• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Crewe to Alsager - why was it singled?

Status
Not open for further replies.
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
15,157
Location
Bristol
Fairly sure it's been mentioned before that the budget didn't stretch to rebuilding the bridges that were too low for electrification on two tracks but moving the track to the centre of the arch gave sufficient clearance.
 

Railsigns

Established Member
Joined
15 Feb 2010
Messages
2,753
It was singled as part of the Crewe remodelling scheme in 1985, long before the line was electrified.
 

ChiefPlanner

Established Member
Joined
6 Sep 2011
Messages
8,060
Location
Herts
Before singling - there was a connection off the Kidsgrove line under the WCML into Gresty Lane Yard , this was removed at the same time due to structural changes in freight traffic.

At the time , and correct me if wrong - there was just a patchy Lincoln - Crewe DMU service.

The electrification was a quick job done to facilitate the SRA strategy to ensure the blockade strategy to try and get PUG 2 done quicker. (Crewe - Cheadle Hulme via Wilmslow, and via the Stoke route) - handy for other electric diversions post this.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
26,694
Location
Nottingham
The passenger service terminated at Crewe (and still does) so it's very unlikely one will be departing when another one is due to arrive.
 

AndrewE

Established Member
Joined
9 Nov 2015
Messages
5,983
It was singled as part of the Crewe remodelling scheme in 1985, long before the line was electrified.
No, it was singled to make building the A500 westward extension (new B5472 bridge) cheaper
Before singling - there was a connection off the Kidsgrove line under the WCML into Gresty Lane Yard , this was removed at the same time due to structural changes in freight traffic.
It was removed at the time of the Crewe remodelling, I suspect that (like the S chord at Nuneaton) it could have been quite useful if it had been retained.
At the time , and correct me if wrong - there was just a patchy Lincoln - Crewe DMU service.

The electrification was a quick job done to facilitate the SRA strategy to ensure the blockade strategy to try and get PUG 2 done quicker. (Crewe - Cheadle Hulme via Wilmslow, and via the Stoke route) - handy for other electric diversions post this.
but a full hourly Derby to Crewe service.
The passenger service terminated at Crewe (and still does) so it's very unlikely one will be departing when another one is due to arrive.
Now there are 2 services so there is definitely a regular conflict when one is running late (EM trains usually.) Plus test trains and other traffic... singleing Crewe to Barthomly junction has proved to be a disaster (apart from for the bean-counters.) Thank goodness that (we have been told here) that the first new bridge SE of Crewe has been built with passive provision for redoubling.
 

norbitonflyer

Established Member
Joined
24 Mar 2020
Messages
3,857
Location
SW London
but a full hourly Derby to Crewe service.
The Lincoln - Derby service was also hourly, and as I recall most, if not all, ran through to Crewe. At 100 miles in 3 hr 45 it was a long slog, but at least the extension to Crewe got us Cross Country class 120s instead of the rattly 104s we had when they only ran to Derby.
(Mind you, the view through the cab of a 104 was far superior - 104s probably had the largest, and 120s the smallest, windscreens of any 1st gen DMUs)
 

AndrewE

Established Member
Joined
9 Nov 2015
Messages
5,983
"No"?
I only wrote when it was singled, not why it was singled.
My memory is that it was singled for the A500 extension (late '80s?) but the Crewe remodelling was 1985. I particularly remember this singling because I am local and it was yet another example of rail's future being compromised to allow a short-term reduction in the cost of a road improvement.

(On reflection, the cause might have been the bridge on "Main Road" to Weston, part of the same road scheme, which was rebuilt cheaper to force the singled track.)
 

Railsigns

Established Member
Joined
15 Feb 2010
Messages
2,753
My memory is that it was singled for the A500 extension (late '80s?) but the Crewe remodelling was 1985.
The line was singled in conjunction with the Crewe remodelling in July 1985, no earlier and no later.
 

