If one of the on-test units has a problem in the daytime it’ll cause absolute mayhem.
One of the recent tests carried out was the current fleet rescuing the new fleet, and I believe it was also tested the other way round too. As
@DanNCL says, an adapter is needed but most of the network is reachable within at most 1 hour in a van. If they think it's going to be needed it may even be worth the new fleet carrying an adapter for the first while, they'll likely be riding round with an engineer on board anyway. I imagine the bigger issue is the current fleet failing and needing rescued and this is only going to become more likely, at which point the old fleet could then do with an emergency coupler being carried in a B end cab.
Do we know why they may be trying to minimise daytime testing before the units enter passenger service? Sounds quite bizarre.
It's significantly better to do simulated testing at night with no passengers around. Doors can be released, the gap fillers can be checked for level etc. If this was done during the day passengers may attempt to board. Daylight testing will however be necessary, along with simulated testing during the day, doors would not be released, but train would stop and dwell and then depart as a normal service train would.
having the three already here enter passenger service would be a great starting point. The service has really got worse since February.
I do understand that the testing is still ongoing, but how could Nexus have planned their entry into service so poorly? The trains were originally due to enter passenger service in Summer 2023, but this has already been postponed multiple times and the new deadline is now May/June 2024. Do they not know how long testing for a new unit takes?
I believe 003 is the unit being used for the full suite of testing that will be needed for ORR approval with 004 and 005 undertaking testing alongside.
The service is only going to get worse so I'd not expect any improvements soon. Once the new fleet does start revenue earning service they will likely be kept to short diagrams, though I can see them partly covering a full diagram until a new set can be shunted out should a failure occur.
Any timescale Nexus gives out you should always add either months or years too, not sure they've ever delivered a project on time, let alone a train service
Part of me is wondering whether the testing is really going as well as advertised, because it certainly looks like they are trying not to have the Class 555 enter passenger service at all.
From what I know from old colleagues, the testing is going fairly well for a brand new train but there are numerous niggles. Trust me when I say they will be doing their darndest to get them into service as quickly, and safely, as possible.