trains build and software are not up to being in service, so payment has been withheld.
Alstom do not see it as thier fault.
A spokesman said: "Since then Alstom has delivered the same model of train to other customers including the Elizabeth Line which are operating very successfully."
Guess lawyers are now involved?

So there must be pressure to get the trains in service before the end of the year, but the only tests are the 5Q50/51/52 by GBRF staff (been running OK this week).
It’s not just the SWR build, though - there’s the West Mids/LNR fleet, too.
 

PG

Established Member
Joined
12 Oct 2010
Messages
3,277
Location
at the end of the high and low roads
"However, the Aventra program in the UK, one of the legacy non-performing contracts, has not been completed as per original plans during this first half and is now expected to be completed beginning of fiscal year 2024/25. The negative impact has been recognized on first half adjusted EBIT."
Their use of the word legacy implies (or I infer?) that they won't be offering the Aventra platform for new orders? Not that any UK orders are likely for EMUs for a good while.
 

Hophead

Established Member
Joined
5 Apr 2013
Messages
1,294
Their use of the word legacy implies (or I infer?) that they won't be offering the Aventra platform for new orders? Not that any UK orders are likely for EMUs for a good while.

You would have thought that Aventra orders would be scarce indeed, even from those operators who have been able to get them running.
 

stuving

Member
Joined
26 Jan 2017
Messages
496
Their use of the word legacy implies (or I infer?) that they won't be offering the Aventra platform for new orders? Not that any UK orders are likely for EMUs for a good while.
Remember, this was Alstom trying to explain away that their "free cash flow" for the last six months was minus €1.2 billion, compared with about zero for the same period in 2022. A third (but only a third) of that is due to the Aventras, where out of 443 trains in all, 90% are built but only 70% accepted by customers. To what extent the 701s count as "accepted" is not at all clear, and probably depends on accounting conventions and the details of the horse-trading done with SWR and Rock Rail.

So they are trying to distance the Alstom brand from anything designed and built by Bombardier. (They may claim to be improving production to meet their own higher standards, but that takes time.) The rest of the cash flow problem is due to building more trains (to clear a backlog) while taking in less in initial payments on new orders. It sounds like shortage of cash flow is a problem inherent in the way train-makers do business.
 

hwl

Established Member
Joined
5 Feb 2012
Messages
7,672
Their use of the word legacy implies (or I infer?) that they won't be offering the Aventra platform for new orders? Not that any UK orders are likely for EMUs for a good while.
No, legacy in this context is a Bombardier pre merger contract. The context is contracts not products
 

43096

On Moderation
Joined
23 Nov 2015
Messages
16,860
Unless it's good. They're happy to tell you about more orders for Traxx locmotives, for instance, or that Tren Maya units have Flexx Eco bogies.
To be fair, Alstom are putting a lot of work into the Traxx product, as it was an absolute dog under the latter days of Bombardier. To what extent the orders are down to confidence in Alstom and Traxx, or because Siemens' order book for Vectrons is pretty much full and there's little capacity for substantial new orders for some time.
 

XCTurbostar

Established Member
Joined
13 Sep 2014
Messages
2,127
Safe to say December introduction won't happen now.. I wonder how long it will be? <D
 

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
11,842
No, legacy in this context is a Bombardier pre merger contract. The context is contracts not products
Having said that, who would order any more Aventras, apart from a possible top-up order for the Elizabeth line? The things have have been fraut with problems right from the start.

It's Juniper all over again. By the time Alstom had designed Juniper 2 no one was interested and went elsewhere.
 

Peter Sarf

Established Member
Joined
12 Oct 2010
Messages
7,759
Location
Croydon
Having said that, who would order any more Aventras, apart from a possible top-up order for the Elizabeth line? The things have have been fraut with problems right from the start.

It's Juniper all over again. By the time Alstom had designed Juniper 2 no one was interested and went elsewhere.
I predict that by the time TfL actually order a few more 345s for the Elizabeth line the Derby production line will have moved on from Aventras or become a "development opportunity". But then again the biggest factor effecting that will be how quickly the 701 order gets completed.
 

Goldfish62

Veteran Member
Joined
14 Feb 2010
Messages
11,842
I predict that by the time TfL actually order a few more 345s for the Elizabeth line the Derby production line will have moved on from Aventras or become a "development opportunity". But then again the biggest factor effecting that will be how quickly the 701 order gets completed.
Litchurch Lane will probably be "Derby Urban Village and Retail Park" before the 701s enter service. :D
 

Peter Sarf

Established Member
Joined
12 Oct 2010
Messages
7,759
Location
Croydon
Litchurch Lane will probably be "Derby Urban Village and Retail Park" before the 701s enter service. :D
Construction of said facility held up by all the scrap metal in the way !.
It's déjà vu - the Aventra is a wonderful marketing tool for Siemens :D
And this time also Hitachi, CAF and the Chinese.

Looking back was it not the case that Siemens declined to bid for Crossrail stock (Elizabeth Line) due to them deciding they could not commit to so much work at the time as they had other orders to fulfil.

Meanwhile the sales team at Derby were rather more er confident........
 

Mainsideman

Member
Joined
6 Jul 2018
Messages
201
Location
Croydon
Has a method of working been agreed yet for crew?

Last 707s leaving this week! Are we any closer to seeing the 701s in service??
 

TheHSRailFan

Member
Joined
16 Jun 2018
Messages
285
Has a method of working been agreed yet for crew?

Last 707s leaving this week! Are we any closer to seeing the 701s in service??
Theres been talk about it and a date has been surfacing in discord gen channels, but I will not say by the complete chance that it's complete wibble and nothing happens on that date.
 

The_Train

Established Member
Joined
2 Jun 2018
Messages
4,783
Can anyone confirm what 701s are at Worksop at the moment please?
I try to keep up to date with these moves at https://www.ukraillog.co.uk/fleet-data/emu/701 - although these unit moves (without internal systems) are hard work trying to keep up to date so I can't guarantee this is 100% correct. Try the link and type "Worksop" into the Search Fleet box :)

Edit: If anyone else checks this and spots any errors, then let me know :)
 

Top