AndrewE

Established Member
Joined
9 Nov 2015
Messages
5,983
OK, but why? What gain did the railway get (apart from a shortish bit of single line, extra points at each end and potential congestion on the approach to a major junction?)

The perception round here was definitely that the cheaper road bridge was what drove the singling. The new (more recent) "rusty" bridge has provision for re-doubling, can the track under the Weston village access road bridge be doubled again?
 

Railsigns

Established Member
Joined
15 Feb 2010
Messages
2,753
I understood that it was singled to help the business case for the Crewe remodelling (lower maintenance costs, and no need for a crossover to access the ordnance sidings).
 

AndrewE

Established Member
Joined
9 Nov 2015
Messages
5,983
I understood that it was singled to help the business case for the Crewe remodelling (lower maintenance costs, and no need for a crossover to access the ordnance sidings).
except that ROF Radway Green is several miles beyond the end of the single-track section (and hasn't had a siding for decades), so completely irrelevant.
Screenshot 2023-12-16 at 23-11-38 TRAKSY.UK.png
 

Railsigns

Established Member
Joined
15 Feb 2010
Messages
2,753
except that ROF Radway Green is several miles beyond the end of the single-track section, so irrelevant.
The connection into the sidings was less than one mile from the end of the single line. Regardless of the distance, a crossover was avoided.
 

nw1

Established Member
Joined
9 Aug 2013
Messages
8,361
It was singled as part of the Crewe remodelling scheme in 1985, long before the line was electrified.

Alton was another line which was I believe singled at the same time.

Astonishing short-termism; did people not think demand might come back in the future?
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
17,657
Alton was another line which was I believe singled at the same time.

Astonishing short-termism; did people not think demand might come back in the future?
At the time, probably not. We are 40 years since the decsion was made.
 

nw1

Established Member
Joined
9 Aug 2013
Messages
8,361
At the time, probably not. We are 40 years since the decsion was made.

Except that presumably the demand probably came back just 10-15 years after the singlings, AFAIK it was the late 90s that demand started growing significantly following the early 90s recession.

Also, as a point of principle, destructive and hard-to-reverse short-termist decisions, which only consider the immediate situation rather than that of the medium- and long-term, are IMO rarely a particularly good idea.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
17,657
Except that presumably the demand probably came back just 10-15 years after the singlings, AFAIK it was the late 90s that demand started growing significantly following the early 90s recession.

Also, as a point of principle, destructive and hard-to-reverse short-termist decisions, which only consider the immediate situation rather than that of the medium- and long-term, are IMO rarely a particularly good idea.
Unless there are plans to increase the service along there, its not causing massive problems.
 

Helvellyn

Established Member
Joined
28 Aug 2009
Messages
2,241
DfT have form here - given in its various historic guises it would have had to sign-off large scale BR schemes I can hardly see it allowing major re-signalling schemes keeping either massive excess capacity ot passive provision for expansion if that added to the capital outlay at the time.

When I talk about form there are many road schemes where bridges were built for a single carriageway ruling out future dualling. When the M5 was widened between Birmingham and Worcester in the 1990s I am surprised they actually built all the overbridges with such future-proofing!
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
17,657
DfT have form here - given in its various historic guises it would have had to sign-off large scale BR schemes I can hardly see it allowing major re-signalling schemes keeping either massive excess capacity ot passive provision for expansion if that added to the capital outlay at the time.

When I talk about form there are many road schemes where bridges were built for a single carriageway ruling out future dualling. When the M5 was widened between Birmingham and Worcester in the 1990s I am surprised they actually built all the overbridges with such future-proofing!
I think that was a unexpected outcome as the M5 was widened on one side only and the road shifted to one side, so the bridges are wider on one side? It wasn't a conventional widening where both sides are done such as the M40 between 4 and 5.
 

furnessvale

Established Member
Joined
14 Jul 2015
Messages
4,740
Unless there are plans to increase the service along there, its not causing massive problems.
The old chicken and egg situation. How can there ever be plans to increase the service along ANY line when a new restricted capacity has been built into it?
 

John R

Established Member
Joined
1 Jul 2013
Messages
4,558
I think many people have forgotten how few services there were on many lines back in the late 70s or early 80s. The Filton dequadrification in 1984 seems absurd now until you realise that there were often just two trains an hour in each direction between Narroways Jn and Filton.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
17,657
The old chicken and egg situation. How can there ever be plans to increase the service along ANY line when a new restricted capacity has been built into it?
Because if an uplift in service is deemed strategic, the cost of putting it back in would be factored in.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,111
Location
Leeds
When I talk about form there are many road schemes where bridges were built for a single carriageway ruling out future dualling. When the M5 was widened between Birmingham and Worcester in the 1990s I am surprised they actually built all the overbridges with such future-proofing!
The M5 bridges were not future-proofed. The widening was by a mixture of techniques along the length of the scheme, mostly asymmetrical as The Planner says, involving replacing most of the bridges.

At J4, for example, the treatment was different. The original bridges can still be seen carrying the roundabout. They originally accommodated two lanes and hard shoulder each way underneath, but now there are three lanes with the hard shoulder omitted inside the junction.

Around the road network there are places where future proofing was provided - some where it was later used and some where it never has been. Some where later developments were incompatible with the original idea of the future proofing.
 

nw1

Established Member
Joined
9 Aug 2013
Messages
8,361
Because if an uplift in service is deemed strategic, the cost of putting it back in would be factored in.

Even still, it seems better just to leave it in place rather than lifting a track and putting it back later, which to me seems incredibly wasteful.
 

30907

Veteran Member
Joined
30 Sep 2012
Messages
20,613
Location
Airedale
Even still, it seems better just to leave it in place rather than lifting a track and putting it back later, which to me seems incredibly wasteful.
You do, of course, have to maintain it if it is to be used :)
I think many people have forgotten how few services there were on many lines back in the late 70s or early 80s. The Filton dequadrification in 1984 seems absurd now until you realise that there were often just two trains an hour in each direction between Narroways Jn and Filton.
And there are 2tph over the section of track we are discussion, against a capacity of at least 5tph.
 

AndrewE

Established Member
Joined
9 Nov 2015
Messages
5,983
And there are 2tph over the section of track we are discussion, against a capacity of at least 5tph.
If you are still on Crewe (rather than Alton) there are 2 in each direction per hour, plus occasional freight, ECS and test train etc.
Delays on any one of the single line services has a serious knock-on effect on the other services.
 

HurdyGurdy

Member
Joined
30 Aug 2023
Messages
312
Location
Bulbourne
Even still, it seems better just to leave it in place rather than lifting a track and putting it back later, which to me seems incredibly wasteful.
To expand on what @30907 has already said, leaving the track in place would not have been a zero cost, or even the minimal cost option. The expense of removing the track would easily have been exceeded by the cost of continuing to manage, monitor and maintain it. Crewe remodelling, like almost every resignalling or remodelling scheme I was involved with during the 1980's and into the 90's, took advantage of whatever rationalisations were possible to achieve the lowest overall infrastructure costs. From BR's perspective at the time, it was wasteful to retain, maintain and renew assets which weren't really required and showed no prospect of being required in the foreseeable future. Occasionally you could make out a costed case for a strategic retention. If there had been a realistic case for retaining both tracks between Crewe and Alsager, I'm sure it would have been made.

Delays on any one of the single line services has a serious knock-on effect on the other services.
I can think of many other rationalisations, at Crewe alone, where that same case can be made. And you could make the same observation at every double junction that was replaced with single leads. But what are the respective costs? Of the delay minutes incurred versus either that of reinstating the double track now, or of having retained, maintained and potentially renewed it since 1985.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
17,657
If you are still on Crewe (rather than Alton) there are 2 in each direction per hour, plus occasional freight, ECS and test train etc.
Delays on any one of the single line services has a serious knock-on effect on the other services.
Its not serious at all. Its a 3 minute section on the single line.
 
Status
Not open for further replies.

Top